Universal Match Corp. v. United States

161 Ct. Cl. 418, 1963 U.S. Ct. Cl. LEXIS 72, 1963 WL 8568
United States Court of Claims·Decided April 5, 1963·No. No. 554-59·Published·Cited by 14 cases

Opinion

Davis, Judge,

delivered tbe opinion of the court:

This suit seeks $33,731.42 because of the termination by the defendant, for its own convenience, of a contract for the production of photoflash cartridges. Plaintiff, a St. Louis-based company, had a series of three agreements (Contracts 744, 850, 866) with the St. Louis Ordnance District of the Department of the Army to manufacture various types of these items. The only one of the contracts involved here is No. 866, entered into on June 30, 1954. It contained a standard termination-for-convenience article, obligating the defendant to pay, on such termination, for all completed supplies accepted by the Government and also for other costs incurred in the performance of the work terminated.

Because of the plaintiff’s difficulties with, and the consequent changes in, the prototype cartridge contract — No. 744, entered into a year earlier — the Government did not wish to incur costs under the new supplemental contract, No. 866, until it was sure that the items, as they might be changed in the course of performing the initial contract, could in fact be produced. Satisfactory cartridges had not yet been made under Contract 744. During the negotiations for Contract 866, plaintiff met this obstacle by writing to the defendant that it was “agreeable to a clause providing that no cost will be incurred against the pending contract [No. 866] without the prior approval of the Contracting Officer until this contract be released for production.” The Government’s notice of award referred to this letter as part of the company’s proposal which the Government accepted, and Article VIII of the formal contract provided that the contractor was not to incur any costs in preparation for production under this contract without prior written approval of the contracting officer.

Simultaneously with the negotiation of Contract 866, the parties were also considering another supplemental cartridge contract, No. 850 — not involved in the present case — which contained an identical provision for prior written approval of costs, designed to deal with the same uncertainty as to the [420] feasibility of making the end-item. This Contract 850 was wholly released for production in March 1955.

The production problems under the basic Contract 744 continued until the early part of 1956, when these difficulties were solved and the parties then began to consider production and delivery under Contract 866. Informal oral discussions led to a letter from plaintiff to the Ordnance District, dated May 22, 1956, in which the contractor requested “release of Contract 866 for material procurement and production.” The letter pointed out that there would be an interruption in schedule between Contract 744 and Contract 866 unless the latter “can be released shortly”; it was also said that aluminum prices had increased several times since the original contract date but that if Contract 866 were immediately released the plaintiff would be able to produce the cartridges at no extra cost.

In response, the contracting officer’s letter of June 27, 1956, authorized plaintiff to procure materials necessary for production of the cartridges covered by Contract 866 but also specifically said that “acquisition of materials shall be limited to the raw materials necessary for production of the cartridge in accordance with the change orders” applicable to this item in Contract 744 (which changes were to be incorporated in Contract 866) (emphasis added). The contracting officer deliberately restricted his release to raw materials in order to meet plaintiff’s complaint about the rising price of aluminum, but the company’s representative has testified that he did not notice the word “raw” in the letter.1

The Government terminated Contract 866, for its own convenience, on October 4, 1956. No deliveries had been made under it, and none of the contract items had been completed. Plaintiff’s settlement proposal, as revised, consisted of claims for (a) a large number of electric primers, finished components destined for incorporation in the end-item, and [421] (b) dies and other tooling for manufacturing the end-item. These claims were denied by the contracting officer on the ground that the primers and the tooling were not “raw materials”, which alone had been released for acquisition by the plaintiff. The Board of Contract Appeals affirmed on the same ground.

Plaintiff no longer contends that the primers and the tooling were “raw materials.” 2 The argument in this court is, first, that the parties agreed, when they negotiated Contract 866, that the contract when released for production would be released in toto; and, second, that the defendant’s letter of June 27, 1956, necessarily amounted to such a total release, despite its wording. We cannot adopt either of these propositions.3

Free access — add to your briefcase to read the full text and ask questions with AI

Universal Match Corp. v. United States, 161 Ct. Cl. 418, 1963 U.S. Ct. Cl. LEXIS 72, 1963 WL 8568 (cc 1963).

161 Ct. Cl. 418 (Universal Match Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tektel, Inc. v. United States
116 Fed. Cl. 612 (Federal Claims, 2013)
Vassar v. United States
63 Fed. Cl. 166 (Federal Claims, 2004)
Missouri Baptist Hospital v. United States
555 F.2d 290 (Court of Claims, 1977)
Macke Co. v. United States
467 F.2d 1323 (Court of Claims, 1972)
General Warehouse Two, Inc. v. The United States
389 F.2d 1016 (Court of Claims, 1967)
The Franklin Company v. The United States
381 F.2d 416 (Court of Claims, 1967)
Olin Mathieson Chemical Corp. v. United States
179 Ct. Cl. 368 (Court of Claims, 1967)
Merritt-Chapman & Scott Corp. v. United States
178 Ct. Cl. 883 (Court of Claims, 1967)
Northbridge Electronics, Inc. v. United States
175 Ct. Cl. 426 (Court of Claims, 1966)