Rogers v. United States

99 Ct. Cl. 393, 1943 U.S. Ct. Cl. LEXIS 84, 1943 WL 4217
CourtUnited States Court of Claims
DecidedApril 5, 1943
DocketNo. 44581
StatusPublished
Cited by13 cases

This text of 99 Ct. Cl. 393 (Rogers v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rogers v. United States, 99 Ct. Cl. 393, 1943 U.S. Ct. Cl. LEXIS 84, 1943 WL 4217 (cc 1943).

Opinion

Jones, Judge,

delivered the opinion of the court:

The plaintiffs as trustees for the stockholders of B. & R. Company, Inc., successors to Bates & Rogers Construction Company, instituted this suit to recover excess costs caused by delay in furnishing rights-of-way and easements for the construction of a dam on the Tuscarawas River near Dover, Ohio. The delay is alleged to have been the fault of the defendant.

Bates & Rogers Construction Company, hereinafter referred to as the contractor, agreed for an estimated consideration of $957,262 to furnish all labor and materials and perform all work required for the construction of the Dover [405]*405Dam, except that certain materials designated in paragraph 1-15 of the specifications were to be furnished by the Government.

The contract was to be commenced within 10 calendar days after receipt of notice to proceed, and to be completed within 700 calendar days thereafter. Notice to proceed was given June 5, 1935, thus fixing May 5, 1937, as the date for completion.

A progress chart was furnished by the contractor, indicating the intention of completing one-third of the concrete operations during the working season of 1935, the balance up to 95 percent to be completed during the working season of 1936, leaving only 5 percent to be poured after the second winter layoff, together with topping off and dressing up of the work.

At the time the contract was executed a branch of the Pennsylvania Railroad passed through the dam site on the left or south bank of the river, from 11 to 21 feet above the normal level of the river. The river was about 300 feet wide at this point, with sharp up-sloping banks on both sides.

The specifications contemplated that the north half of the dam, including monoliths 1 to 11 to the center of the stream, would be constructed first, after which the river would be diverted and the south half of the dam, including the remaining monoliths, would be constructed. The specifications provided that the south half of the dam might be constructed at the contractor’s convenience, provided its operations did not interfere with traffic over the existing line of the Pennsylvania Railroad and that it would be permitted to construct monolith No. 16 as soon as the existing railroad line should be abandoned. The specifications stated “it is estimated that this line will be abandoned by or prior to March 1, 1936. The contractor will not be allowed to construct the second cofferdam and the remaining dam monoliths Nos. 12 to 15 inclusive, until the existing railroad line is abandoned, or until authorized in writing by the contracting engineer and subsequent to completion of work in the first cofferdam as previously specified.” They also stated that in case the relocation of the Pennsylvania Railroad was not completed by March 1, 1936, the contracting officer would extend the time [406]*406for completion of plaintiff’s contract. The railroad was to be relocated at approximately 70 feet above the river or at the elevation of the top of the dam.

The major part of the work of relocating the railroad, which required the removal and relocation of about 12 miles of track, was covered by a contract between the United States and the Geo. W. Condon Company dated March 29, 1935, though there were other contractors involved. On June 6, 1935, the contractor in the instant case arrived on the job and began the work of clearing the site of timber, drawing up plans for the construction plant and preparing to bring on its equipment. Excavation was begun July 1, and construction of the north cofferdam July 5. The cofferdam was unwatered August 2. There was a short delay on account of a flood overtopping the cofferdam. It was necessary to redesign the steel trestles in order to make them stronger. In the meantime cranes were used. This for a short time slowed down the progress of the work. In an effort to keep up with its progress schedule the contractor continued to pour concrete until December 24, 1935, although it had anticipated discontinuing not later than December 1. This brought it within 10,000 cubic feet of its schedule, about one month’s plant capacity. In March 1936 when the contractor expected to resume pouring concrete it had no aggregate on hand, and because of winter conditions was unable to secure delivery thereof until April. However, prior to that time the defendant had notified the contractor that the railway would not be relocated until about May 15, so this delay was immaterial. Pouring of concrete was resumed on April 18,1936.

During the spring of 1936 floods caused a suspension of the work, for which an extension of time of 8 days was granted. In July 1936 the contracting officer gave the contractor authority to divert the river through the north half of the dam and remove the first cofferdam. The river was diverted in August 1936. Rock faults were discovered which caused a further extension of time and an increase in the contract price. There were repeated delays in relocating the railroad. The engineer in charge notified the contractor that it would probably not be completely done until May 15, [407]*4071986, the completion date for removal was deferred from time to time and the railroad was not finally relocated until October 8,1936, more than 7 months after the time estimated in the specifications and more than 9 months after the time called for in the contract with the Geo. W. Condon Co. This greatly handicapped the contractor in the instant case, made it necessary to slow down its work, and increased its costs of operation.

The crux of plaintiffs’ complaint is that the contractor had undertaken a two-season contract and that because of the failure of defendant to have the railroad tracks removed by March 1, 1936, or within a reasonable time thereafter, the time within which the construction of the dam could have been completed was greatly extended and the cost thereof greatly increased, and that this being the fault of the defendant, they are entitled to recover the increased costs thus necessarily incurred, which they allege to be approximately $210,000.

The defendant answers with the plea that necessary delays and change orders made it impossible for the work to be substantially finished in the year 1936 and that it was not responsible for the delays in relocating the tracks of the Pennsylvania Railroad.

It is rather clear from the evidence that had the railroad been relocated within a reasonable time after March 1,1936, and had there been no delays and change orders, the contractor could have completed the contract practically in accordance with its original schedule. It is also clear, however, that because of floods, rock faults, and extra work and change orders which were the fault of neither party, it probably could not have finished before June 15, and possibly not before July 15, 1937. Taking all these matters into consideration, it is very evident that on account of the delays directly flowing from the failure to relocate the railroad tracks, the contractor was delayed at least 85 days. This delay of 85 days was conceded by the defendant’s engineer and the contracting officer.

There is much dispute as well as conflicting evidence as to the responsibility for other delays, and in view of the state of the record the plaintiffs should be confined on this [408]*408phase of the case to the damages which directly resulted from the 85 days’ delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
Metropolitan Paving Co. v. United States
163 Ct. Cl. 420 (Court of Claims, 1963)
Metropolitan Paving Company v. The United States
325 F.2d 241 (Court of Claims, 1963)
Ozark Dam Constructors v. United States
153 Ct. Cl. 120 (Court of Claims, 1961)
Union Paving Co. v. United States
115 F. Supp. 179 (Court of Claims, 1953)
McGuire & Hester v. City & County of San Francisco
247 P.2d 934 (California Court of Appeal, 1952)
Psaty & Fuhrman, Inc. v. Housing Authority
68 A.2d 32 (Supreme Court of Rhode Island, 1949)
Harwood-Nebel Construction Co. v. United States
105 Ct. Cl. 116 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
99 Ct. Cl. 393, 1943 U.S. Ct. Cl. LEXIS 84, 1943 WL 4217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rogers-v-united-states-cc-1943.