Macke Co. v. United States

467 F.2d 1323, 199 Ct. Cl. 552, 1972 U.S. Ct. Cl. LEXIS 127
CourtUnited States Court of Claims
DecidedOctober 13, 1972
DocketNo. 420-70
StatusPublished
Cited by42 cases

This text of 467 F.2d 1323 (Macke Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Macke Co. v. United States, 467 F.2d 1323, 199 Ct. Cl. 552, 1972 U.S. Ct. Cl. LEXIS 127 (cc 1972).

Opinion

Davis, Judge,

delivered tlie opinion of the court:

This is a dispute arising out of a 1964 contract with the Exchange Council, a non-appropriated fund activity of the Kennedy Space Center (of the National Aeronautics and Space Administration), under which the plaintiff Macke Company obtained the right to supply extensive and exclusive food services for employees (and others) at that location. This concession-type arrangement did not require the Council to pay Macke; rather, the latter agreed to perform in the expectation of making a profit and promised to pay the Council approximately five percent of the total receipts from its operations at the Center. However, the venture did not prove profitable (as the parties had anticipated) and in this suit plaintiff claims recoupment of losses, price relief, or other adjustments, from June 1965 until the termination of the contract in the spring of 196Y.1

The gist of the complaint is that, when it became clear that the contractor continued to suffer unreasonable losses not of its own making, the Exchange Council failed to ¡allow cafeteria and food prices to be raised, or to make sufficient reduction in the payments to be made by Macke to the NASA Council, so as to wipe out or alleviate these losses. For the period through June 1965, an adjustment along these lines, satisfactory to plaintiff, was made, but no similar agreement could be reached for the later time. Plaintiff then made the controversy an issue under the “all disputes” clause of the contract, the contracting officer decided adversely, and the agency’s Board of Contract Appeals upheld that determination (in the main), with one member dissenting. The board ruled that plaintiff should be paid for losses stemming from the Government’s actual fault, but not for those unexpected [556]*556losses intrinsic to the operation. 67-1 BCA ¶6156 (1967), motion for reconsideration denied, 68-1 BCA ¶7041 (1968). The case is before us, through cross-motions for summary-judgment, on that decision and tbe administrative record.

'I.

Tbe questions are largely legal, as tbe parties recognized when tbey stipulated tbe issues 'before tbe Board.2 The primary one is whether the contractor was entitled to be compensated for losses which turned out to be inherent in tbe provision of food service at tbe unique Kennedy Center under tbe special system established by tbe contract. In this inquiry, the greatest help comes, not from tbe bare text of tbe original contract, but from external indications of tbe parties’ joint understanding, contemporaneously and later, of what tbe contract imported. Tbe case is an excellent specimen of tbe truism that how the parties act -under the arrangement, before the advent of controversy, is often more revealing than tbe dry language of tbe written agreement by itself. We are, of course, entirely justified in relying on this material to discover tbe parties’ -underlying intention. See, e.g., Topliff v. Topliff, 122 U.S. 121, 131 (1887); Firestone Tire & Rubber Co. v. United States, 195 Ct. Cl. 21, 30, 444 F. 2d 547, 551 (1971); Franklin Co. v. United States, 180 Ct. Cl. 666, 670, 381 F. 2d 416, 418 (1967); Williamsburg Drapery Co. v. [557]*557United Mates, 177 Ct. Cl. 776, 786, 369 F. 2d 729, 735 (1966); Universal Match, Corp. v. United States, 161 Ct. Cl. 418, 422 n.4 (1963).

As initially framed, the contract did not deal directly with the problem of whether Macke was to bear the full risk of unreasonable losses inherent in this special undertaking at an exceptional installation. There was nothing explicit on that point in the contract form. But the terms of the agreement did make clear that food prices were not irrevocably fixed as of the time the pact was entered into, and also that there was to be a continuing relationship between prices and plaintiff’s operating costs.

The fixing of prices, portions, and quality was to be controlled by the contracting officer, a member of the Exchange Council. Paragraph 3 says that prices charged, equipment used, and all other phases of the operation should be subject to his review and approval.3 Paragraph 9c requires the contractor to submit monthly reports to the contracting officer “as to costs of operation which may affect the maintaining of sales price at a satisfactory level.” Another provision, 8, remits approval of sales prices to the contracting officer, directing his exercise of this power by the guidelines of operating costs, on the one hand, and prevailing area prices on the other: “Although sales prices should be reasonable in relation to prevailing prices for similar service in the surrounding area, which shall be approved by the Contracting Officer and shall in no case exceed prevailing area prices, due consideration shall be given to prospective operating costs.” This provision was amplified by the contracting officer’s letter transmitting the signed contract in January 1964, admitted on both sides to be an integral part of the contract, which said that “Paragraph 8 * * * provides for change in food prices as may be required by operational costs or other conditions” and “prices, portions, and variety are subject to the approval of the Contracting Officer.”

One permissible explication of these somewhat amorphous and open-ended provisions is that the agency would be sensi[558]*558tive to the contractor’s need for adjustments to allow it to make a profit and avoid a loss. The pre-bid conference, attended generally by potential bidders, expressed exactly this understanding. Defendant’s authorized representative told those at the meeting that “You are expected to make a profit,” and promised that the contractor could negotiate with the contracting officer were no profit realized. As we have recently emphasized, such official statements can and should be taken into account in ascertaining the parties’ joint understanding. See Manloading & Management Associates, Inc. v. United States, 198 Ct. Cl. 628, 461 F. 2d 1299 (1972); Sylvania Elec. Products, Inc. v. United States, 198 Ct. Cl. 106, 458 F. 2d 994 (1972).

Apparently Macke, when it became the contractor at the beginning of 1964, expected a loss of some $55,000 for its first year, but it was anticipated that a profit would be realized overall during the life of the contract. However, disappointment soon succeeded hopeful anticipation. In the middle of July 1965, after a year-and-a-half of performance, plaintiff wrote the contracting officer complaining that its losses through June 1965 exceeded $117,000, much more than the $55,000 loss foreseen for the first year. Its request for relief included a report of operating costs and a projection of profit as of September 1965.

After confirmation of these expenses and losses through June 1965, the parties negotiated Modification #4, which reduced the commissions the plaintiff was required to pay the Exchange Council from 5.1% downward to 2.1%, until such time as $60,000 of losses had been recouped. Modification #4 contained the following recital in explanation of the parties’ supplemental agreement:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheffield Barbers, LLC
Armed Services Board of Contract Appeals, 2025
Anderson Contracting, LLC
Armed Services Board of Contract Appeals, 2024
The Public Warehousing Company
Armed Services Board of Contract Appeals, 2015
Tektel, Inc. v. United States
116 Fed. Cl. 612 (Federal Claims, 2013)
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)
Pacific Gas & Electric Co. v. United States
536 F.3d 1282 (Federal Circuit, 2008)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
Gemini Electronics, Inc. v. United States
65 Fed. Cl. 55 (Federal Claims, 2005)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Johnson Controls World Services, Inc. v. United States
48 Fed. Cl. 479 (Federal Claims, 2001)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Cray Research, Inc. v. United States
44 Fed. Cl. 327 (Federal Claims, 1999)
Fort Myer Construction Corp. v. United States
43 Cont. Cas. Fed. 77,425 (Federal Claims, 1999)
Omni Corp. v. United States
41 Fed. Cl. 585 (Federal Claims, 1998)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
467 F.2d 1323, 199 Ct. Cl. 552, 1972 U.S. Ct. Cl. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macke-co-v-united-states-cc-1972.