Oman-Fischbach International (Jv) v. Robert Pirie, Secretary of the Navy

276 F.3d 1380, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20437, 2002 U.S. App. LEXIS 768, 2002 WL 63363
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 18, 2002
Docket01-1075
StatusPublished
Cited by27 cases

This text of 276 F.3d 1380 (Oman-Fischbach International (Jv) v. Robert Pirie, Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oman-Fischbach International (Jv) v. Robert Pirie, Secretary of the Navy, 276 F.3d 1380, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20437, 2002 U.S. App. LEXIS 768, 2002 WL 63363 (Fed. Cir. 2002).

Opinion

*1382 MAYER, Chief Judge.

Oman-Fischbach International appeals the decisions of the Armed Services Board of Contract Appeals, ASBCA Nos. 41474 (May 15, 1991) and 44195 (July 12, 2000), denying its application for an equitable adjustment for additional costs incurred under its contract with the United States Navy. Because the board properly interpreted the contract, we affirm.

Background

The United States Navy, Atlantic Division, Naval Facilities Engineering Command awarded Oman a firm fixed-price contract for the construction of fuel tank facilities at Lajes Air Base, Terceira Island, Azores. Prior to bidding, an Oman representative attended a pre-bid site visit on Terceira Island, as suggested by the Navy. During the site visit all prospective bidders were taken on a bus tour that included stops at the location of the tank farm where construction was to take place and other remote locations on the Lajes Base. The bus tour did not travel to all of the waste disposal sites designated in the contract.

The contract required Oman to haul rubbish and debris resulting from its construction work to a base waste disposal site, and required compliance with disposal site regulations. Specification section 02200, paragraph 3.5.3.1 of the contract pertinent to these requirements states:

Except for soil impregnated with lead, the Contracting Officer shall direct the Contractor to dispose of waste materials to one of the following sites indicated on drawing C-2:
1) North end of abandoned] runway 29
2) North west end of active runway 34
3)South of the south tank farm, in the lowland (marsh) area.
Minimal grading and leveling shall be preformed [sic] at each site, as directed by the Contracting Officer.

Oman began work in 1985, and until August of 1987 it was able to use either the waste disposal site south of the south tank farm or other locations not delineated in the contract that were advantageous in both time and cost. In September of 1987, however, these waste sites had reached full capacity and Oman informed the Navy that it would begin using the disposal site at the north end of abandoned runway 29. On the first scheduled day of use, the disposal site at runway 29 was inaccessible because the Portuguese Armed Forces had locked the gate that allowed access to the disposal site through the Lajes Base. The contracting officer then instructed Oman to use the disposal site at the northwest end of active runway 34 via a route around the Lajes Base.

As a result of using the route around the Lajes Base, Oman incurred increased waste transportation costs. It submitted a price proposal for an equitable adjustment in the amount of $897,500. Through a series of reports, the Defense Contract Audit Agency questioned $431,185 of the requested equitable adjustment. The Navy then informed Oman that its price proposal was not in accordance with the Contract Disputes Act because it did not: (1) refer to the proposal as a claim; (2) request a final decision; and (3) reference the Disputes Clause of the contract. Oman filed a notice of appeal based upon the “deemed denial” of its price proposal. The board dismissed this appeal, ASBCA No. 41474 (May 15, 1991), and the Navy subsequently issued bilateral Modification P00052, to settle a subcontractor’s claim *1383 and unilateral Modification P00053, in the amount of $215,271.20, to compensate Oman. Oman resubmitted its request for an equitable adjustment in the amount of $531,907 (reflecting the adjustment for the amount awarded in Modification P00053). The contracting officer issued a final decision denying Oman’s claim but reaffirmed the amount awarded in Modification P00053. Oman appealed the contracting officer’s decision to the board.

The board upheld the contracting officer’s decision that Oman was not entitled to an equitable adjustment other than what was awarded in Modification P00053. It held that Oman failed to show that the Navy had affirmatively assumed, by implicit or explicit warranty, the risk of increased costs due to a sovereign act of a government not a party to the contract.

Discussion

We will not disturb the factual findings of the board unless they are fraudulent, arbitrary, capricious, so grossly erroneous as to necessarily imply bad faith, or unsupported by substantial evidence. 41 U.S.C. § 609(b) (1994); McClure Elec. Constructors, Inc. v. Dalton, 132 F.3d 709, 710 (Fed.Cir.1997). On questions of law, this court reviews the board’s decisions de novo. 41 U.S.C. § 609(b) (1994); W. Coast Gen. Corp. v. Dalton, 39 F.3d 312, 314 (Fed.Cir.1994). Notwithstanding this lack of deference on questions of law, we accord the board’s legal determinations careful consideration because of its experience in construing government contracts. See Ingalls Shipbuilding, Inc. v. Dalton, 119 F.3d 972, 975 (Fed.Cir.1997); W. Coast, 39 F.3d at 314.

Oman challenges the board’s conclusion that there was no warranty of access to the haul route through the Lajes base. In support of its position, Oman argues that paragraph 3.5.3.1 of the contract was silent as to the haul route for access to the waste disposal sites at the north end of abandoned runway 29 and at the northwest end of active runway 34. It further contends that this contractual silence coupled with the government’s representations during the pre-bid site visit created an implied warranty of access through the Lajes Base to the waste disposal sites at runways 29 and 34. Oman concedes that the contracting officer had sole discretion under the contract to determine which of the three waste disposal sites were to be used by it; however, because of the warranty of access created by the government, the contracting officer could not order a haul route other than the one through the Lajes Base.

The Navy responds that no implied warranty was created because the express language of the contract carries no clear and direct affirmative promise from which a warranty or guarantee can be inferred. The Navy points out that the contract does not identify the particular haul route to be used in getting to the contract’s identified waste disposal sites. Moreover, the “Site Investigation and Conditions Affecting The Work,” 48 C.F.R. § 52.236-3 (April 1984), and “Conditions Affecting The Work” clauses, expressly placed the burden on Oman to ascertain the nature and location of the work. The Navy also argues that Oman improperly seeks to rely upon parol evidence to create a contractual warranty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mutakaber v. Secretary of State
Federal Circuit, 2025
GSI Pacific, Inc.
Armed Services Board of Contract Appeals, 2025
David Boland, Inc.
Armed Services Board of Contract Appeals, 2024
Targe Logistic Services Company
Armed Services Board of Contract Appeals, 2024
Hahnenkamm, LLC v. United States
104 F.4th 1333 (Federal Circuit, 2024)
Omran, Inc.
Armed Services Board of Contract Appeals, 2024
ACC Construction Co., Inc.
Armed Services Board of Contract Appeals, 2022
AISG, Inc.
Armed Services Board of Contract Appeals, 2020
Hejran Hejrat Co. Ltd v. US Army Corps of Engineers
930 F.3d 1354 (Federal Circuit, 2019)
ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2019
ECC International, LLC
Armed Services Board of Contract Appeals, 2018
Zafer Construction Company
Armed Services Board of Contract Appeals, 2017
IAP Worldwide Services, Inc.
Armed Services Board of Contract Appeals, 2017
Contrack International, Inc.
Armed Services Board of Contract Appeals, 2016
Northrop Grumman Computing Systems, Inc. v. United States
93 Fed. Cl. 144 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
276 F.3d 1380, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20437, 2002 U.S. App. LEXIS 768, 2002 WL 63363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oman-fischbach-international-jv-v-robert-pirie-secretary-of-the-navy-cafc-2002.