Bromion, Incorporated v. The United States

411 F.2d 1020, 188 Ct. Cl. 31, 1969 U.S. Ct. Cl. LEXIS 27
CourtUnited States Court of Claims
DecidedJune 20, 1969
Docket368-67
StatusPublished
Cited by16 cases

This text of 411 F.2d 1020 (Bromion, Incorporated v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bromion, Incorporated v. The United States, 411 F.2d 1020, 188 Ct. Cl. 31, 1969 U.S. Ct. Cl. LEXIS 27 (cc 1969).

Opinion

DURFEE, Judge.

On August 21, 1967, the Armed Services Board of Contract Appeals (hereinafter referred to as the Board or the ASBCA) denied an appeal from a default termination by Bromion, Inc., 67-2BCA, fl 6543, pp. 30, 399. Plaintiff is now suing under the Wunderlich Act, 41 U.S.C. §§ 321, 322, to review this decision. Both sides have moved for summary judgment.

Plaintiff was awarded a negotiated contract on April 29, 1966 for 14 electronic testers. A major component of the tester, an “automatic electric stepping switch”, was manufactured by Automatic Electric Co., the sole source of supply.

The contract called for delivery of the testers within 60 days of the award, or by June 28, 1966, at a total price of $35,406.00. In response to plaintiff’s inquiry, Automatic Electric Co. submitted a quotation on May 20th, showing delivery of the switches in approximately 90 days, which would have been well beyond the June 28th delivery date set by the contract. Plaintiff therefore corresponded with the contracting officer on May 24,1966, as follows:

The largest sub-component in the system is the automatic electric stepping switch, and since practically all of the parts in the assembly are wired to the stepping switch, it is very difficult to proceed without this switch on hand. Since the supplier of this switch indicates delivery in approximately 90 days, we feel we must request an extension to the contract in order to allow time for the receipt of supplies and the incorporation of the components into our complete test sets.
It is recommended that a 150 day extension to the contract be made in order to allow time for receipt of these supplies. This would place the final delivery date of these units on October 28. As an additional compensation, Bromion is willing to reduce the cost of the contract by .7% ($228).

The contractor’s original proposal for a price reduction was not accepted. Thus, on June 27, 1966, the contractor again offered a price reduction in exchange for a time extension, and requested that its proposed extension for 150 days be reconsidered; it also reasserted that this would bring the delivery date to October 28,1966.

On July 22, 1966, the contracting officer sent a telegram to the contractor, accepting the price reduction offered, and extending the delivery schedule to October 29, 1966. No mention was made of a 150-day extension. A supplemental agreement, Modification No. 1, was eventually entered into by the parties, which incorporated the terms of the telegram. The contractor signed the agreement on August 5, 1966, and took no exception to its wording.

The 14 switches were received by plaintiff on August 31, but because they lacked basic assemblies, they had to be returned. Proper switches were received on October 7th, and on October 18th plaintiff notified the Government that it would be unable to meet the delivery schedule. Bromion, on October 19th, requested a time extension to January 31, 1967, offering a further price reduction. On October 31, 1966, the contracting officer, having considered the latest request for a time extension, issued a notice terminating plaintiff’s contract for default.

The contracting officer’s decision was appealed to the ASBCA, which found that plaintiff’s delay was not excusable, and that Modification No. 1 reflected *1022 what the parties actually bargained for. It therefore denied plaintiff’s appeal.

Plaintiff is now claiming that the Modification embodied a mutual mistake, that it did not accurately reflect the parties’ intent, and that therefore, the Board decision was arbitrary, capricious and not supported by substantial evidence. Upon a careful examination of all the facts and circumstances surrounding the events heretofore described, we conclude that the Board’s decision was not arbitrary, or capricious, and was supported by substantial evidence. In addition, the Board’s decision is not based on any conclusion of law and thus, under the Wunderlich Act, 41 U.S.C. § 322, its findings are entitled to finality.

