Dale Construction Co. v. United States, Seaboard Surety Co.

168 Ct. Cl. 692, 1964 U.S. Ct. Cl. LEXIS 184, 1964 WL 8611
CourtUnited States Court of Claims
DecidedDecember 11, 1964
DocketNo. 134-57
StatusPublished
Cited by85 cases

This text of 168 Ct. Cl. 692 (Dale Construction Co. v. United States, Seaboard Surety Co.) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dale Construction Co. v. United States, Seaboard Surety Co., 168 Ct. Cl. 692, 1964 U.S. Ct. Cl. LEXIS 184, 1964 WL 8611 (cc 1964).

Opinion

Per Curiam :

This case was referred pursuant to Rule 45 (since April 1, 1964, Rule 57) to Trial Commissioner Herbert N. Maletz with directions to make findings of fact and recommendation for conclusion of law. The Commissioner has done so in an opinion 'and report filed December 10,1963. Exceptions to the Commissioner’s findings were taken by the parties, briefs were filed and the case was submitted to the court on oral argument of counsel. Since the court is in agreement with the opinion, findings and recommendation of the Trial Commissioner, as hereinafter set forth, it hereby adopts the same, with correction of inadvertent minor errors, as the basis for its judgment in this case. Therefore, plaintiff is entitled to recover of and from the United States in the sum of $71,241.33 and the defendant, United States, is entitled to recover on its counterclaim from the Seaboard Surety Company, intervenor, in the sum of $13,145.37.

OPINION OF COMMISSIONER

This is a suit for damages for an alleged breach of contract by the Army in terminating a contract for default. The principal issue is whether the termination was justified or not. An unusual feature of the case is the Government’s challenge of an administrative determination by the Armed Services Board of Contract Appeals on behalf of the Secretary of the Army that the alleged grounds asserted by the contracting officer for the default termination were not supported by the evidence of record. The Government maintains (1) that the administrative findings are devoid of support in the record, and (2) that in any event, since the ultimate issue in the case is one of law, i.e., a breach of contract, the determination, though on a question of fact, is not final or conclusive.

Plaintiff also seeks damages for various delays allegedly caused by the Government during performance of the Army contract and reimbursement for increased costs resulting from underground obstructions, etc. It further contends [697]*697that wrongful termination of the Army contract was responsible for its default on a Navy contract and that the latter default was, therefore, due to causes beyond its control and without its fault and should be treated as one for the convenience of the Government.

In early June 1950, plaintiff, Dale Construction Co. (Dale), submitted the low bid on a bid invitation issued by the Army which called for replacement of a deteriorated 16" cast-iron high service water main at the Boston, Massachusetts Army Base and for installing in its place an estimated quantity of 6,794 linear feet of new water pipe, consisting of 2,080 feet of 16" diameter cast-iron pipe, 3,884 feet of 16" cement-asbestos pipe, and 880 feet of 12" cement-asbestos pipe. Dale’s bid was in the amount of $164,400, which was an estimate since payment was to be made on the number of feet of pipe actually installed. When bids were opened, Dale discovered that its proposed price was some $75,000 less than the next lowest one. It then sought to withdraw its bid on the ground that the disparity indicated a mistake in. computation; however, it rescinded the attempted withdrawal and executed a contract with the Army on June 27, 1950, after receiving assurances from the contracting officer and the post engineer that it would not be required to do anything unnecessarily expensive or unreasonable and that the Army would assist it and make the work easier. As prescribed by the contract, the contractor furnished performance and payment bonds in the amount of $164,000 issued by the Seaboard Surety Company.

The contract required operations to begin on July 17,1950, and to be completed by January 12, 1951, but difficulties in obtaining pipe and other materials as a result of the Korean hostilities, delayed the start until October 24, 1950, when Dale proceeded with a section of the cement-asbestos replacement line along Dry Dock Avenue1 which is located on the adjacent South Boston Navy Yard Annex.

