Detroit Steel Products Co. v. United States

62 Ct. Cl. 686, 1926 U.S. Ct. Cl. LEXIS 304, 1926 WL 2602
CourtUnited States Court of Claims
DecidedDecember 13, 1926
DocketNo. D-787
StatusPublished
Cited by4 cases

This text of 62 Ct. Cl. 686 (Detroit Steel Products Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit Steel Products Co. v. United States, 62 Ct. Cl. 686, 1926 U.S. Ct. Cl. LEXIS 304, 1926 WL 2602 (cc 1926).

Opinion

Campbell, Chief Justice,

delivered the opinion of the court:

The plaintiff entered into a contract with the Government to furnish all necessary labor and materials for and to install certain steel sash and incidentals in four designated buildings in accordance with specifications made a part of the contract. The contract was dated the 14th day of September, 1919, and related to buildings then in course of construe[694]*694tion by other contractors. The sash could not be installed until the buildings were ready for it. There was much delay, and not until the fall of 1922 was plaintiif’s work completed. To what extent the Government should be held responsible for these delays and the damages occasioned to plaintiff By reason of them is the important question. A recital of the facts makes clear the conclusion that the Government did not undertake that the buildings would be ready for plaintiff’s work at the “ approximate dates ” stated in the specifications. Bids were asked for this steel-sash work under specifications furnished to bidders. These showed on their face that the Government had awarded a contract to the American Bridge Company for the provision and erection of the structural steel frames for the several buildings, and the bidders well knew that the buildings were to be erected by one or more contractors. As to the form of their proposals, bidders were informed, among other things, that they were “ expected to read the specifications with special care and to observe all of its requirements.” Also that they were expected to examine the site of the proposed work and inform themselves thoroughly of the actual conditions and requirements before submitting proposals.

Under the heading of “time of completion” the bidders were required to state the number of calendar days required to complete the steel sash work “ after notification that the building is ready for installing the work,” and under this same heading the specification stated “ approximate dates ” when the structural steel work of the four buildings would be ready to receive the steel sash, with the further statement that these “ approximate dates ” are “ for the information of bidders only and are not guaranteed,” the dates so stated being August 1, 1919, October 1, 1919, and September 1, 1919, for the severally named buildings, the last date mentioned applying to two of them. The specifications stated that the Government would notify the contractor “ when these buildings are ready for the steel-sash work ” and when so notified the contractor should proceed to install it. When to this is added the requirement already stated that the bidders should state the number of days they would require [695]*695for their work “ after notification that the building is ready ” for it, there would seem to be no room for the contention that the approximate dates stated were binding upon either party. And when it is observed that the contract itself was made on September 14, at which time the stated approximate dates had already expired as to three of the buildings and lacked about two weeks of expiration as to. the fourth, and it is further observed that the plaintiff several months later was inquiring as to when the buildings would be ready, evidencing a desire to get its materials together, we think there can be no serious contention that either party understood or agreed that the work would or could be begun at any definite date.

Besides these considerations it may be said the contract provided that the Government could make changes and thus interrupt the stipulated continuity of the work. See H. E. Crook Co. case, 270 U. S. 4. And some months after the original contract was made a supplemental contract was entered into that involved the price to be paid for changes. It can not be held that the contract, provided definite dates for the plaintiff’s work to begin, and as was said by the Supreme Court in the Crook case, supra, “it was obvious on the face of the contract that these dates were provisional.” In the cases of Lange do Bergstrom, 61 C. Cls. 666, and 61 C. Cls. 682 (certiorari denied by Supreme Court, October 18, 1926), the court considered the effect of provisions in a contract very similar to that in the instant case and said it was manifest from the terms of the contract that the parties had in contemplation that there might be delays (in that case incident to securing the materials), and in the instant case while awaiting other contractors. In the Crook case the contract provided that plaintiff would commence work when a copy of the contract was delivered to the contractor, while in the instant case the provision is that plaintiff would complete its work on the four several buildings within a stated number of days “ to be figured from the date of receipt of written notice * * * that the respective buildings are ready for the * * * sash.” This feature is therefore quite as plainly brought out in the instant case as it appeared in the Crook case, and in the latter case it was said by the [696]*696Supreme Court: “When such a situation was displayed by the contract it was not to be expected that the Government should bind itself to a fixed time for the work to come to an end, and there is not a word in the instrument by which it did so, unless an undertaking contrary to what seems to us the implication is implied.” For delays occurring prior to notification that the building was ready there can be. no recovery. Three of the buildings were completed after more or less delay. They were accepted and payment for them was received without objection, except as to a retained percentage hereafter mentioned.

But the facts further develop a situation which we think is not governed by what was said in the Crook case or presented in any of the other cases cited. The plaintiff was notified in January, 1922, that the heat-treatment building was ready for the installation of the sash and proceeded to perform the work. The work on some of the buildings had commenced in or about March, 1919, and was completed as already stated. We may dismiss consideration of any delays incident to these three because the evidence relates to the fourth, the heat-treatment building, which was the last to be completed. It was not until January 5, 1922, that plaintiff was notified by the Government’s agent that this building was ready for the steel sash and was requested to install it. Upon receiving this notification plaintiff promptly brought its men and equipment to the site and actually began work on January 16. If it had been allowed to proceed, uninterruptedly, it would have concluded its work within the contract time of 40 days, but plaintiff was subjected to a series of suspensions or interruptions by the Government, such as an order to “ discontinue immediately ” from the Navy Department on February 9, followed by an order on February 17 to resume, though its force of men and equipment had been returned to Detroit.

Having at once brought this fact to the attention of the officer in charge, it was ordered on February 23 to resume work and then proceeded to gather and return its scattered force to the site on March 4. Part of its equipment, which had been returned to Detroit under the order to “ discon[697]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rogers v. United States
99 Ct. Cl. 393 (Court of Claims, 1943)
Ross Engineering Co. v. United States
92 Ct. Cl. 253 (Court of Claims, 1940)
Phoenix Bridge Co. v. United States
85 Ct. Cl. 603 (Court of Claims, 1937)
Donnell-Zane Co. v. United States
75 Ct. Cl. 368 (Court of Claims, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
62 Ct. Cl. 686, 1926 U.S. Ct. Cl. LEXIS 304, 1926 WL 2602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-steel-products-co-v-united-states-cc-1926.