Young-Fehlhaber Pile Co. v. United States

90 Ct. Cl. 4, 1939 U.S. Ct. Cl. LEXIS 165, 1939 WL 4196
CourtUnited States Court of Claims
DecidedNovember 6, 1939
DocketNo. 43841
StatusPublished
Cited by6 cases

This text of 90 Ct. Cl. 4 (Young-Fehlhaber Pile Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Young-Fehlhaber Pile Co. v. United States, 90 Ct. Cl. 4, 1939 U.S. Ct. Cl. LEXIS 165, 1939 WL 4196 (cc 1939).

Opinion

GeeeN, Judge,

delivered the opinion of the court:

On November 10, 1936, the plaintiff entered into a contract with the defendant under the terms of which it agreed to furnish all labor and material and perform all work required for reinforcing the south pier of Summit Bridge over the Inland Waterway from the Delaware River to Chesapeake Bay, Delaware and Maryland, for the consideration of $41,783. Plaintiff’s work under the contract was to be completed within 100 days from the date of receipt of written notice to proceed.

Article 19 of the contract provided in part as follows:

Art. 19.. (a) Labor preferences. — With respect to all persons employed on projects, except as otherwise pro[12]*12vided in Regulation No. 2 (a), they shall be referred for assignment to such work by the United States Employment Service and (b) preference hi employment shall be given to persons from the public relief rolls and, except with the specific authorization of the Works Progress Administration, at least ninety percent (90%) of the persons employed on any project, shall have been taken from the public relief rolls: Provided, however, That, expressly subject to the requirement of subdivision (b), the supervisory, administrative,. and highly skilled workers on the project, as defined in the specifications, need not be so referred by the United States Employment Service.

Pursuant to notice received from the defendant, the plaintiff, on December 17, 1936, placed its equipment on the site of the work preparatory to beginning work. On December 16, 1936, the plaintiff made a request on the United States Employment Service for workmen and as the work proceeded continued to request workmen from the United States Employment Service, which was the office designated from which plaintiff was to receive its labor supply. But the United States Employment Service was not able to furnish sufficient qualified men to carry on the work and the necessary workmen could not be obtained in accordance with the terms of the contract. Part of this was caused by the dangerous nature of the work and part by other causes. The plaintiff attempted to get permission to use his own men on the work but did not succeed and in order to complete the contract was compelled to hire more than 10 percent of his labor from a source other than the United States Employment Service.

The contracting officer found that by reason of the failure of the United States Employment Service to furnish the necessary labor to complete the contract plaintiff was delayed 23 days in completing the work, and having so found, extended the time of plaintiff for completion of the contract accordingly. The plaintiff now seeks to recover damages on account of the delay. The defendant concedes the delay and also the amount of damage sustained which was found by the contracting officer, but says there has been no breach of the contract on its part, that it did not agree to furnish a sufficient supply of labor, and that there is nothing in the [13]*13■contract providing that the contractor might recover damages in case of delay being caused by failure to furnish workers.

There is in fact no provision in the contract that defendant should furnish a sufficient supply of labor, and nothing is said therein with reference to the plaintiff being entitled to recover damages in case such a supply was not furnished. The nature of the contract, however, was such that we think it carried an implied agreement to furnish the men necessary to carry on the work. It must have been understood between plaintiff and the defendant’s agents who prepared and executed the contract that plaintiff would be permitted in some way to obtain a sufficient force to carry on the work contemplated thereby. The provisions contained in the contract with reference to the source from which the plaintiff should obtain its workers surely were not understood by the parties to mean that if the workmen could not be so obtained the plaintiff would not be permitted to obtain the necessary workmen to complete the contract. Under any other construction, we would have in one part of the contract a provision that plaintiff must complete it within a certain time, and in another part a provision which meant that it could not be completed in event there was a shortage of workmen.

In Black v. Woodrow, 39 Md. 194, 215, it is said:

It not infrequently occurs that contracts on their face and by their express terms appear to be obligatory on one party only; but in such cases, if it be manifest that it was the intention of the parties, and the consideration upon which one party assumed an express obligation, that there should be a corresponding and correlative obligation on the other party, such corresponding and correlative obligation will be implied. Thus, if the act to be done by the party.binding himself can only be done upon a corresponding act being done or allowed by the other party, an obligation by the latter to do or allow to be done the act or things necessary for the completion of the contract will be necessarily implied.

This case is cited as authority for the principle laid down therein in 13 C. J., sec. 122, p. 649. We think the rule stated is a correct one and conclude that the contract in the case at bar carried an implied provision that the defendant would [14]*14furnish the necessary workmen to complete the work within the required time. It follows that by its failure so to do the defendant breached the contract and was liable in damages.

It is urged on the part of the defendant that the contract provided in substance that, except with the specific authorization of the Works Progress Administration, at least 90 percent of the persons employed should be taken from the public relief rolls. The plaintiff did not comply with this provision nor did it request the Works Progress' Administrator to waive it. The evidence shows definitely that the plaintiff used every effort to obtain men from the source required by the contract and obtained all the workmen it possibly could in that manner. Apparently the officials of the Employment Service did what they could to aid in the matter, but they were unable to furnish the necessary workmen. The fact was that the men necessary to carry on the work could not be obtained in the manner required by the contract and plaintiff was compelled to go outside of its literal provisions in order to complete the work which it required.

It is urged on behalf of defendant that the contract provided in effect that the Works Progress Administration might waive this provision as to the source from which labor should be obtained but that plaintiff did not communicate with the Works Progress Administrator and ask that such a waiver be made. It is sufficient answer to the defense so set up, as we think, that such action would have been absolutely useless. The provision with reference to permission being given by the Works Progress Administration is quite peculiar and we think amounts to little or nothing because there was nothing that required the Works. Progress Administration to give such permission or consent even though no laborers whatever could be obtained in the manner required by the contract. Moreover, the plaintiff violated no provision of the contract by not requesting specific authority from the Works Progress Administration, for the contract did not require it to so act. But if the plaintiff had requested such authority, it would have made, no difference in the situation whether the Works Progress. [15]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. J. Albrecht Co. v. United States
63 F. Supp. 85 (Court of Claims, 1945)
Worsham v. United States
103 Ct. Cl. 378 (Court of Claims, 1945)
York Engineering & Construction Co. v. United States
62 F. Supp. 546 (Court of Claims, 1945)
Irwin & Leighton v. United States
101 Ct. Cl. 455 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
90 Ct. Cl. 4, 1939 U.S. Ct. Cl. LEXIS 165, 1939 WL 4196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/young-fehlhaber-pile-co-v-united-states-cc-1939.