Daff v. United States

39 Cont. Cas. Fed. 76,697, 31 Fed. Cl. 682, 1994 U.S. Claims LEXIS 154, 1994 WL 425261
CourtUnited States Court of Federal Claims
DecidedAugust 15, 1994
DocketNos. 90-3952C, 90-3958C
StatusPublished
Cited by17 cases

This text of 39 Cont. Cas. Fed. 76,697 (Daff v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daff v. United States, 39 Cont. Cas. Fed. 76,697, 31 Fed. Cl. 682, 1994 U.S. Claims LEXIS 154, 1994 WL 425261 (uscfc 1994).

Opinion

OPINION

BRUGGINK, Judge.

This is an action brought pursuant to the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1988) (“CDA”). On May 9, 1988, the Contracting Officer (“CO”) terminated the contract at issue for default because of alleged fraud on the part of Triad Microsystems, Inc., the contractor. On January 3,1990, the CO entered a second final decision, this time demanding return of unliquidated progress [686]*686payments. In its appeal, Triad1 seeks to have those decisions set aside. Defendant has counterclaimed to recover on its claim for unliquidated progress payments as a remedy for fraudulent breach of contract, for forfeiture of plaintiffs “claims,” and for damages and penalties under the False Claims Act. After trial, and for the reasons set forth below, the court concludes that the defendant has established by clear and convincing evidence that there was fraud in the performance of the contract. The default termination is, accordingly, sustained and defendant and is entitled to return of unliquidated progress payments. It is also entitled to recover damages and penalties under the False Claims Act.

BACKGROUND FACTS

The contract at issue was awarded in September 1984 by the United States Army Missile Command (“MICOM”), acting through the Small Business Administration. By the terms of the contract, Triad was required to produce 1,432 TOW Missile Vehicle Power Conditioners (“TVPC”). The total price of the contract was approximately $21,000,000.

The TOW missile is a versatile guided missile used in many battlefield applications as an anti-armor weapon. During its trajectory to a target, it maintains a connection to a guidance source by means of a tiny wire, which can pay out up to two miles. The operator focuses on the target, thereby automatically sending directional information to the missile in flight. The TVPC is a device used as an interface between the TOW missile and a vehicle, such as a jeep. The vehicle’s battery is a source of electricity to power the guidance apparatus. The battery current is converted to alternating current, amplified, and then reconverted to direct current.

Colonel Thomas Devaney, who manages acquisition for the Army on a number of systems, including the TOW, testified concerning the TVPC. He explained the importance of the conditioners to reliable operation of the missiles in battlefield settings. The missiles are deployed in a number of harsh environments. Consequently the TVPC can be exposed to salt fog on long ocean voyages and to rain, humidity, and dust. The unit, accordingly, must be reasonably weatherproof. Its most recent notable application was in Operation Desert Storm. Colonel Devaney explained that the contract at issue was not merely for production of training devices. The TVPC’s procured went into the Army’s combat inventory.

Triad points out that the contract was a DOD 1000B, Level 3, contract. The effect of this is that the contractor did not need special interpretive expertise in implementing the data package. It should have been able to follow the drawings and achieve a satisfactory product. In fact, there were 67 “deviation and waivers” granted during contract performance, prompted by inaccuracies and gaps in the Technical Data Package (“TDP”). Triad offered to rewrite and update the TDP, but MICOM declined, indicating that the work would be performed by another contractor, although it never was.

The contract contains a provision at section E making the work subject to the “Higher-Level Contract Quality Requirement” set out at MIL-Q-9858A. This specification creates a generally higher level of quality controls than would otherwise be applicable. Among other elements, at paragraph 3.4 “Records,” it directs the contractor to ensure that

records are complete and reliable. Inspection and testing records shall, as a minimum, indicate the nature of the observations together with the number of observations made and the number and type of deficiencies found. Also, records for monitoring work performance and for inspection and testing shall indicate the acceptability of work or products and the action taken in connection with the deficiencies. The quality program shall provide for the analysis and use of records as a basis for management action.

