Langevin v. United States

100 Ct. Cl. 15, 1943 U.S. Ct. Cl. LEXIS 70, 1943 WL 4247
CourtUnited States Court of Claims
DecidedMay 3, 1943
DocketNo. 43903
StatusPublished
Cited by26 cases

This text of 100 Ct. Cl. 15 (Langevin v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Langevin v. United States, 100 Ct. Cl. 15, 1943 U.S. Ct. Cl. LEXIS 70, 1943 WL 4247 (cc 1943).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiff seeks to recover (1) for damages for delays caused by defendant; (2) for liquidated damages deducted; and (3) for the cost of putting on a copper roof.

Plaintiff had a contract for the construction of a Post Office at Weston, West Virginia. It was to be constructed under the supervision of Stephen W. Ford, an architect of Clarksburg, West Virginia, who was authorized to prepare all drawings and specifications, to pass on all shop drawings, to approve or reject architectural samples and all ornamental work, colors, and finishes. Mr. Ford severed his connection with the work on June 22, 1933, and thereafter his duties were assumed by the supervising architect in Washington.

The contracting officer granted extensions of time totaling 238 days for delays caused by the defendant. The plaintiff claims damages for these delays, and also for others for which no extensions of time were granted.

The delays for which extensions of time were granted were occasioned by the following:

(1) 15 days’ additional time required for lowering the footings to a depth greater than that originally specified;

(2) 19 days’ delay for time lost due to the failure of the architect to promptly approve the structural steel drawings;

[27]*27(3) 180 days’ delay in providing terra cotta models;

(4) 24 days’ delay on account of extremely cold weather during which plaintiff had to work caused by defendant’s previous delays.

In addition to these delays, plaintiff claims damages for the following delays for which no extensions of time were granted:

(5) 18 days during which the work was suspended while awaiting instructions for lowering the footings;

(6) 27 days’ delay in supplying details and drawings for millwork and in approving the drawings and samples for marble;

(7) 37 days’ delay due to the reluctance of subcontractors to fulfill their contracts after the expiration of the original period of the prime contract;

(8) 27 days’ delay due to defendant’s failure to promptly make final inspection of the building.

DELAYS EOR WHICH EXTENSIONS OE TIME WERE GRANTED

(1) 15 days' additional time required for lowering the footings to a depth greater than that originally specified

Plaintiff is not entitled to recover damages for the period of this delay. The defendant had the right to make changes in the contract and, therefore, in doing so it did not breach the contract and no damages can be recovered for the extra time required. United, States v. Rice and Burton, Receivers. 317 U. S. 61. See (5) below.

(2) 19 days' delay for time lost due to the fail/wre of .the architect to promptly approve the structural steel drawings

Plaintiff received notice to proceed on January 17, 1933. The work was to be completed in 360 days, or by January 12, 1934. On February 14, 1933 plaintiff submitted to Mr. Ford, the architect, various samples and drawings. Six days later Mr. Ford wrote plaintiff that he had not received the instructions from the Treasury Department necessary for him to approve these samples and drawings, and suggested to plaintiff that he send all drawings and samples direct to Washington, although the contract named Mr. Ford as the [28]*28person to approve or reject them. Accordingly, plaintiff submitted to the supervising architect in the Treasury Department the reinforcing steel drawings on February 27, 1933, and the structural steel drawings on March 8, 1933. On March 17 and 22 the supervising architect wrote plaintiff that the samples and drawings were being returned to Mr. Ford for his approval. These were not approved until April 28, 1933, and as a result work on the building was at a standstill from May 2 to May 20, both inclusive, a total of 19 days. This was a delay solely occasioned by the defendant’s representatives and, therefore, the plaintiff is entitled to recover the damages resulting therefrom.

(3) 180 days’ delay in providing terra cotta 'models

The contract required defendant to furnish plaintiff with terra cotta models. Plaintiff requested it to do so on February 17, 1933, but received no reply to his request. He repeated this request in letters directed both to Mr. Ford and the supervising architect on May 4, May 17, June 14, and June 22. As a result of defendant’s long continued failure to furnish the models the terra cotta was not delivered on the job until February 10,1934, although plaintiff repeatedly complained of the delay and notified defendant of the additional expense the delay was causing him.

The defendant recognized its default and granted an extension of 180 days on account thereof. Plaintiff is .entitled iso recover for the damages caused by. this delay.

(4) %4 days’ délo/y on accotmt of extremely cold weather■ during which plaintiff had to work caused by defendants previous delays

The building was due to be finished on January 12, 1934. On account of the foregoing delays by the defendant the work was extended' throughout the winter of 1933-1934. It was one of the coldest winters recorded in the preceding twenty years, and on account thereof plaintiff’s work was delayed. The defendant recognized this and granted him 24 days’ additional time on account thereof. Plaintiff is entitled to recover damages suffered on account of this 24 days’ delay.

[29]*29DELAYS FOR WHICH EXTENSION'S OF TIME WERE NOT GRANTED

(5) 18 days during which the ivorJc was suspended while-awaiting instructions for lowering the footings

While plaintiff was excavating for footings on March 6,. 1933, it was found that the depths originally specified were-not sufficient to reach solid bearing. The construction engineer ordered suspension of the work until defendant could, determine what it wanted to do. It did not make this determination until March 24, 1933. Plaintiff asked for the cost of superintendence and overhead for 15 days of the total of' 18 days while it was awaiting instructions. This was disallowed by the contracting officer.

It is said that this action of the contracting officer is made-conclusive by article 9 of the contract. We do not think so. That article relates alone to the assessment of liquidated damages for delay in completing the contract; it does not. relate to the defendant’s liability for damages resulting from a delay caused by it. On the question of the assessment of liquidated damages the findings of fact of the contracting officer, or the head of the department in case of appeal, on the cause and extent of delay were made final and conclusive ; but it is not provided that they are final and conclusive on the question of the defendant’s liability for damages.

The contract provides for the assessment of liquidated' damages for each day of delay beyond the termination of' the contract period, but it provides that liquidated damages-shall not be assessed—

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark-Fitzpatrick Incorporated v. Gill, 88-785 (1993)
Superior Court of Rhode Island, 1993
Wilner v. United States
26 Cl. Ct. 260 (Court of Claims, 1992)
Pathman Construction Co. v. United States
652 F.2d 70 (Court of Claims, 1981)
Law v. United States
195 Ct. Cl. 370 (Court of Claims, 1971)
Utah Construction & Mining Co. v. United States
339 F.2d 606 (Court of Claims, 1964)
Robert E. Lee & Co. v. United States
164 Ct. Cl. 365 (Court of Claims, 1964)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)
Kehm Corp. v. United States
93 F. Supp. 620 (Court of Claims, 1950)
Anthony P. Miller, Inc. v. United States
77 F. Supp. 209 (Court of Claims, 1948)
Schmoll v. United States
63 F. Supp. 753 (Court of Claims, 1946)
Harwood-Nebel Construction Co. v. United States
105 Ct. Cl. 116 (Court of Claims, 1945)
George F. Driscoll Co. v. United States
63 F. Supp. 657 (Court of Claims, 1945)
Irwin & Leighton v. United States
101 Ct. Cl. 455 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
100 Ct. Cl. 15, 1943 U.S. Ct. Cl. LEXIS 70, 1943 WL 4247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/langevin-v-united-states-cc-1943.