This text of 101 F. Supp. 755 (Continental Illinois Nat. Bank & Trust Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Illinois Nat. Bank & Trust Co. v. United States, 101 F. Supp. 755, 121 Ct. Cl. 203 (cc 1952).

Opinion

MADDEN, Judge.

The plaintiff Bank and Trust Company, as the executor of the estate of Alfred N. Severin, has been authorized by the Probate Court of Cook County, Illinois, to act a,s liquidator of the partnership affairs of Nils P. Severin and Alfred N. Severin. Both the Severins are deceased. During their lives they carried on a contracting business under the partnership name of N. P. Severin Company. The claims here in suit arise out of a building contract between the N. P. Severin Company and the United States. The Severin Company will be referred to hereinafter as the contractor.

On March 30, 1935, the contractor and the Government, which acted through the Federal Emergency Administrator of Public Works, entered into a contract for the construction of a low-cost housing project known as the University Housing Project at Atlanta, Georgia, for the sum of $1,984,-042.

Claim for Cost of Inspector at Concrete Dry Batching Plant

Findings 15 and 16 relate to this claim. Briefly, the pertinent facts are these. Section 9 of Division VII of the specifications of the contract provided for the inspection of the contents of the concrete mix and the testing of the concrete for strength and other requisite qualities. It provided that the cost of the inspection and testing should be borne by the contractor. In fact, however, the Government would have had the inspection and testing done .by its own employees without cost to the contractor if the inspection and testing could have been done on the site of the job. The plaintiff found it more economical and convenient to dry-batch the concrete mixture at the railroad siding where it received the ingredients from the railroad. This was two miles from the site where the construction was going on and the concrete was to be used. The dry mix was placed in mixing trucks and hauled to the job site where the water was added and the mixing completed. Because of the distance of the batching plant from the job site, the Government required the contractor to hire and pay an inspector, designated by an independent testing laboratory, who would inspect and approve the quality of each batch of concrete mixed at the batching plant.

We think the Government had the right to make this requirement. Under the terms of the contract, it would seem *757 that the Government could have required the contractor to pay for the inspection, even at the job site. The fact that it would not have done so did not put it under the additional burden of furnishing an inspector at the remote 'batching plant, where, whether busy with inspection of concrete or not, he could not do anything else that was useful to the Government. This claim of the plaintiff is not well founded.

Claim for Delays

The completion of the construction was .greatly delayed. The contract provided for a performance period of one year. That period was extended by 253 days by the Government’s contracting officer for causes for which, he found, the contractor was not responsible. Thus the contractor was excused from liability for liquidated damages for these 253 days, though, as we shall see, it was assessed liquidated damages for a later period. The plaintiff claims that the Government was culpably responsible for much of the 253 days’ delay, and that the plaintiff was damaged thereby, by having its job overhead and administrative expense continued when, but for the delay, it would have been through with the job.

The contract contained the usual Article 3, permitting the contracting officer to, within limits, make changes in the required work; Article 4 providing what should be done if unanticipated conditions were encountered; and Article 15 providing that disputes arising under the contract should be decided by the contracting officer, subject to an appeal by the contractor to the head of the department.

At the very 'beginning of the work, the ■contractor’s excavation subcontractor was delayed for seven days while the contracting officer considered, and at last abandoned, an idea of raising the grades of all the buildings in the project. Then some days’ delay was caused the subcontractor by the discovery that the Government’s drawings of the grade elevations were erroneous. The contractor, at its own expense, had new and correct drawings made, but the plaintiff has not proved their cost and makes no claim for it.

When excavation for foundation footings began, unsuitable soil conditions consisting of soft ground and water, rubbish fills and old sewer lines and wells were encountered. Time was required for the Government to investigate these conditions and redesign the foundations. The contractor claimed that it was delayed 53 days, and it was allowed 33 days of excusable delay, on this account, when its extended completion date was fixed. We think that the Government is not required to pay the contractor’s overhead losses caused by the encountering of these unanticipated conditions. They were not due to the fault of either party to the contract. Besides, the evidence shows that the plaintiff could have avoided the delay by planning its work better and going ahead on other parts of the site where there were no obstacles to progress.

Block B of the project consisted of a number of buildings, garages, and the boiler house for the project. Excavation for the 'boiler house was begun on October 14, 1935. On October 17 the contractor was instructed to stop work on the boiler house because it was going to be redesigned. Not until April 15, 1936, 175 days later, was the contractor permitted to proceed in accordance with the new design.

We think that the Government’s taking 175 days for the redesign of the boiler house was inconsiderate of the harm which was being caused the contractor, and was a breach of the contract. The right reserved in the contract to make changes in the work does not 'mean that the Government can take as much time as it pleases to consider such changes, regardless of consequences to the other party to the contract. Brand Investment Co. v. United States, 58 F.Supp. 749, 102 Ct.Cl. 40, 44. We think that not more than 40 calendar days would have been, in the circumstances, a reasonable time for the redesign of the boiler house, and that the plaintiff may recover its job overhead and administrative expense, which we have found to have *758 averaged ,$207.79 per day, for the balance of 135 days, a total o.f $28,051.65.

Liquidated Damages

Article 9 of the contract and Section 10 of the specifications provided that the contractor should be assessed liquidated damages of $200 per day for lateness of completion of the project. The contracting officer excused, as iwe have said, 253 days of delay, thus fixing the completion date, as extended on December 30, 1936. On that date the project was reported by the Government’s project manager to be 99.6% complete. But the Government would not “accept” it on that date, nor even on February 27, 1937, when it was 99.9% complete. As a consequence, the plaintiff was assessed liquidated damages at $200 per day from December 31, 1936, to March 17, 1937, 77 days, amounting to $15,400. The Comptroller General, in settling the contractor’s account, excused 21 days of this time, thus reducing the liquidated damages by $4,200, to the sum of $11,200. The plaintiff sues for the $11,200. We think it is entitled to recover on this claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
Tri-Cor, Inc. v. United States
458 F.2d 112 (Court of Claims, 1972)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Jefferson Construction Company v. The United States
392 F.2d 1006 (Court of Claims, 1968)
Utah Construction & Mining Co. v. United States
339 F.2d 606 (Court of Claims, 1964)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
G. L. Christian & Associates v. United States
160 Ct. Cl. 1 (Court of Claims, 1963)
St. Paul Dredging Co. v. State
107 N.W.2d 717 (Supreme Court of Minnesota, 1961)
Donovan Construction Company v. United States
149 F. Supp. 898 (Court of Claims, 1957)
Railroad Waterproofing Corp. v. United States
137 F. Supp. 713 (Court of Claims, 1956)
FH McGraw and Company v. United States
130 F. Supp. 394 (Court of Claims, 1955)
Allied Contractors, Inc. v. United States
124 F. Supp. 366 (Court of Claims, 1954)
Boomer v. Abbett
263 P.2d 476 (California Court of Appeal, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
101 F. Supp. 755, 121 Ct. Cl. 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-illinois-nat-bank-trust-co-v-united-states-cc-1952.