J. J. Kelly Co. v. United States

69 F. Supp. 117, 107 Ct. Cl. 594, 1947 U.S. Ct. Cl. LEXIS 84
CourtUnited States Court of Claims
DecidedJanuary 6, 1947
Docket46032
StatusPublished
Cited by10 cases

This text of 69 F. Supp. 117 (J. J. Kelly Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. J. Kelly Co. v. United States, 69 F. Supp. 117, 107 Ct. Cl. 594, 1947 U.S. Ct. Cl. LEXIS 84 (cc 1947).

Opinions

JONES, Judge.

Plaintiff on November 2, 1942, contracted to construct for the defendant a decontamination building in the Navy Yard at Philadelphia, Pennsylvania.

Notice to proceed was given December 10, 1942, thus fixing February 8, 1943, as the date for completion of the work.

The work was completed May 1, 1943, except for some items which were taken over by the Government. This was 82 days later than the contract date for completion.

The contracting officer advised plaintiff in writing that the delay was due to unforeseeable causes beyond plaintiff’s control and he, therefore, extended for a period of 82 days the time for the completion of the work. These causes as listed were—

1. Operation of the preference system which delayed the delivery of materials.

2. Unusually severe weather.

3. An act of the Government in failing to deliver promptly the necessary protector units.

The contract price, as modified by change orders, was paid to plaintiff, the last pay[118]*118ment being made August 31, 1943. Prior thereto plaintiff had executed a document releasing the Government from all claims arising under the contract except “overhead” in the amount of $2,990.37.

The building which plaintiff was to construct was to be approximately 54 feet by 75 feet. It was to be used for the treatment of persons who had been subjected to gas attacks. Five protector units were to be installed. These were to be furnished by the government and were to be the heart of the decontamination building without which it could not function. These protector units were a military secret. Neither the plaintiff nor the officers who were in charge of the construction of the building knew the nature of them. However, it was revealed that the protector units were to be enclosed in rooms or placed within enclosures. Three kinds of connections were to lead to these enclosures including an electric, a duct, and an exhaust system. The plans did not reveal the location of the terminals of the duct and exhaust systems nor was plaintiff able to determine where these were to be located until after the protectors arrived. The location of the electric system was disclosed by the drawings.

None of the protector units arrived until long after the day which had been fixed for the completion of the building. Three of these five protector units were not furnished by the Government until 49 days after the time that had been set for the building to be finished. The two remaining units had not been furnished by May 1, 1943, on which date the defendant released the plaintiff from further work on the contract.

The plaintiff had further difficulties in securing materials due to the preference or priority system which was in effect during this war-time period. There were two bases for the delay in construction — one, the delay in furnishing the protector units, and two, the delay caused by the system of priorities in respect to materials. Both of these delays were serious, but, while plaintiff at first indicated that the major portion of the delay was due to the failure to promptly furnish the protector units which were to be installed, he later stated that the delay was due to both causes and declined to state or estimate how much of the delay was attributable to the respective causes.

There is no doubt that plaintiff was compelled to incur additional expense and costs of construction because of these delays. There was a third interference — that of severe weather conditions which prevailed during a 20 day period. However, plaintiff, by employing additional help, was able to overcome this delay.

Unfortunately for plaintiff, the testimony does not show clearly what proportion of the delay was due to the system of priorities and what proportion was due to nondelivery of the protector units. These were generally concurrent and not distinct, and, since the evidence does not furnish any proper basis for determining the part of the delay due to each of these the court is unable to satisfactorily apportion the delay attributable to the respective causes.

The preference or the priority system was an essential wartime policy. It was an act of sovereignty which was applied on a national scale to essential materials and since the Government was acting in this capacity it is not liable to the contractor for any damages due to that system. Horowitz v. United States, 267 U.S. 458, 45 S.Ct. 344, 69 L.Ed. 736; J. F. Barbour & Sons v. United States, 63 F.Supp. 349, 104 Ct.Cl. 360.

Unquestionably there were 82 days’ delay. None of this delay was the fault of the plaintiff. Yet, since a portion of it was due to conditions for which the defendant cannot be held liable and, since on the basis of the testimony and the documents in the record, we are unable to separate this portion and have no reasonable basis in the record for calculation of the portion that was due to each of the two causes of delay, the record does not afford a definite ground for recovery on the part of the pl.rutiff.

Flowever, even if we were able uo determine the amount of the delay that was due to the nondelivery of the protector units, the plaintiff could not recover in the light of the recent decision of the United States Supreme Court in the case of United States v. Howard P. Foley Co., 67 S.Ct. 154.

[119]*119While, probably due to our own fault and limitations, we do not find ourselves completely in accord with the logic of that decision, yet, since under our system the Supreme Court is the final arbiter in these matters and has the authority to set the pattern, we accept and apply the principle laid down by that court. In fact, we are glad to have a final determination of this long-disputed question. Article 9 of the standard contract was involved in both cases in identical language.1

In a number of decisions this court has held that Article 9 of the standard contract undertakes only to fix the liquidated damages that are to be assessed against the contractor in the event such contractor refuses or fails to prosecute the work, and provides only for an extension of time in behalf of the plaintiff in the event the delay is due to no fault on his part, and that such article does not attempt to determine the amount of damages that may be due plaintiff in the event the delay is due to a fault or breach of contract on the part of the Government.

We have held that this article is limited to the situation where the contractor fails or refuses to prosecute the work with sufficient diligence to insure its completion within the time specified, in which event the Government is to have the choice of two alternatives, to wit, cancellation or the assessment of liquidated damages; and that the proviso simply limits the Government’s choice of the two alternatives, and does not undertake to pass on the question of plaintiff’s damages due to delay caused by wrongful acts of the government.

We are still convinced that this is the proper interpretation but, since the final decision is otherwise, there can be no recovery in this case even though the delays had been clearly established as the fault of the agency or representatives of the Government.

[120]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lichter v. Mellon-Stuart Company
193 F. Supp. 216 (W.D. Pennsylvania, 1961)
Griffith Co. v. San Diego College for Women
289 P.2d 476 (California Supreme Court, 1955)
Thompson v. United States
124 F. Supp. 645 (Court of Claims, 1954)
Chalender v. United States
119 F. Supp. 186 (Court of Claims, 1954)
Kehm Corp. v. United States
93 F. Supp. 620 (Court of Claims, 1950)
J. J. Kelly Co. v. United States
69 F. Supp. 117 (Court of Claims, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
69 F. Supp. 117, 107 Ct. Cl. 594, 1947 U.S. Ct. Cl. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-j-kelly-co-v-united-states-cc-1947.