Ecc International Constructors v. Secretary of the Army

CourtCourt of Appeals for the Federal Circuit
DecidedJune 5, 2020
Docket19-1619
StatusUnpublished

This text of Ecc International Constructors v. Secretary of the Army (Ecc International Constructors v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ecc International Constructors v. Secretary of the Army, (Fed. Cir. 2020).

Opinion

Case: 19-1619 Document: 56 Page: 1 Filed: 06/05/2020

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

ECC INTERNATIONAL CONSTRUCTORS, LLC, Appellant

v.

SECRETARY OF THE ARMY, Appellee ______________________

2019-1619 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in Nos. 59138, 59586, 59643, 60284, Administrative Judge Owen C. Wilson, Administrative Judge Richard Shackleford, Administrative Judge Timothy Paul McIl- mail. ______________________

Decided: June 5, 2020 ______________________

ROY DALE HOLMES, Cohen Seglias Pallas Greenhall & Furman, Philadelphia, PA, for appellant. Also represented by MICHAEL H. PAYNE.

JESSICA R. TOPLIN, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, for appellee. Also represented by JOSEPH H. Case: 19-1619 Document: 56 Page: 2 Filed: 06/05/2020

2 ECC INT’L CONSTRUCTORS v. SECRETARY OF THE ARMY

HUNT, ROBERT EDWARD KIRSCHMAN, JR., PATRICIA M. MCCARTHY. ______________________ Before LOURIE, LINN, and WALLACH, Circuit Judges. LINN, Circuit Judge ECC International Construction, LLC (“ECC”), the holder of Contract No. W912ER-10-C-0054 (“contract”) awarded under Solicitation No. W912ER-10-R-0062 (“solic- itation”) for the design and construction of a Special Oper- ations Facility Joint Operations Center (“JOC”), appeals the decision of the Board of Contract Appeals (“Board”) granting summary judgment in favor of the Army and denying ECC entitlement to additional compensation for costs and delays incurred in meeting heightened “inside the wire” security procedures imposed by the operator of a nearby International Security Assistance Force military base (“Base”) after it expanded the perimeter of the Base to envelop the JOC construction site. See Appeals of ECC Int’l Constructors, LLC, ASBCA No. 59138, 19-1 BCA ¶ 37252, 2019 WL 495998 (Jan. 24, 2019). Because the Board cor- rectly concluded that the change in security procedures was not a constructive change in the contract for which ECC is entitled to compensation, we affirm. I It is undisputed that the operator of the Base is a third party and that the Base expansion was the act of that third party and not the government. As the Board recognized, the government is not liable under contract for increased costs caused by acts of a third party absent the breach of an unqualified warranty that would amount to a construc- tive change in the agreed terms. Such liability exists only where “the parties in unmistakable terms agreed to shift the risk of increased costs [to the government].” Oman- Fischbach Int’l (JV) v. Pirie, 276 F.3d 1380, 1385 (Fed. Cir. 2002). Case: 19-1619 Document: 56 Page: 3 Filed: 06/05/2020

