Harwood-Nebel Construction Co. v. United States

105 Ct. Cl. 116, 1945 U.S. Ct. Cl. LEXIS 119, 1945 WL 4047
United States Court of Claims·Decided November 5, 1945·No. No. 44587·Published·Cited by 5 cases

Opinion

LittletoN, Judge,

delivered tne opinion of the court:

Pursuant to defendant’s invitation for bids of October 3,. 1936, on the basis of certain detailed specifications and drawings dated September 30, 1936, and the acceptance of plaintiff’s bid of $141,377, plaintiff and the defendant entered into- and executed the Standard Government Contract for Construction, Form 23, on February 24-, 1937, for the construction by plaintiff of an extension to the building of the Capitol Power Plant to house certain refrigeration machinery and. equipment in connection with the air conditioning systems in. [157] the Capitol, Senate, and Ho'use Office Buildings. Detailed specifications and drawings for the furnishing and installation of the refrigeration and air conditioning apparatus and equipment were issued at the same time as the building specifications, and bids were likewise invited on October 3, 1936, for this work.

Paragraph 30 of the building specifications called the attention of bidders for the construction contract, which was awarded to plaintiff, to the drawings and specifications for installation of the refrigerating machinery and equipment (finding 2). The contract for installation of the air conditioning equipment was awarded to the York Ice Machinery Corporation, and a contract therefor, dated February 24, 1937, was made by defendant with that corporation. In the specifications and bid forms defendant fixed a period of 150 days for completion of the York contract and a period of 160 days for completion by plaintiff of its construction contract. Notices to proceed were given to both contractors on March 17, 1937.

Plaintiff computed its bid price for all work, materials, overhead, etc., on the basis of the period specified by defendant for completion of its contract. However, for the reasons’ set forth in findings 4, 5, and 6, plaintiff was unable, because of delays caused by defendant, to substantially complete the original construction work called for until March 25, 1938; a total delay of 213 days after the contract completion date of August 24, 1937. By reason of this delay in completion of the original contract work, plaintiff incurred and sustained actual increased expenses and damages of $6,781.49 (findings 8 and 9).

On the evidence submitted by both parties we find this delay to have been unreasonable and, therefore, to have constituted a breach by defendant of its contract with plaintiff. Langevin v. United States, 100 C. Cls. 15; Diamond v. United States, 98 C. Cls. 543, 551, 552; Rogers, et al. v. United States, 99 C. Cls. 393, 411; George A. Fuller Co. v. United States, 104 C. Cls. 176.

The extent of the delay to plaintiff’s work has been shown by the evidence not to have been justified by the circumstances and conditions which existed, nor by the authority [158] reserved by defendant in art. 3 of both contracts to make changes. The right to make changes contemplates, as has been consistently held, that they be made as promptly as possible and within a reasonable time without unnecessary and unreasonable delay to the contractor concerned. In the case at bar plaintiff was not delayed by unforeseen or changed conditions nor by acts of an independent contractor, but it was delayed by reason of defendant’s failure to act with reasonable promptness in making decisions and supplying information and material necessary to the orderly and continuous progress of plaintiff’s, work. The pipe-sleeve delay of 19 days from April 1 to April 19,1937; the switchT board room floor slab delay of 127 days from May 19 to September 22, 1937; and the monorail delay to the original contract work which extended from early in May 1937 until the construction work was substantially completed and accepted, were all relatively minor matters, and defendant had had a long period of time from the issuance of the specifications and drawings on September 30, 1938, to decide upon these matters. No proof has been submitted to justify these long delays. Under the terms of its contract and the circumstances disclosed by the evidence, plaintiff had the right to suppose that the necessary information and material concerning the matters mentioned and shown, in the plans and specifications would be supplied within a reasonable time. In each instance plaintiff gave defendant adequate advance notice as to when the information and material concerning the three items mentioned would be needed and necessary to permit the work to continue without delay.

Plaintiff is therefore entitled to recover its increased costs and damages incident to this delay of 213 days which the evidence satisfactorily shows amounted to a total of $6,781.49.

Defendant argues that in any event plaintiff may not recover increased overhead and other expenses and damages incident to delay in performance of the original contract work for a period longer than 146 days, made up of the pipe-sleeve delay of 19 days and the switchboard room floor delay, (in conditionally approving plaintiff’s shop drawing). It is argued that- as the delay with reference to plaintiff’s original contract work in connection with the monorail was [159] concurrent with the other delays of 146 days mentioned and with the 55 days allowed in connection with certain outside extra work ordered by defendant, no increased expenses, by way of damages, for this additional time of 68 days until substantial completion of the original work on March 25, 1938, may be recovered. We think this argument cannot be sustained. .

Free access — add to your briefcase to read the full text and ask questions with AI

Harwood-Nebel Construction Co. v. United States, 105 Ct. Cl. 116, 1945 U.S. Ct. Cl. LEXIS 119, 1945 WL 4047 (cc 1945).

105 Ct. Cl. 116 (Harwood-Nebel Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bell BCI Co. v. United States
56 Fed. Cl. 465 (Federal Claims, 2003)
Pfotzer v. United States
77 F. Supp. 390 (Court of Claims, 1948)
George A. Fuller Co. v. United States
69 F. Supp. 409 (Court of Claims, 1947)
J. J. Kelly Co. v. United States
69 F. Supp. 117 (Court of Claims, 1947)