Aptus Co. v. United States

61 Fed. Cl. 638, 2004 U.S. Claims LEXIS 225, 2004 WL 1941201
CourtUnited States Court of Federal Claims
DecidedAugust 30, 2004
DocketNo. 01-362C
StatusPublished
Cited by14 cases

This text of 61 Fed. Cl. 638 (Aptus Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aptus Co. v. United States, 61 Fed. Cl. 638, 2004 U.S. Claims LEXIS 225, 2004 WL 1941201 (uscfc 2004).

Opinion

OPINION

REGINALD W. GIBSON, Senior Judge.

I. INTRODUCTION

The present action arises from the government’s termination for default of plaintiffs, [640]*640Aptas Company’s, contract to install government-furnished equipment, and design, manufacture, and install contractor-furnished equipment at the government-owned and operated Sault Ste. Marie Hydroelectric Power Plant (the “Soo”) in Sault Ste. Marie, Michigan.2 The contractor’s right to proceed with work on the contract at issue, DACW35-99C-0001, was terminated for default on June 26, 2000, for failure to make progress,3 unsatisfactory work and unsound work methodology, and violations of the Davis-Bacon Act. At trial, the government also averred fraud as an additional post-hoc rationale to justify the termination decision. Plaintiff, proceeding pro se, alleged five (5) counts as separate bases for recovery in his First Amended Petition, which are as follows:

(i) wrongful termination of contract;
(ii) government’s breach of contract;
(in) government’s changes to the contract;
(iv) government’s breach of federal surety-ship law; and
(v) compensation for unjust enrichment.

After significant discovery, we heard this matter over a two-week period. At the close of plaintiffs case-in-chief, the government made a motion for entry of judgment in its favor on all counts, pursuant to RCFC 52(c). We took said motion, and plaintiffs response thereto, under advisement. For the reasons set forth in detail below, we hold that the decision to terminate Aptas for default is supported by substantial evidence, and that Aptas failed to meet his burden with respect to his defense of justifiable delay. Therefore, we uphold the defendant’s default termination. Consequently, plaintiffs claim of wrongful termination is DENIED. Further, we hold that the claim of government breach of contract, based entirely on the unavailability of the GFE, merges with, and is subsumed by, plaintiffs affirmative defense of justifiable excuse. Plaintiffs third claim seeking compensation for changes to the contract is DENIED, as plaintiff failed to meet his burden with respect to such claim. Further, we DISMISS the claim premised upon an alleged breach of suretyship law for want of jurisdiction pursuant to RCFC 12(b)(1). Finally, we find that plaintiffs claim for unjust enrichment is, in fact, an attempt to recover for the work he did during his performance of the contract, and an attempt to recoup the reproeurement costs that the government collected from his surety. Thus, it is not an equitable claim: it is a third restatement of his wrongful termination claim. Consequently, Count V is also merged with, and subsumed by, Count I. Our holdings herein render defendant’s motion for entry of judgment in accordance with RCFC 52(c) moot, and it is therefore DENIED.

II. BACKGROUND

A. The Purpose of the Contract

The instant contract was issued by the United States through the U.S. Army Corps of Engineers, Detroit District (USACE), as part of a plan to update and automate the equipment at the government owned and operated hydroelectric power plant at the Soo. That facility provides power to the USACE’s Soo Area Office, which encompasses the Soo Locks — a group of locks that facilitates commercial ship traffic between Lakes Huron and Superior. Any excess power generated by the Soo is sold to Edison Sault Electric Company (ESELCO), which in turn supplies power to the eastern portion the Upper Peninsula of Michigan. In total, four contracts were issued as part of this Automation Project: three equipment supply contracts, and one installation contract. These four contracts, collectively, call for the installation of automation equipment at five separate gener[641]*641ating units at the Soo: Units 1-3, 3A, and 10. The equipment contracts were issued to: Voith Hydro, Inc. for governor equipment, Asea Brown Boveri, Inc. (“ABB”) for excitation equipment, and Scipar, Inc. for SCADA equipment.4 The way the Automation Project was structured, a fourth party was required to install the government-furnished governor, excitation, and SCADA equipment acquired under the supply contracts. In addition to installing the GFE, the installation contract required the contractor to modify some portions of existing equipment, and design and install additional equipment necessary for automation.5

B. The Solicitation, Pre-Award Survey, and Award

On July 9, 1998, the government issued a solicitation for bids for the installation contract, with completion required within 450 days from the Notice to Proceed. Plaintiff responded to the government’s solicitation for the instant contract, and was the low bidder with a bid of $1,265,110.00.6 The government confirmed that plaintiff’s bid was responsive to the solicitation, and turned its attention to ascertaining whether plaintiff was a responsible bidder with respect to the contract. To make its responsibility determination, the government conducted a preaward survey.

During its pre-award survey, the government learned that plaintiff had performed three prior government contracts successfully. Those contracts all involved designing and installing SCADA equipment. The government also learned that plaintiff had been awarded an installation contract by the USACE for the Savannah District Power Plant. Said contract was terminated for convenience. The Contracting Officer charged with administering the contract at bar, Mr. George Fedynski, contacted the Savannah District and found that they considered termination for default. “They considered Aptas Company to be incompetent and wanted to get rid of it, and [termination for convenience] was a convenient way of doing it.” Trial Transcript (Tr.) 1321. Concerned respecting the foregoing, Mr. Fedynski participated in the pre-award survey himself, which he does not ordinarily do.

The government learned that Aptas was a single-man operation, consisting only of Mr. Lin. Mr. Fedynski “was very concerned that Mr. Lin did not have any permanent staff.” Tr. 1336. As stated above, Mr. Lin had significant experience with SCADA systems, and also holds a B.S. degree in Electrical Engineering, and an M.S. degree in Computer Science. However, Mr. Lin had no prior experience with hydroelectric power plant installation work. Mr. Lin also had no experience with governor or excitation equipment. To allay Mr. Fedynski’s concerns, Aptas provided written assurances that he would recruit experienced workers. Relying on (i) these assurances, (ii) Mr. Lin’s experience, and (iii) Aptas’ ability to obtain the required performance and payment bonds, Mr. Fedynski found that Aptas was a responsible bidder, and thus awarded Aptas the contract at bar on November 5, 1998. A Notice to Proceed was issued and acknowledged on December 9,1998, thereby starting the clock on the 450-day completion deadline of March 3, 2000,7 set forth in the contract.

C. The Default Termination Decision

The contract and its subsequent performance are explored in detail infra; however, a brief introduction to the contract require[642]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelleher v. Dream Catcher, L.L.C.
District of Columbia, 2019
Gilbane Federal v. United Infrastructure Projects FZCO
275 F. Supp. 3d 1180 (N.D. California, 2017)
Allen Engineering Contractor Inc. v. United States
611 F. App'x 701 (Federal Circuit, 2015)
Bulova Technologies Ordnance Systems LLC
Armed Services Board of Contract Appeals, 2014
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Takota Corp. v. United States
90 Fed. Cl. 11 (Federal Claims, 2009)
McDonnell Douglas Corp. v. United States
76 Fed. Cl. 385 (Federal Claims, 2007)
Moreland Corp. v. United States
76 Fed. Cl. 268 (Federal Claims, 2007)
Aptus Company v. United States
189 F. App'x 946 (Federal Circuit, 2006)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
Aptus Co. v. United States
62 Fed. Cl. 808 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
61 Fed. Cl. 638, 2004 U.S. Claims LEXIS 225, 2004 WL 1941201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aptus-co-v-united-states-uscfc-2004.