ECC INT’L CONSTRUCTORS v. SECRETARY OF THE ARMY 3

Paragraph 1.2 of the contract states that the JOC “will be sited at Mazar-e-Sharif, Afghanistan, on a dedicated area located outside the perimeter fencing of the existing base.” J.A. 70. This is confirmed by Solicitation Drawing C-1. Paragraph 1.2 merely describes the location of the building site. It does not warrant the security procedures that will apply to the site. Paragraph 1.2 also does not limit the reading of ¶ Y of the contract. Paragraph Y explicitly provides that “Base security [the operator of the Base] maintains the ultimate authority for establishing, monitoring, and enforcing secu- rity requirements for the work site,” and that “[t]he Con- tractor shall be responsible for compliance with all Base security requirements.” J.A. 215. ECC argues that “work site” in this provision only applies to work sites within the Base. That limitation, however, nowhere appears in the contract. Moreover, limiting ¶ Y in that way would render it superfluous in light of special clause SC 1.53 of the con- tract, which states that “Base Security maintains the ulti- mate authority for establishing, monitoring, and enforcing security requirements . . . on the Base.” J.A. 74; see also Appellant’s Reply Br. at 6–7 (arguing that SC 1.53 applies to on-Base sites). Paragraph X of the contract obligates the contractor to “erect a temporary security fence around the construction limits of the project” and specifies that “[a]ccess to this se- cure area shall be controlled by the Contractor’s forces.” That paragraph is not inconsistent with the requirement of paragraph Y that Base security procedures be followed where and when necessary. The contractor’s obligation to control access to the site—either inside or outside the wire—does not grant the contractor the right to determine the security standards or procedures that might apply over the course of the contract. Nothing in that paragraph cre- ates an implied or express warranty that the work site would not be subject to Base security procedures until ECC decided it would be so. Case: 19-1619 Document: 56 Page: 4 Filed: 06/05/2020

4 ECC INT’L CONSTRUCTORS v. SECRETARY OF THE ARMY

Further, requiring that the contractor “shall sequence construction to complete the majority of the work outside the base perimeter fence before cutting the base perimeter fences” also does not warrant that the Base security proce- dures would not apply to the work site, or that the Base perimeter would not expand. It merely governs the Con- tractor’s sequencing of its work. This provision is wholly consistent with ¶ Y’s vesting of ultimate authority for se- curity procedures with the operator of the Base. The Board did not err in finding no meaningful distinc- tion between this case and Oman-Fischbach. In Oman- Fischbach, the mere fact that the contract depicted several routes to a disposal site on a map did not explicitly assure the contractor of access to any particular route. Oman- Fischbach, 276 F.3d at 1384–85. Here, ECC’s contractual responsibility to enforce security procedures on the work site did not unmistakably give it the right to determine the particular security procedures applicable thereto or the timing of when the work site might be brought within the Base perimeter fence and subject to heightened security procedures. This case, like Oman-Fischbach, is distin- guishable from D&L Construction, where “[t]he contract provided that defendant would make available to plaintiff existing off-site improvements, such as existing streets,” and where the contracting officer sent contractor a letter on the same day that the contract was executed, indicating that the United States “will provide suitable access and means of ingress and egress to and from the subject pro- ject.” D&L Const. Co. & Assoc. v. United States, 402 F.3d 990, 997 (Ct. Cl. 1968). This case is also distinguishable from J.E. McAmis, where the contract included drawings showing haul routes, one of which explicitly required the use of designated roads and stated that “all designated ac- cess roads will be maintained for permanent access.” In re J.E. McAmis, Inc., ASBCA No. 54455, 10-2 B.C.A. (CCH) ¶ 34607, 2010 WL 4822734 (Nov. 18, 2010). There are no similar provisions in the contract at issue here. Case: 19-1619 Document: 56 Page: 5 Filed: 06/05/2020

ECC INT’L CONSTRUCTORS v. SECRETARY OF THE ARMY 5

II In a series of chain cites, ECC argues that parole evi- dence in the form of the parties’ contemporaneous commu- nications reflects the parties’ understanding that the government warranted that the Base safety procedures would not apply to the JOC site. The Board did not err in not considering these communications. First, as explained above, the contract unambiguously stated that the opera- tor of the Base maintained ultimate authority for security. See Banknote Corp. of Am. v. United States, 365 F.3d 1345, 1353 (Fed. Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Society of Lloyd's v. Reinhart
402 F.3d 982 (Tenth Circuit, 2005)
Max Drill, Inc. v. The United States
427 F.2d 1233 (Court of Claims, 1970)
Macke Co. v. United States
467 F.2d 1323 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Ecc International Constructors v. Secretary of the Army, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecc-international-constructors-v-secretary-of-the-army-cafc-2020.