Anderson Contracting, LLC

CourtArmed Services Board of Contract Appeals
DecidedApril 17, 2024
Docket63632
StatusPublished

This text of Anderson Contracting, LLC (Anderson Contracting, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson Contracting, LLC, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Anderson Contracting, LLC ) ASBCA No. 63632 ) Under Contract No. W912P8-21-C-0043 )

APPEARANCES FOR THE APPELLANT: Christopher Solop, Esq. Lynn Patton Thompson, Esq. Biggs, Ingram & Solop, PLLC Jackson, MS

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney William G. Meiners, Esq. Engineer Trial Attorney U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGE MCLISH

Appellant Anderson Contracting, LLC (Anderson) claims it has been underpaid on a contract with the United States Army Corps of Engineers (USACE) to construct a seepage berm on the grounds of Angola State Prison in West Feliciana Parish, Louisiana. Anderson contends that USACE failed to pay it for the full amount of compacted fill material it provided to construct the berm. The contract contained an estimated amount of compacted fill and provided that Anderson would be paid the actual amount of fill it placed, measured on the basis of quantity surveys the USACE would conduct. Anderson contends that USACE’s quantity survey was not taken in accordance with the contract requirements, resulting in an understatement of the amount of compacted fill Anderson provided and a failure to pay Anderson the full amount due. USACE’s contracting officer rejected Anderson’s claims and Anderson appealed to the Board.

The parties elected to proceed under the Board’s Rule 11, which provides for resolution on the written record without an oral hearing. The parties agreed that the Board would address only entitlement at this stage.

We deny the appeal. FINDINGS OF FACT

I. The Contract

1. On July 2, 2021, the USACE issued Solicitation No. W912P821B0059 (Solicitation) for “clearing and grubbing, placement [of] compacted fill for an earthen seepage berm, fertilizing, seeding and mulching, borrow pit development of a Government furnished borrow area, maintenance of access roads and other incidental work” at Angola State Prison, located in West Feliciana Parish, Louisiana (R4, tab 4 at 8-9; Joint Stipulation of Facts (Joint Stip.) ¶ 1).

2. On August 12, 2021, Anderson was awarded Contract No. W912P812C0043 (Contract) for $1,892,020 (R4, tab 4 at 8-9, 12; Joint Stip. ¶ 3).

A. Measurement and Payment for Compacted Fill

3. Contract Line Item No. (CLIN) 0006, Embankment, Compacted Fill, estimated a quantity of 81,000 cubic yards of compacted fill, priced at $13.00/CY for a total of $1,053,000 (R4, tab 4 at 12; Joint Stip. ¶ 4).

4. Paragraph 1.3.1 of the Embankment specifications addresses how the amount of compacted fill would be measured for payment purposes:

Unless otherwise specified, compacted fill materials of any description specified in this section will be measured for payment by the cubic yard, and quantities will be determined by the average end area method. The basis for the measurement will be cross sections of the areas to be filled taken prior to clearing, grubbing, and vegetation removal operations and the theoretical design sections. Embankment not constructed to design grade and section, including allowable tolerance as indicated on the Contractor's compliance survey will not be accepted. There will be no separate measurement or payment for tolerances. Embankment quantities for payment will be determined by the government.

(R4, tab 4 at 412)

2 5. The “cross sections of the areas to be filled” were to be established by quantity surveys to be conducted by USACE. 1 As indicated in Paragraph 1.3.1, the cross-sections were to be taken “prior to clearing, grubbing, and vegetation removal operations. . . .” (Id.)

B. Clearing and Grubbing

6. The Contract contains specifications for Clearing and Grubbing, which provides at Paragraph 1.2:

No measurement will be made for clearing and grubbing. Payment will be made at the contact job price for “Clearing and Grubbing”. Price and payment shall constitute full compensation for furnishing all plant, labor, materials, and equipment; and performing all operations necessary for clearing and grubbing of the areas specified herein or indicated on the drawings, for removing and disposing of all cleared and grubbed materials, and for filling holes resulting from grubbing operations.

