Universal Sportswear, Inc. v. United States

180 F. Supp. 391, 145 Ct. Cl. 209, 1959 U.S. Ct. Cl. LEXIS 85
CourtUnited States Court of Claims
DecidedMarch 4, 1959
Docket411-57
StatusPublished
Cited by10 cases

This text of 180 F. Supp. 391 (Universal Sportswear, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Sportswear, Inc. v. United States, 180 F. Supp. 391, 145 Ct. Cl. 209, 1959 U.S. Ct. Cl. LEXIS 85 (cc 1959).

Opinion

LARAMORE, Judge.

This action is brought by plaintiff to recover extra costs as a result of additional work required under an amendment to the contract.

Both the plaintiff and defendant have filed motions for summary judgment, and the following facts are presented by the pleadings, affidavits, and exhibits filed:

On or about March 14, 1952, plaintiff, a New York corporation, entered into a contract with the Navy for the manufacture of approximately 9,400 wool raincoats with removable rayon cloth linings. The contract provided that the defendant was to supply the wool outer cloth and the plaintiff to supply the rayon lining and other components. For its labor and material plaintiff was to receive under the contract approximately $112,000. To insure its performance under the contract, plaintiff was required to and did post a performance bond in the penal sum of $100,000.

When plaintiff began its operations, it attempted to purchase the specified rayon cloth for the lining but found the cloth was not available on the market. Upon advising the Navy of its difficulty, the Navy advised that it would authorize a Navy supplier to sell to plaintiff the yardage required under the contract. As a result plaintiff purchased 27,000 yards from this source. Plaintiff received the cloth and so advised the Navy. Representative samples were tested by the Navy laboratory and on or about May 1, 1952, the Navy informed plaintiff that samples had been tested and found to meet all specifications.

Thereupon plaintiff began to cut the rayon and by July 1, 1952, all lining had been cut, most of the yardage sewn into garments, and shipments of completed raincoats begun. At this point the Navy orally informed plaintiff that further laboratory tests showed that some of the rayon failed to meet specifications in that it revealed excessive staining under simulated perspiration tests. Plaintiff denied any liability by reason thereof on the grounds that it had used the cloth on the Navy’s previous approval. Nevertheless plaintiff advised the supplier of the Navy’s position. The supplier denied that the Navy’s tests were valid or accurate and had tests made by an independent laboratory which demonstrat *393 ed that its rayon cloth met contractual specifications. When plaintiff was informed of the results of the recent Navy tests, a Lt. Yarborough informed plaintiff that the matter did not present a serious problem and directed the continuance of all aspects of production.

Some time in August 1952 the contracting officer informed plaintiff that he would be willing to accept a price reduction of two cents per yard as a solution. Plaintiff informed the supplier of this and a meeting between the supplier, the contracting officer, and plaintiff was had some time thereafter. At this meeting, the supplier brought with him and exhibited to the contracting officer further laboratory tests which demonstrated that its cloth met specifications. During the discussions, the suggestion of the two-cent reduction was made by the contracting officer and refused by the supplier on the ground that the offer was unreasonable in the light of the tests made by the supplier. Plaintiff offered to pay the reduction but stated it ought not be required to do so. The conference ended with no decision being reached.

Shortly thereafter the contracting officer informed plaintiff that he had decided to have arm shields inserted in all the raincoats and directed the plaintiff to proceed at once under these instructions. Plaintiff objected and advised the contracting officer that it would insist upon additional compensation for the extra work. The contracting officer assured plaintiff that it would not suffer by the change order and that it would be fairly treated.

Under date of September 16, 1952, the contracting officer issued contract Amendment No. 5, in which he directed plaintiff, pursuant to section 2, “Changes,” of the provisions, to insert arm shields in all the raincoats. Amendment No. 5, which describes the work to be done, reads as follows:

“Pursuant to Section 2 ‘Changes’ of the General Provisions, the Contract Specifications are hereby changed as follows:
“The entire quantity of garments to be furnished under the subject contract shall have an arm shield made from rayon lining and bound with a rayon binding stitched in the armpit of each garment to serve as a safeguard against staining from perspiration. The shield shall cover the area of the garment contacting the armpit of the wearer. The arm shield shall be a segment of a circle finishing approximately 8long and 2%" at the center of each half. The shield shall be in two pieces securely handstitched in position.
“On page 11 under clause ‘Charges for additional Government furnished property’ delete 20% and substitute 5%. This change in percentage applies ONLY to the 14,322 yards of rayon binding and 700 yards of rayon lining, which shall be purchased from the Naval Supply Facility.”

In accordance with the change order plaintiff began to insert arm shields in all the raincoats. In so doing, plaintiff was forced to rip apart all the completed coats.

Some time in October 1952 plaintiff was informed that it would be denied compensation for the extra work. Plaintiff objected to this and was informed that if it did not agree to do the work without compensation, the contract would be terminated for default, all raincoats would be rejected, and plaintiff would be subjected to large claims for damages. Plaintiff was further told that in the event of termination for default, the Navy would confiscate all raincoats which contained Navy material (all did); that it would have to pay the cost of such Navy material; that it would be charged with any excess in the purchase price paid to a successor contractor; and that the performance bond would be defaulted and claim made thereunder. Plaintiff protested orally and in writing to no avail, and then signed Amendment No. 6, which is dated October 27, 1952. Amendment No. 6 reads as follows:

“Contract Amendment No. 5, being inaccurate in its statement, is *394 hereby withdrawn. In lieu thereof, subject contract is hereby amended as follows:
“The Contractor has offered for delivery garments which showed excessive staining under certain perspiration tests provided in the specifications. In order to overcome the above described deficiency, the Contractor has offered to insert arm shields in the garments. This is acceptable to the Government. Accordingly, pursuant to Section 5, ‘Inspection’, of the General Provisions ■of the contract, the Government ■agrees to accept hereunder garments, which the Government has a right to reject by reason of their failure to satisfy all of the perspiration tests called for in the specifications, provided that the Contractor inserts in each armpit of each garment delivered hereunder an arm shield conforming to the following specifications: The arm shield shall be made from rayon lining, bound with a rayon binding, and shall be stitched in each armpit of each garment to serve as a safeguard against staining from perspiration. The arm shield shall cover the area of the garment which contacts the armpit of the wearer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daff v. United States
39 Cont. Cas. Fed. 76,697 (Federal Claims, 1994)
Hannon Electric Co. v. United States
39 Cont. Cas. Fed. 76,664 (Federal Claims, 1994)
Robinson Contracting Co. v. United States
35 Cont. Cas. Fed. 75,654 (Court of Claims, 1989)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Maxwell Dynamometer Company v. United States
386 F.2d 855 (Court of Claims, 1967)
Maxwell Dynamometer Co. v. United States
386 F.2d 855 (Court of Claims, 1967)
Universal Ecsco Corporation v. The United States
385 F.2d 421 (Court of Claims, 1967)
Commonwealth Engineering Co. of Ohio v. United States
180 F. Supp. 396 (Court of Claims, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
180 F. Supp. 391, 145 Ct. Cl. 209, 1959 U.S. Ct. Cl. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-sportswear-inc-v-united-states-cc-1959.