When plaintiff first asked for a time extension, it asked for an extension of 150 days, and stated that this would bring the delivery date to October 28. Since the contracted-for-delivery date was June 28, 150 days from then would have in actuality produced a delivery date of November 24. Thus, plaintiff claims that both parties actually intended this latter date, rather than the “mistaken” date of October 28 (or October 29, which was the date- set by the contracting officer).

The Board found that, while it was unclear as to how plaintiff arrived at the October 28 date, it was obvious that its request for a 150-day extension was derived from the 90-day delay in the deliveries from Automatic Electric Co., plus the 60 days it would take to fabricate the testers, once plaintiff had all the necessary components. It therefore found that the dominant purpose of the extension was to give the contractor 150 days within which to deliver the product. It also found that such 150-day extension from plaintiff’s May 24 request would have yielded an October 21 delivery date. Even though a correct calculation would thus have yielded a date different from October 28 (or 29) the date actually mentioned in the Modification is obviously in closer harmony with October 21 than the date for which plaintiff is arguing, i. e., November 24.

It is clear from the chronology of events that the Board’s findings are supported by substantial evidence. Plaintiff’s request for a time extension was prompted by a May 20th communication from Automatic Electric Co. which alerted plaintiff that delivery of the switches would take place in about 90 days. Thus, when plaintiff sought the extension on May 24th, the 150 days actually required should have yielded the October 21 date. When the contracting officer replied on June 22, and gave a final date of October 29, he was merely giving a date which approximated this 150-day request. In view of how this length of time was probably arrived at, there is no basis for saying that the contracting officer knew or should have known that plaintiff was seeking a November 24 date, and therefore no basis for arguing that he was only mistaken in specifying the wrong date certain. In fact, it would have been unreasonable, in light of the communications back and forth, and the events which necessitated them, for the contracting officer to have set a November 24 delivery date.

By asking this court to declare that the ASBCA decision was wrong, plaintiff is in effect asking us to reform this contract. This we cannot do, since “ [r] eformation is not a proper remedy for the enforcement of terms to which the defendant never assented; it is a remedy the purpose of which is to make a mistaken writing conform to antecedent expressions on which the parties agreed.” 3 Corbin on Contracts § 614, at p. 723 (1960). There is no evidence here that either of the parties agreed to the November 24 delivery date. In fact, the case was submitted to the ASBCA without hearing. If plaintiff had introduced any evidence as to the intent of the parties, we might have been more sympathetic to a plea for reformation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SupplyCore, Inc.
Armed Services Board of Contract Appeals, 2022
Rieschick v. United States
21 Cl. Ct. 621 (Court of Claims, 1990)
Jeppesen Sanderson, Inc. v. United States
14 Cl. Ct. 624 (Court of Claims, 1988)
Jetco, Inc. v. United States
11 Cl. Ct. 837 (Court of Claims, 1987)
Utility Contractors, Inc. v. United States
32 Cont. Cas. Fed. 73,446 (Court of Claims, 1985)
Bromley Contracting Co. v. United States
652 F.2d 70 (Court of Claims, 1981)
Spencer v. Newton
79 F.R.D. 367 (D. Massachusetts, 1978)
Fraass Surgical Mfg. Co. v. United States
571 F.2d 34 (Court of Claims, 1978)
Highway Products, Inc. v. United States
530 F.2d 911 (Court of Claims, 1976)
Burnett Electronics Lab., Inc. v. United States
479 F.2d 1329 (Court of Claims, 1973)
Dale Ingram, Inc. v. United States
475 F.2d 1177 (Court of Claims, 1973)
Sperry Rand Corp. v. United States
475 F.2d 1168 (Court of Claims, 1973)
Space Corp. v. United States
470 F.2d 536 (Court of Claims, 1972)
Macke Co. v. United States
467 F.2d 1323 (Court of Claims, 1972)
Jamsar, Inc. v. The United States
442 F.2d 930 (Court of Claims, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
411 F.2d 1020, 188 Ct. Cl. 31, 1969 U.S. Ct. Cl. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bromion-incorporated-v-the-united-states-cc-1969.