Universal Ecsco Corporation v. The United States

385 F.2d 421, 181 Ct. Cl. 10, 1967 U.S. Ct. Cl. LEXIS 256
CourtUnited States Court of Claims
DecidedOctober 13, 1967
Docket256-65
StatusPublished
Cited by21 cases

This text of 385 F.2d 421 (Universal Ecsco Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Ecsco Corporation v. The United States, 385 F.2d 421, 181 Ct. Cl. 10, 1967 U.S. Ct. Cl. LEXIS 256 (cc 1967).

Opinion

SKELTON, Judge.

This is a contract case. The plaintiff is a Delaware Corporation with its principal place of business in California.

On or about June 20,1960, the plaintiff entered into a contract with the United States Post Office Department to furnish and install a mechanized mail handling system in the Post Office in New Orleans for the total sum of $993,785. Several change orders issued during the period of the contract increased the amount of the contract to $1,001,810.25. The contract contained a Changes and a Disputes clause applicable to Government contracts, but did not contain Termination for Convenience or Suspension of Work clauses usually found in Government contracts.

During the performance of the work under the contract, various controversies and disputes arose between the parties. Those which were not resolved resulted in the filing of this suit. The plaintiff has set forth its claims in the various numbered paragraphs of its petition. The parties have presented the case to this court by referring to these numbered paragraphs which are paragraphs 12, 18, 19, 21, 22, and 23. We will dispose of the case by considering these claims by these numbers for the convenience of the parties and for the sake of continuity.

The defendant filed a motion for a partial summary judgment as to the claims asserted in paragraphs 12, 19, 21, and 22 of the petition. The defendant has also asserted a counterclaim in the amount of $24,000, representing alleged liquidated damages of $300 per day for 80 days’ delay on the part of the plaintiff in finishing the work called for by the contract.

*423 I

Claims 18 and 28 — The Discount on Invoices and the Power Turn Equipment

The plaintiff alleges in paragraph 18 that the defendant was entitled to a discount of 1 percent on invoices of plaintiff which defendant paid within 20 days after they were submitted to defendant by plaintiff, but that defendant breached the contract by taking a 1 percent discount on plaintiff’s invoices which it did not pay within 20 days. These wrongful discounts amounted to $3,450.67. Defendant admitted in its answer that it had taken a 1 percent discount on some invoices which it had not paid within 20 days, but does not allege the amount thereof.

In paragraph 23, the plaintiff alleges that defendant, after demand by plaintiff, has refused and continues to refuse to pay monies due plaintiff on the non-terminated portion of the contract, which is a breach of the contract. Plaintiff claims that because of such breach, defendant owes plaintiff $31,545.63 for power turn equipment engineered and installed by plaintiff. Defendant denies these allegations in its answer.

These two claims are not before us in connection with defendant’s motion, except indirectly. The plaintiff contends that since these two claims will remain in this court even if we grant defendant’s motion, we should braid these minor claims with the major ones involved in defendant’s motion so that all of the claims could be tried in one case in this court. Plaintiff cites Universal Ecsco Corp. v. United States, 345 F.2d 586, 588, 170 Ct.Cl. 809, 813 (1965), in support of this proposition. The defendant says the Supreme Court has overruled the doctrine of the Ecsco case in this regard in United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966). We do not deem it necessary to decide this question, as we will dispose of the claims involved in this case on a different basis. In the meantime, plaintiff’s claims 18 and 23 described above will remain before this court and will be ruled upon in due course by the court.

