Allied Contractors, Inc. v. United States

124 F. Supp. 366, 129 Ct. Cl. 400, 1954 U.S. Ct. Cl. LEXIS 92
CourtUnited States Court of Claims
DecidedOctober 5, 1954
DocketNo. 49929
StatusPublished
Cited by12 cases

This text of 124 F. Supp. 366 (Allied Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Contractors, Inc. v. United States, 124 F. Supp. 366, 129 Ct. Cl. 400, 1954 U.S. Ct. Cl. LEXIS 92 (cc 1954).

Opinion

Littleton, Judge,

delivered the opinion of the court:

The plaintiff sues to recover $3,006 as damages for an alleged breach of contract by defendant. On June 15, 1948, plaintiff entered into a construction contract with the Navy Department whereby plaintiff was to furnish the materials, labor and equipment necessary to perform the work of erecting antenna poles and transmission wire poles; to construct access roads, and perform certain miscellaneous work at the Navy Communication Station, Annapolis, Maryland. The work was to be completed, as originally specified, on or before October 13, 1948.

The relevant portions of the contract specifications provide:

[403]*4032-01. General requirements. — The erection of antenna support and transmission line poles shall be accomplished in the groups as hereinafter set forth and shall be governed by the restrictions as hereinafter specified.
2-02. Bestrietions. — * * * Poles specified or indicated to be erected or removed shall in no case be stored at the site of the erection or removal, but shall be immediately erected or removed from the site. Poles specified to be disposed of shall be (a) stored at the site of the culvert, where directed, for use as piles; (b) stored on the reservation, where directed, for cutting into short lengths for deadmen; or (c) removed from the reservation.
2-03. Sequence of construction. — The erection and removal of antenna and transmission line poles shall be accomplished in three groups as directed. The three groups are as follows:
Group A.
^ *
2. (a) Existing antenna wires to be removed by the Government.
(b) Remove 4 long poles for disposal.
(c) Remove 3 short poles.
(d) Erect 5 antenna support poles, approximately 90 feet long.
te) Set 2 deadmen.
(f) Antenna then to be installed by the Government.
3. (a) Existing antenna wires to be removed by the Government.1
2-04. The procedure for erection of antenna supports and transmission line poles will be determined by the Government in a manner to cause the least possible interference with the operation of the Navy Communication Station. * * *

The specifications required the defendant to first remove the existing antenna wires. Following this the plaintiff was to remove the old poles either for re-erection, disposal, or for use as piles for the culvert in connection with the road work. Then plaintiff was to erect the new poles and set the deadmen. Following this work the defendant was then to install the antenna wire on the new poles. The defendant concedes, and the evidence clearly shows, that defendant did not follow the sequence of work as set forth [404]*404in the specifications in that defendant failed to promptly remove the wire from the old poles. This delayed and disrupted the orderly progress of plaintiff’s work, resulting in delay and expense to plaintiff. The plaintiff was prevented from immediately removing the old poles and was required to move its heavy equipment to another pole and later return to remove the old pole. Also, some of the old poles were designated by defendant for use as piles in the construction of the culvert under part of the road. The plaintiff, obviously, could not remove or use the designated poles for piles until defendant had removed the wire.

The defendant’s failure to promptly remove the wires in the sequence expressly required by the contract specifications delayed the culvert and road work beyond the original completion date of the contract and threw the work into the winter months. In early November plaintiff was authorized to purchase the poles needed for piles rather than wait until the wires were removed by defendant from the old poles. The plaintiff purchased the poles and proceeded with the road work.

On January 28, 1949, plaintiff was ordered to suspend work because of inclement weather. On March 24, 1949, plaintiff was ordered to resume work and the contract was completed in May 1949, within the contract time, as extended.

The plaintiff rented a caterpillar and roller to perform the road work. The roller, which was idle from December 1,1948, to April, 1949, cost plaintiff $335 per month or $1,340 for the idle time. The caterpillar, which was idle from December 1, 1948, to February 1, 1949, cost plaintiff $583 per month or $1,166 for the idle time. The plaintiff did not return this equipment to the owner from whom it had been rented during the work stoppage, due to the impossibility of anticipating the duration of such stoppage, and due further to the fact that such equipment was difficult to obtain on short notice, especially during the spring.

The plaintiff requested payment by defendant for the extra costs incurred by reason of defendant’s failure to follow the sequence of work set forth in the specifications, in the performance of the work required of defendant by the contract. The plaintiff’s request for $1,790 for extra cost on the antenna [405]*405work is itemized in finding 15. The plaintiff’s request for $2,406 was for the rental for the idle time of the caterpillar and roller, due to the failure of defendant to perform its part of the work under the contract, as it should and could have done within a reasonable time.2

The defendant paid plaintiff the $1,790 requested for the antenna work by change order “C” dated June 21,1949, which said in part: “Owing to the following change in the work, namely, revision in plans and procedure of construction by the Government, the contract price, in accordance with Article 10 of the contract, is hereby increased by $1,790.00 * *

The second item of extra costs of $2,506, the one for which plaintiff now seeks recovery, was denied by letter dated June 27,1949, “on the grounds that it is in the nature of damages and therefore not compensable [administratively] under the contract.” Both claims were founded on defendant’s failure to follow the sequence of work expressly set forth and called for in the specifications. Upon plaintiff’s further request for payment it was subsequently denied again by a letter dated August 26,1949, which stated:

In response to your oral inquiry, you are advised that report from the Public Works Office at the Naval Academy does not indicate that the Government so modified your procedures under the subject contract as to cause additional costs and entitle you to additional compensation.
Accordingly, there would appear to be no basis for reversing the Bureau’s decision denying your claim for $2,406 which was communicated to you .by the Officer in Charge of Construction on 27 June 1949.
This is a final decision of the Contracting Officer under Article 16 of the contract.

The plaintiff did not appeal this decision of the contracting officer.

It is clearly apparent from the evidence that defendant breached the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lakeview Lumber Products Co.
24 Cont. Cas. Fed. 81,811 (Court of Claims, 1977)
United States v. Morrison
370 F. Supp. 193 (E.D. Virginia, 1974)
Universal Ecsco Corporation v. The United States
385 F.2d 421 (Court of Claims, 1967)
Kayfield Construction Corp. v. United States
278 F.2d 217 (Second Circuit, 1960)
United States v. Adams
160 F. Supp. 143 (W.D. Arkansas, 1958)
United States v. Smith
152 F. Supp. 322 (E.D. Pennsylvania, 1957)
United States v. E. C. Nickel
243 F.2d 924 (Tenth Circuit, 1957)
Railroad Waterproofing Corp. v. United States
137 F. Supp. 713 (Court of Claims, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
124 F. Supp. 366, 129 Ct. Cl. 400, 1954 U.S. Ct. Cl. LEXIS 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-contractors-inc-v-united-states-cc-1954.