Utah Construction & Mining Co. v. United States

339 F.2d 606, 168 Ct. Cl. 522
CourtUnited States Court of Claims
DecidedDecember 11, 1964
DocketNo. 3-61
StatusPublished
Cited by11 cases

This text of 339 F.2d 606 (Utah Construction & Mining Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Construction & Mining Co. v. United States, 339 F.2d 606, 168 Ct. Cl. 522 (cc 1964).

Opinions

Whitaker, Senior Judge,

delivered the opinion of the court:

Plaintiff had a contract with the Atomic Energy Commission for the construction of an assembly and maintenance area at the National Reactor Testing- Station in Jefferson and Butte Counties, Idaho. The contract was fully performed on January 7, 1955, several extensions of time having been, granted on account of delays for which the contractor was not responsible. During the performance of the contract and after its completion, plaintiff made various claims for increased costs and for damages, some of which were claims arising under the contract and some for alleged breaches of contract by the defendant on account of delays and other causes.

The case was referred to Trial Commissioner C. Murray Bernhardt for the taking of testimony and for a report. On February 18,1964, the commissioner issued an order defining the scope of the testimony to be taken with reference to the several claims, in the light of the Supreme Court’s opinion in United States v. Bianchi, 373 U.S. 709 (1963). The defendant now asks us to review this order.

[525]*525Prior to United States v. Wunderlich, 342 U.S. 98 (1951), this court had held that in determining whether or not the action of the contracting officer or the head of the department was arbitrary or capricious or unsupported by substantial evidence or otherwise contrary to law, it was not confined to the evidence before the Board of Contract Appeals (which in most cases was the representative of the head of the department), but was entitled to receive evidence de novo. However, the Supreme Court in United States v. Wunderlich, supra, held that we were bound by the action of the contracting officer on claims arising under the contract unless his action was fraudulent; that is to say, unless it amounted to conscious wrongdoing. Following this decision, the Congress enacted what is known as the Wunderlich Act, being the Act of May 11,1954, 68 Stat. 81. This act in substance provided that the decision of the head of a department or bis duly authorized representative or board “in a dispute involving a question arising under such contract * * * shall be final and conclusive unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence.”

Following the enactment of this statute, this court first held in Wagner Whirler and Derrick Corp. v. United States, 128 Ct. Cl. 382, 121 F. Supp. 664 (1954), that the Wunder-lich Act was designed to restore the status quo ante the decision of the Supreme Court in United States v. Wunderlich, supra, but we did not decide in that case whether or not de novo evidence was admissible to determine whether the action of the board was arbitrary, etc. However, in Volentine and Littleton v. United States, 136 Ct. Cl. 638, 145 F. Supp. 952 (1956), we explicitly held that since the purpose of Congress was to restore the status quo ante and since the practice prior to the Wunderlich decision had been to receive evidence de novo, we would continue to do so. We reiterated this position in Bianchi v. United States, 144 Ct. Cl. 500, 169 F. Supp. 514 (1959), 157 Ct. Cl. 432 (1962); but the Supreme Court reversed and held that in the determination of this question we were confined to the evidence admitted before the board. United States v. Bianchi, 373 U.S. 709 (1963).

[526]*526In cases where the administrative record was defective or inadequate, the Court had this to say:

* * * First, there would undoubtedly be situations in which the court would be warranted, on the basis of the administrative record, in granting, judgment for the contractor without the need for further administrative action. Second, in situations where the court believed that the existing record did not warrant such a course, but that the departmental determination could not be sustained under the standards laid down by Congress, we see no reason why the court could not stay its own proceedings pending some further action before the agency involved. Cf. Pennsylvania R. Co. v. United States, 363 U.S. 202. Such a stay would certainly be justified where the department had failed to make adequate provision for a record that could be subjected to judicial scrutiny, for it was clearly part of the legislative purpose to achieve uniformity in this respect. And in any case in which the department failed to remedy the particular substantive or procedural defect or, inadequacy, the sanction of judgment for the contractor would always be available to the court. [373 U.S. 709, 717-18.]

Where the dispute “arises under the contract” the contracting officer and the head of the department have authority to decide questions of fact and the contract makes their decision thereon final and conclusive; but where the dispute involves an alleged breach of the contract, and the contractor seeks unliquidated damages therefor, neither the contracting officer nor the head of the department has jurisdiction to decide the dispute. Miller, Inc. v. United States, 111 Ct. Cl. 252, 77 F. Supp. 209 (1918); Langevin v. United States, 100 Ct. Cl. 15 (1943); Beuttas v. United States, 101 Ct. Cl. 748 (1944), reversed in part on other grounds, United States v. Beuttas, et al., 324 U.S. 768 (1944). If they undertake to do so — which they rarely do— neither their decision nor the findings of fact with reference thereto have any binding effect. This necessarily follows because they are without authority to decide the dispute. It goes without saying that a decision of any court or other agency on a matter, concerning which it has no jurisdiction has no binding effect whatsoever. Steamship Co. v. Tugman, 106 U.S. 118, 122 (1882); Coyle v. Skirvin, 124 F. 2d 934, 937 [527]*527(10th Cir. 1942), and cases there cited. See also Petition of Taffel, 49 F. Supp. 109, 111 (S.D.N.Y. 1941).

Defendant contends that since the contract gives to the contracting officer and the head of the department authority to make findings of fact concerning all disputes, they have authority to make findings concerning a dispute over whether the contract had been 'breached. This contention cannot be sustained. The contract plainly limits their authority to make such findings to “disputes concerning questions of fact arising wider this contract.” This means a dispute over the rights of the parties given by the contract; it does not mean a dispute over a violation of the contract.

The Supreme Court’s opinion in Bianchi, supra,,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
339 F.2d 606, 168 Ct. Cl. 522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utah-construction-mining-co-v-united-states-cc-1964.