The contract incorporated by reference Federal Acquisition Regulation (“FAR”) § 52.246-2 which, in substance, requires the [687]*687contractor to establish an inspection system that results in delivery of an end item that has “been inspected and ... found by the Contractor to be in conformity with contract requirements.” The regulation also requires the contractor to “prepare records evidencing all inspections made under the system and the outcome.” Id. § 52.246-2(b).

John Pacetti is President of Triad. Corporate headquarters were in Santa Ana, California. At the time of the contract at issue, Triad had a number of government contracts pending. The production work on the TVPC contract was to take place at Triad’s facility in Huntsville, Alabama. At the time of the TVPC contract, Triad was also working on other government contracts at the Huntsville facility.

Charles Huggins came to Triad in July 1987 as a consultant, hired by Pacetti to advise him with regard to the personnel, facility, and processes at the Huntsville plant. Huggins was not entirely pleased with what he found, particularly with regard to personnel. Joseph Griggs, who was appointed production manager somewhat later, also testified to problems with workmanship, even at a subassembly level, and a high number of rejects. In September, Huggins was made plant manager. He was tasked with getting the facility reorganized and the TVPC contract back on schedule. It is clear enough from the testimony of Huggins and Pacetti that the headquarters office believed that production needed to be speeded up dramatically in Huntsville. During this period Huggins reported to John Danes, Chief Operating Officer, at the Santa Ana office.

On May 9, 1988, the CO terminated the contract for default prior to expiration of the contract term. No cure notice preceded the termination. Default was premised on the alleged falsification of records that the contract required be maintained with respect to certification of solderers. No other ground was offered. Subsequent to default, the CO demanded the return of excess progress payments in the amount of $6,251,924.78.

At the time of default, Triad had received $11,166,479.00 in progress payments. MI-COM had been furnished 673 TVPC units that Triad represented as meeting contract requirements. The government put on some evidence at trial that the delivered goods had a contract value of $4,914,554.22. Triad admits to a value of $5,564,301.64. Plaintiffs Response to Def.Prop. Finding of Fact 134.

The delivered units were gathered after default at the Anniston Army Depot in Anni-ston, Alabama. There the units were opened up, tested, repaired if necessary, and slightly modified by the addition of a foam rubber insulating pad. The government incurred expenses in the amount of $240,714.74 in doing this testing and repair. After this work, at least 615 units were deployed. There was no evidence at trial of failures of the unit in the field.

A large amount of parts and work in process was left in place at the Huntsville facility.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
Monterey Bay Military Housing, LLC v. Pinnacle Monterey LLC
116 F. Supp. 3d 1010 (N.D. California, 2015)
United States ex rel. Wuestenhoefer v. Jefferson
105 F. Supp. 3d 641 (N.D. Mississippi, 2015)
Chapman Law Firm, LPA v. United States
113 Fed. Cl. 555 (Federal Claims, 2013)
San Francisco Unified School District Ex Rel. Contreras v. Laidlaw Transit, Inc.
182 Cal. App. 4th 438 (California Court of Appeal, 2010)
Aptus Co. v. United States
61 Fed. Cl. 638 (Federal Claims, 2004)
American Pelagic Fishing Co., L.P. v. United States
55 Fed. Cl. 575 (Federal Claims, 2003)
Glazer Construction Co. v. United States
52 Fed. Cl. 513 (Federal Claims, 2002)
American Pelagic Fishing Co. v. United States
52 Fed. Cl. 341 (Federal Claims, 2002)
Pacetti v. United States
50 Fed. Cl. 239 (Federal Claims, 2001)
United States Ex Rel. Roby v. Boeing Co.
79 F. Supp. 2d 877 (S.D. Ohio, 1999)
Driggs Corp. v. Maryland Aviation Administration
704 A.2d 433 (Court of Appeals of Maryland, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,697, 31 Fed. Cl. 682, 1994 U.S. Claims LEXIS 154, 1994 WL 425261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daff-v-united-states-uscfc-1994.