II

Claim 12 — The Supplemental Agreement

The contract provided that payments would be made to plaintiff in the following manner: 25 percent when fabrication of the equipment was 50 percent complete ; 25 percent when installation of the equipment was 50 percent complete; 25 percent when installation of the equipment was complete; and the remaining 25 percent upon final acceptance of the work. The facts show, however, that instead of following this method of payment, the Post Office Department paid plaintiff progress payments of 90 percent on this contract (and also on two other contracts plaintiff had for the Post Office Department) as the work progressed for about one year after the work started. In 1961 the Post Office Department changed its contracting officers. The new officers changed the method of payment to plaintiff from the 90 percent progress payments to the method set forth in the contract. This change applied to all three of plaintiff’s contracts and suddenly caused plaintiff to be indebted to defendant in the sum of $413,-000. Plaintiff was unable to secure adequate lines of credit and was on the verge of bankruptcy. After considerable negotiations between the parties, the Post Office Department offered to restore the 90 percent progress payments if plaintiff would sign a supplemental agreement which included a reduction in consideration to be paid to the plaintiff in the sum of $250,000, of which $31,500 is applicable to this contract. Plaintiff had the choice of signing the agreement or defaulting on all three contracts and going out of business. It signed the agreement April 25, 1962, and finished the contracts.

The plaintiff now contends that it was forced to sign the agreement by duress and coercion on the part of the Post Office Department, and that it would not have agreed to these onerous terms if the *424 Post Office Department’s abrupt change in its method of payment had not forced plaintiff to the brink of bankruptcy. The plaintiff avers that the agreement is without consideration, was obtained by coercion and duress, and is null and void, and by reason thereof the Post Office Department breached the contract. Plaintiff alleges that because of such breach of contract, defendant owes plaintiff $31,500. The plaintiff took no administrative action with reference to this claim, but filed its suit directly in this court.

The defendant says that this claim is barred by plaintiff’s failure to exhaust the administrative remedies provided in the contract, citing Frauhauf Southwest Garment Co. v. United States, 111 F.Supp. 945, 126 Ct.Cl. 51 (1953). We do not agree. The contract in the Fruhauf case provided for negotiating lower or higher prices (for manufactured overcoats) and also stated that a failure of the parties to agree would be appealable pursuant to the disputes clause. There is no such provision in the contract in this case. We must accept as true the allegations of plaintiff that the supplemental agreement was without consideration and was obtained by coercion and duress as against defendant’s motion for summary judgment. In fact, defendant does not argue that it was not obtained by duress, but says that even if there was duress, plaintiff was required to appeal to the Post Office Board of Contract Appeals.

We cannot accept defendant’s argument, because the plaintiff’s claim does not “arise under” the contract but is for breach of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SUFI Network Services, Inc. v. United States
102 Fed. Cl. 656 (Federal Claims, 2012)
Zinger Construction Company, Inc. v. The United States
753 F.2d 1053 (Federal Circuit, 1985)
D'Appolonia Consulting Engineers, Inc.
226 Ct. Cl. 633 (Court of Claims, 1981)
Midwest Window Systems, Inc.
650 F.2d 286 (Court of Claims, 1980)
Fischbach & Moore International Corp. v. United States
617 F.2d 223 (Court of Claims, 1980)
DeMauro Constr. Corp. v. United States
568 F.2d 1322 (Court of Claims, 1978)
SCM Corp.
553 F.2d 104 (Court of Claims, 1976)
Cities Service Helex, Inc. v. United States
543 F.2d 1306 (Court of Claims, 1976)
Manpower Inc. of Tidewater v. United States
513 F.2d 1396 (Court of Claims, 1975)
Airco, Inc. v. United States
504 F.2d 1133 (Court of Claims, 1974)
Autogiro Co. of America
202 Ct. Cl. 1105 (Court of Claims, 1973)
Sun Shipbuilding & Dry Dock Co. v. United States
461 F.2d 1352 (Court of Claims, 1972)
Southwestern Engineering Co.
196 Ct. Cl. 782 (Court of Claims, 1971)
Zidell Explorations, Inc. v. The United States
427 F.2d 735 (Court of Claims, 1970)
Clement Brothers Company, Inc. v. The United States
418 F.2d 1356 (Court of Claims, 1970)
Nelse Mortensen & Co. v. United States
301 F. Supp. 635 (E.D. Washington, 1969)
Vitro Electronics v. The United States
408 F.2d 1038 (Court of Claims, 1969)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
385 F.2d 421, 181 Ct. Cl. 10, 1967 U.S. Ct. Cl. LEXIS 256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-ecsco-corporation-v-the-united-states-cc-1967.