Union Paving Co. v. United States

115 F. Supp. 179, 126 Ct. Cl. 478, 1953 U.S. Ct. Cl. LEXIS 114
CourtUnited States Court of Claims
DecidedOctober 6, 1953
DocketNo. 48241
StatusPublished
Cited by13 cases

This text of 115 F. Supp. 179 (Union Paving Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Paving Co. v. United States, 115 F. Supp. 179, 126 Ct. Cl. 478, 1953 U.S. Ct. Cl. LEXIS 114 (cc 1953).

Opinion

Littleton, Judge,

delivered the opinion of the court:

Plaintiff seeks to recover $24,400, which it alleges was wrongfully and illegally assessed against it by the defendant [481]*481as liquidated damages for its alleged delay in completing various portions of work within certain interim periods specified under a contract, whereby the plaintiff company constructed the piers and abutments for the Pit River Bridge in northern California, at the site of the Shasta Dam.

The erection of this bridge was part of a much larger project undertaken by the Bureau of Reclamation, Department of Interior, known as the Central Valley Project, in the State of California, which was to provide for the storage of water, through the construction of the Shasta Dam, for irrigation purposes and for the development of hydroelectric power. The principal structure for the entire project was the Shasta Dam and Power Plant. The erection of this dam required the relocation of parts of various railroads, highways, and public utility lines, within the area of the dam-site. As a result, in addition to the contract for the construction of the dam itself, various other contracts, including the one here in suit, were entered into by the Bureau of Reclamation, acting for the United States, and hereinafter referred to as the defendant, in order to relocate the above mentioned facilities. In its supervision of the entire project the defendant undertook to coordinate the planning, timing and progress of the work under these various contracts, and the invitation for bids, the specifications, and the contract in this case were prepared and drafted with these things in mind.

The contract in question resulted from the necessity to relocate the main line of the Southern Pacific Railroad and U. S. Highway 99, both of which when relocated would run through an area which was to be the reservoir for the storage of water accummulated by the Shasta Dam. Since the dam would store water in the reservoir to a depth of 500 feet it was necessary by the erection of a bridge to raise the roadbed of the railroad and the highway at least that height above •the ground level. The construction of this bridge which would span the Pit River was a major undertaking, and it was necessary that this work be completed in a comparatively short period of time in order to permit the erection of the Shasta Dam on schedule. The plaintiff’s contract related only to the construction of the abutments and piers for the [482]*482Pit River bridge structure. Until the relocation of the railroad was completed, operations on the dam and power plant would be restricted to construction work which could be performed without endangering the original roadbed of the railroad. . .

On September 1,1939, the defendant invited bids on a competitive basis, for the construction of the abutments and piers for what has now become known as the Pit River Bridge. The invitation for such bids stated in part as follows:

The work shall be commenced within thirty (30) calendar days after date of receipt of notice to proceed and the various parts of the work shall be completed within periods of time varying from one hundred and twenty (120) to five hundred (500) calendar days from the date of receipt of such notice, as provided in the specifications.

The specifications, drawings, and the standard form of contract, were furnished to bidders with the invitation for bids. The plaintiff, a Nevada corporation with its principal office in San Francisco, California, submitted a bid in response .to this invitation for bids and the specifications referred to, in which bid it alleges that although it agreed to complete all work within 500 days it did not agree to adhere to the interim completion dates referred to in the invitation and specifications. This bid was not introduced into evidence and the parties have stipulated that it was lost or destroyed and could not now be produced. The invitation, the specifications, and the contract, called for completion of all work within 500 days.

The plaintiff’s bid was accepted, and on November 4,1939, the contract for the construction of the abutments and piers was executed. The contract provided that the work was to be commenced and completed in conformity with paragraph 21 of the specifications. These specifications provided in part as follows:

The contractor shall begin work within thirty (30) calendar days after date of receipt of notice to proceed, and shall complete the various parts of the work within the number of calendar days from the date of receipt of notice to proceed, as follows:
[483]*483Abutments 1 and 2, within one hundred and twenty. (120) calendar days;
Pier 1, within one hundred and eighty (180) calendar days;
Pier 2, within two hundred and twenty (220) calendar days; .
Abutments 3 and 4 and piers 8, 9, and 10, within two hundred and forty (240) calendar days;
Pier 3, within two hundred and eighty (280) calendar days;
Piers 6 and 7, within four hundred (400) calendar days;
Pier 5, within four hundred and fifty (450) calendar days; and
Pier 4, within five hundred (500) calendar days.
The contractor shall at all times during the continuance of the contract prosecute the work with such forces and equipment as, in the judgment of the contracting officer, are sufficient to complete it within the specified periods of time. The contractor’s construction program shall be subject at all times to the approval of the contracting officer. The capacity of the construction plant, sequence of operations, and method of operation shall be such as to insure the completion of the work within the specified periods of time. The contractor’s plant shall be located and operated so as not to interfere with the erection of the superstructure of the bridge.

The invitation for bids and this provision of the specifications are very clear and positive, and the evidence of record shows that the purpose of the defendant in providing for the interim completion dates, as to the various piers and abutments, was to enable the construction of the bridge’s superstructure, under another contract, to proceed in a prescribed manner from both approaches or abutments toward the center piers. This was in keeping with the defendant’s efforts to coordinate all work to be performed under various contracts.

Paragraph 22 of the specifications further provided for the.assessing of liquidated damages in the sum of $100 per day for each day of delay in completing the various portions of the work within the time limitations set forth in paragraph 21 of the specifications, above set forth. The plaintiff did Hot, in its bid or at any time prior to completion of all [484]*484work, make any specific objection or reservation as to the interim completion dates.

Notice to proceed under the contract was issued by the defendant’s contracting officer on December 8, 1989, and received by plaintiff on December 9, 1939. However, the plaintiff had actually commenced work under the contract on November 16, 1939. The written notice to proceed expressly fixed specific dates in conformity with paragraph 21 of the specifications for the completion of the various abutments and piers. Finding 15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Warehouse Two, Inc. v. The United States
389 F.2d 1016 (Court of Claims, 1967)
Stein Bros. Mfg. Co. v. United States
337 F.2d 861 (Court of Claims, 1963)
Universal Match Corp. v. United States
161 Ct. Cl. 418 (Court of Claims, 1963)
Cresswell v. United States
173 F. Supp. 805 (Court of Claims, 1959)
Petrolite Corp. v. United States
161 F. Supp. 618 (Court of Claims, 1958)
Anthony M. Meyerstein, Inc. v. United States
137 F. Supp. 427 (Court of Claims, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 179, 126 Ct. Cl. 478, 1953 U.S. Ct. Cl. LEXIS 114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-paving-co-v-united-states-cc-1953.