[698]*698 Claim for Damages in Connection With Failure of City of Boston To Turn Off Water Supply

At the beginning of the job the post engineer had issued instructions to the contractor that the valves on the Army-Base were not to be turned off or on unless performed and/or ordered by his office. In accordance with these instructions Dale, on October 25 (the day after it started work on the contract), notified the post engineer that it needed the water shut off in a specified locality so that it could remove the old pipe. The day after tills an employee of the post engineer instructed the City of Boston’s- Water Department to shut, off the water supply to the locality in question. On the following day a representative of the contractor checked with the post engineer’s office and was assured that the water supply had been turned off by the City. In view of this assurance, Dale’s work force started to crack the old pipe preparatory to taking it out of the trench and replacing it with the new cement-asbestos pipe. But unbeknownst either to the contractor or the post engineer, the water supply had not, in fact, been turned off by the City. As a consequence, a large amount of water began gushing out of the cracked pipe and eventually filled the trench excavation and spilled over to an adjoining area. An emergency crew from the City Water Department was called to the site and found that the department had turned off the wrong valve; it also found that the proper valve was imbedded in asphalt in the street and was, therefore, not visible. In any event, Dale found it necessary to undertake rather extensive pumping and dewatering operations; also it was delayed in its contract operations for some 5 days. Plaintiff filed a claim with the contracting officer who denied it and expressed the opinion that it should be submitted to the City. Dale’s appeal to the ASBCA was dismissed on the ground that it was untimely.

It is, of course, settled that absent fault or negligence or an unqualified warranty on the part of its representátives, the Government is not liable for damages resulting from the action of third parties. United States v. Foley, 329 U.S. 64 (1946); Ozark Dam Constructors v. United States, 153 Ct. Cl. 120, 129, 288 F. 2d 913, 918 (1961); Ben C. Cerwich v. [699]*699United States, 152 Ct. Cl. 69, 77, 285 F. 2d 432, 436 (1961); George A. Fuller Co. v. United States, 108 Ct. Cl. 70, 101, 69 F. Supp. 409, 415 (1947); Standard Accident Insurance Co. v. United States, 102 Ct. Cl. 770, 790 (1945), cert den. 325 U.S. 870. It is in this context that the record clearly establishes that the post engineer was not at fault in this incident; hence the Government may be held liable in damages only if the circumstances show that it extended a warranty to the contractor which was breached. In essence a -warranty is an assurance by one party to an agreement of the existence of a fact upon which the other party may rely; it is intended precisely to relieve the promisee of any duty to ascertain the facts for himself. Thus, a warranty amounts to a promise to indemnify the promisee for any loss if the fact warranted proves untrue. Metropolitan Coal Co. v. Howard, 155 F. 2d 780, 784 (2d Cir. 1946). Cf., The Fred Smartley, Jr., 108 F. 2d 603, 606 (4th Cir. 1950); Pennsylvania Railroad Co. v. McAllister Brothers, 137 F. Supp. 788, 794 (SDNY 1956). The facts here appear to fall squarely within this concept.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GSI Pacific, Inc.
Armed Services Board of Contract Appeals, 2025
David Boland, Inc.
Armed Services Board of Contract Appeals, 2024
Omran, Inc.
Armed Services Board of Contract Appeals, 2024
Amber Resources Co. v. United States
68 Fed. Cl. 535 (Federal Claims, 2005)
Dodson Livestock Co. v. United States
61 Fed. Cl. 480 (Federal Claims, 2004)
AR Sales Co. v. United States
49 Fed. Cl. 621 (Federal Claims, 2001)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,379 (Federal Claims, 1998)
Sergent Mechanical Systems, Inc. v. United States
40 Cont. Cas. Fed. 76,860 (Federal Claims, 1995)
Ralph L. Jones Co. v. United States
33 Fed. Cl. 327 (Federal Claims, 1995)
Walter Dawgie Ski Corp. v. United States
39 Cont. Cas. Fed. 76,583 (Federal Claims, 1993)
Commercial Contractors, Inc. v. United States
39 Cont. Cas. Fed. 76,582 (Federal Claims, 1993)
Principal Mutual Life Insurance v. United States
29 Fed. Cl. 157 (Federal Claims, 1993)
Clay Bernard Systems International, Ltd. v. United States
37 Cont. Cas. Fed. 76,067 (Court of Claims, 1991)
Troise v. United States
36 Cont. Cas. Fed. 75,904 (Court of Claims, 1990)
Greg Stout Logging v. The United States
892 F.2d 1051 (Federal Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
168 Ct. Cl. 692, 1964 U.S. Ct. Cl. LEXIS 184, 1964 WL 8611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dale-construction-co-v-united-states-seaboard-surety-co-cc-1964.