(R4, tab 4 at 391; Joint Stip. ¶ 5)

7. Paragraph 3.2 of the Clearing and Grubbing specifications is entitled “Clearing.” Paragraph 3.2.1 defines “clearing”:

Clearing, unless otherwise specified, shall consist of the complete removal above the ground surface of all trees, stumps, down timber snags, brush, vegetation, loose stone, abandoned structures, fencing, and similar debris. Growth standing in water in areas that are not drained in accordance with Section 31 24 00.00 12 EMBANKMENT, paragraph Drainage may be cut off so as not to protrude more than 12 inches above the existing water surfaces.

(R4, tab 4 at 392; Joint Stip. ¶ 6)

8. Two paragraphs later, under the sub-heading “Government Surveys,” Paragraph 3.2.3 provides:

1 The contract includes, by full text, FAR 52.236-16, Quantity Surveys, which provides in relevant part that the Government would perform original and final surveys and make computations based on them (R4, tab 4 at 33-34). 3 The Contractor shall clear the baseline traverse, centerline traverse, and ranges at all P.C.’s, P.l.’s, P.T.’s, 100-foot centerline stations and tie-in stations to facilitate the taking of original cross-sections by the Government. This clearing shall consist of the removal to within 6-inches of the ground surface of all trees, brush and vegetation. This clearing shall be completed in 5,000-foot increments and in advance of embankment construction by a minimum of 1,000 feet.

(R4, tab 4 at 392; Joint Stip. ¶ 7)

9. Paragraph 3.3 of the Clearing and Grubbing specification is entitled “Grubbing.” Paragraph 3.3.1 defines “grubbing”:

Grubbing shall consist of the removal of all stumps, roots, buried logs, pipes, drains, and other unsuitable matter as described in Section 31 24 00.00 12 EMBANKMENT, paragraph Materials.

(R4, tab 4 at 393; Joint Stip. ¶ 8)

10. Paragraph 3.3.2.1 provides:

Grubbing shall be performed within the limits of the embankment together with the 5-foot strips contiguous thereto. All roots and other projections over 1-1/2- inches in diameter shall be removed to the depth of 3-feet below the natural surface of the ground or surface of existing embankments and to a depth of 3-feet below the subgrade for the foundation of structures. The areas to be grubbed are those specific areas within the limits specified herein above from which trees, stumps, down timber, snags, abandoned structures, and other projections have been removed.

(R4, tab 4 at 393; Joint Stip. ¶ 9)

II. The Government Survey

11. The USACE issued a Notice to Proceed to Anderson on August 25, 2021 (R4, tab 4 at 7; Joint Stip. ¶ 10).

4 12. USACE issued a task order for surveying services to EMC, Incorporated (EMC) to perform the government survey that would provide the basis for measuring the amount of compacted fill Anderson provided when it constructed the berm, per Paragraph 1.3.1 of the Embankment specifications (R4, tab 19).

13. On October 7, 2021, the USACE conducted a Preconstruction Conference. The minutes of the conference do not refer to the timing of the government survey referenced in Paragraph 3.2.3 of the Clearing and Grubbing specifications. (R4, tab 6; Joint Stip.¶ 11) USACE did, however, direct Anderson to begin the pre-survey clearing required by Paragraph 3.2.3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Pacific Gas & Electric Co. v. United States
536 F.3d 1282 (Federal Circuit, 2008)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Max Drill, Inc. v. The United States
427 F.2d 1233 (Court of Claims, 1970)
Julius Goldman's Egg City v. The United States
697 F.2d 1051 (Federal Circuit, 1983)
P.R. Burke Corp. v. United States
277 F.3d 1346 (Federal Circuit, 2002)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Langkamp v. United States
943 F.3d 1346 (Federal Circuit, 2019)
Macke Co. v. United States
467 F.2d 1323 (Court of Claims, 1972)
H & M Moving, Inc. v. United States
499 F.2d 660 (Court of Claims, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
Anderson Contracting, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-contracting-llc-asbca-2024.