Irwin & Leighton v. United States

101 Ct. Cl. 455, 1944 U.S. Ct. Cl. LEXIS 81, 1944 WL 3721
CourtUnited States Court of Claims
DecidedApril 3, 1944
DocketNo. 44915
StatusPublished
Cited by16 cases

This text of 101 Ct. Cl. 455 (Irwin & Leighton v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irwin & Leighton v. United States, 101 Ct. Cl. 455, 1944 U.S. Ct. Cl. LEXIS 81, 1944 WL 3721 (cc 1944).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiffs entered into a contract with the defendant for the construction of a Post Office and Court House at Wilmington, Delaware. They sue the defendant for damages for delays caused by (1) failure to furnish models on time; (2) changes made in penthouses and a coping; (3) changes [474]*474made in the Judge’s library; (4) on account of a strike; (5) changes necessary to install an electrical signal system; (6) changes in the counters in the deputy clerk’s and deputy marshal’s offices; and (7) changes to provide for an acoustical tile base in certain of the rooms.

1. Delay due to failure to furnish models on time. — The plans and specifications called for the erection of eleven limestone ornamental carvings at various points on the exterior of the building. The models for these carvings were prepared by an independent contractor. After the architects for the building had prepared details for the models, the independent contractor moulded them in clay and photographed them. After the photographs had been approved by the architects and the Treasury Department the models were then cast in plaster and were photographed and, after approval, were shipped to plaintiffs’ subcontractor in Indiana, who constructed the ornamental carvings according to them.

According to plaintiffs’ progress schedule, 2 of these 11 models were required to be in the hands of their subcontractor on December 10, 1935, and 4 on December 15, 1935, but these 6 models were not received by the subcontractor until February 28, 1936. Plaintiffs originally claimed damages for this 80 days of delay; however, in their brief they reduce this claim to 44 days. The contracting officer found that plaintiffs had been delayed 32 days and extended the time for completion of the contract accordingly. The defendant in its brief admits that there was some delay, but says that the proof does not show the extent of it. It suggests that the delay could not have been more than 19 days.

The commissioner finds that defendant was not responsible for the entire 80 days’ delay. He finds that plaintiffs were considerably delayed in the first few months of the contract by tardy delivery of structural steel, brick, tile, waterproofing, granite, and on account of unsatisfactory metal forms, and by unusually severe weather. The result of this was that by the end of December, when the 6 models should have been in the hands of the subcontractor, only 18.4 percent of the work had been completed, whereas 35 percent should have been completed.

[475]*475He also finds that plaintiffs did not begin the setting of limestone until March 24, 1986, whereas, according to their schedule, all of it should have been set between December 23 and March 15; and he finds that they were not ready for the carvings until April 30, 1936. These findings are not disputed and are amply supported by the testimony.

Inasmuch as plaintiffs were not ready for the 6 carvings, the models for which were furnished on February 28, 1936, until April 30, 1936, it would appear that plaintiffs had not been delayed at all due to the tardy furnishing of these 6 models, since plaintiffs had notified the defendant that only 2 months would be required to construct the carvings after the models had been received. However, the commissioner does find that some ornamental carvings were not on hand when plaintiffs were ready for them, and he finds that the defendant was responsible for this delay, whatever the extent of it may have been. He also finds that it took plaintiffs 146 days to do the limestone work, whereas their progress schedule had allowed 83 days therefor.

For how much of this 63 days’ delay the defendant was responsible is exceedingly difficult to determine from the proof. As stated above, the defendant says that this could not have exceeded 19 days, but the contracting officer found that the delay had been 32 days.

It is true that we are not bound by the findings of the contracting officer in a claim for damages due to delay (Langevin v. United States, 100 C. Cls. 15), but there is a strong presumption that the delay was not less than that found. The contracting officer, or his representative, had day to day contact with the work and was in the best position of anyone, except the contractor, to know the extent of the delay. He is supposed to weigh the facts with an even hand before rendering his decision; but it cannot be overlooked that he is the defendant’s selection and its own employee. He is not apt to err on the side of the contractor and against his employer, whose interests he is employed to guard and protect. Unless the clear weight of the evidence shows the delay was less than that found by him, we think the defendant is bound by his finding. His finding in this case is not contrary to the weight of the evidence.

[476]*476On tbe other hand, the plaintiffs evidently were satisfied with the finding because they took no appeal from it to the head of the department.

We hold, therefore, that plaintiffs are entitled to recover from the defendant damages for 32 days’ delay in the furnishing of the models.

2. Belay due to •penthouses and coping changes. — The contract called for two penthouses on top of the third story for housing the elevator machinery. These were to be faced with brick; but in November 1935 defendant notified plaintiffs that it desired to change this facing to limestone with a brick backing, and requested a proposal for doing the work as changed. This proposal was submitted on November 22,1935, in the sum of $1,534.50. Plaintiffs were notified that it was considered excessive and subsequently they submitted several revised proposals, including one on April 3,1936, for $2,567, which included 10 percent overhead and 10 percent profit, and an amount of $600 for “additional job administrative expense due to delays.” They were notified that the contracting officer was without authority to approve any charge for overhead other than overhead incident to the extra work ordered. On April 8,1936, the plaintiffs were ordered to proceed with the changes, subject to a later determination of the price. Drawings for the changes had been transmitted to plaintiffs previously on March 28, 1936. Finally on April 13, 1936, plaintiffs submitted a proposal of $1,529.58, which was accepted.

Plaintiffs claim that the defendant’s delay in making up its mind as to the change it wanted was unreasonable and that they were delayed thereby for 30 days to their consequent damage. The contracting officer extended plaintiffs’ contract time 24 days on account of the delay.

It is questionable whether or not the plaintiffs were delayed at all on account of this change. The commissioner-finds that the plaintiffs could have begun work on the penthouses on April 12, 1936, but the evidence shows that even though they had had the stone on hand at that time they probably would not have done so. As we stated in discussing-[477]*477the delays due to the furnishing of the models, plaintiffs did not begin their limestone work until March 24, 1936. This work, of course, begins at the bottom of the building and works up. It is not reasonable to suppose that plaintiffs would have done the limestone work on the penthouses on the top of the building prior to the time they had done the stone work below this point. As a matter of fact, plaintiffs did not begin the stone work on the penthouses until July 2, 1936, three months after the drawings had been received.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilner v. United States
28 Fed. Cl. 783 (Federal Circuit, 1993)
Wilner v. United States
26 Cl. Ct. 260 (Court of Claims, 1992)
Commercial Cable Co. v. United States
170 Ct. Cl. 813 (Court of Claims, 1965)
Robert E. Lee & Co. v. United States
164 Ct. Cl. 365 (Court of Claims, 1964)
George A. Fuller Co. v. United States
69 F. Supp. 409 (Court of Claims, 1947)
James Stewart & Co. v. United States
63 F. Supp. 653 (Court of Claims, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
101 Ct. Cl. 455, 1944 U.S. Ct. Cl. LEXIS 81, 1944 WL 3721, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irwin-leighton-v-united-states-cc-1944.