Moreland Corp. v. United States

76 Fed. Cl. 268, 2007 U.S. Claims LEXIS 117, 2007 WL 1180489
CourtUnited States Court of Federal Claims
DecidedApril 18, 2007
DocketNo. 03-2154C
StatusPublished
Cited by17 cases

This text of 76 Fed. Cl. 268 (Moreland Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moreland Corp. v. United States, 76 Fed. Cl. 268, 2007 U.S. Claims LEXIS 117, 2007 WL 1180489 (uscfc 2007).

Opinion

OPINION AND ORDER

WHEELER, Judge.1

Introduction

This case involves a timely appeal by the Moreland Corporation (“Moreland”) under the Contract Disputes Act, 41 U.S.C. § 601 et seq., from the Contracting Officer’s default termination of a Government building lease in Las Vegas, Nevada. The Department of Veterans Affairs (‘VA”) contracted with Moreland in September 1995 to construct a two-story building in Las Vegas to be used as a VA medical clinic. After Moreland completed construction of the building in 1997, the VA took occupancy and began its monthly rental payments under a 15-year lease. Moreland financed the design and construction costs of the bufiding with the expectation that those costs would be recouped through the VA’s monthly rental payments under the Lease.

The VA terminated the Lease for default on September 12, 2002, but continued to occupy the building until June 30, 2003. At that point, the VA ceased its monthly rental payments to Moreland, and moved to other facilities. Moreland filed suit in this Court [270]*270on September 11, 2003 within the one-year period for appeal under 41 U.S.C. § 609(a)(3), requesting de novo review of the default termination. Moreland asserts a wrongful termination under a number of legal theories, and claims the value of the remaining monthly payments under the Lease, less operating expenses, plus the value of the building that it lost through foreclosure after termination. Adding the net unpaid rent of $17,992,215.85 and the lost asset value of $20,000,000, Moreland’s total claim is $37,992,215.85, plus interest and attorneys’ fees.

■ The Contracting Officer terminated the Lease for default because Moreland allegedly failed to repair structural deficiencies in a timely 'manner, and because the VA’s engineering consultant found the building unsafe for continued occupancy. Defendant contends that the facility as originally constructed did not meet applicable building code requirements, and in this regard, relies upon admissions against interest that Moreland made in a 2002 Nevada lawsuit against its general contractor and others. Moreland Corp. et al. v. RMA, Inc. et al., No. CV-S-02-1259-JCM-PAL, 2002 WL 32975178 (D.Nev., filed Sept. 26, 2002). Defendant also maintains that, even if the default termination was improper, a “Termination for Convenience of the Government” clause incorporated by reference in the Lease prevents Moreland from recovering unpaid monthly rent.

The Court conducted an eight-day trial in Washington, D.C. during September 18-27, 2006. The parties filed post-trial briefs on December 18, 2006. Plaintiffs and Defendant filed reply briefs on January 29, 2007 and February 13, 2007 respectively. The Court heard closing arguments on February 21, 2007. The Court’s evidentiary record consists of the testimony of nine witnesses, 288 exhibits, and 2,994 transcript pages.2

For the reasons explained below, the Court concludes that the VA’s default termination was improper. Although the building was not perfectly constructed and experienced certain exterior cracks, the Court finds that the defects were largely cosmetic and easily could have been repaired if the VA had permitted Moreland to do so. Indeed, certain omitted “gusset plate” welds on lateral steel bracing could have been repaired upon being identified, but the VA did not allow Moreland to perform this work until after termination. Alleged design deficiencies concerning structural loading capacity appear to have been isolated, minor, or nonexistent. In considering the - competing testimony of the structural engineers on these issues, the Court affords the greatest weight to Plaintiffs’ expert, Dr. David Malone of Exponent Failure Analysis (“Exponent”).3 Based upon Dr. Malone’s testimony and other evidence of record, the Court finds that the building was not unsafe for the VA’s occupancy. ' Despite pronouncements from the VA and its consulting engineer that the building was unsafe, the VA used and occupied the building without interruption for more than five years, and remained in the building for nine months after termination.

As importantly, the Court finds that the VA breached its duty of good faith and fair dealing with Moreland. The VA initially used alleged building deficiencies in late 2000 as a pretext to have Moreland bear the expense of conducting a structural loading study that the VA would later use to add a roof-mounted air conditioning system to the building. Separately, the VA’s Contracting Officer, acting upon the advice of agency counsel, denied approximately $300,000 in Moreland’s construction-related claims. While the Contracting Officer thought the claims were justified and should be paid, counsel advised that the claims should be denied as a means of gaining leverage over [271]*271Moreland. Furthermore, when welding omissions and exterior cracks surfaced, the VA repeatedly imposed upon Moreland the requirement for “a comprehensive plan” before it would allow Moreland to make repairs. The Lease, however, contained no such obligation, and Moreland owned the building. Even when Dr. Malone and his associates proposed a reasonable repair plan on behalf of Moreland in 2002, the VA violated the Lease by not permitting Moreland to make repairs until after the VA had terminated the Lease for default.

The Court finds that Moreland is entitled to damages for the net unpaid rent in the amount of $17,992,215.85, plus interest as allowed under the Contract Disputes Act. In the circumstances of this Lease, the “Termination for Convenience of the Government” clause does not prevent Moreland’s recovery of unpaid rent. This is not a typical Government contract where an improper default is treated as a termination for convenience. Rather, the VA employed other provisions that governed during the lease term. The applicable default clause, “Default by Lessor During the Term,” cited by the Contracting Officer in the default notice, does not convert an improper default termination to a termination for convenience. Moreover, before signing the agreement, the parties clearly manifested their mutual intent to delete the clause entitling the Government to' terminate the Lease for convenience.

Moreland, however, is not entitled to recover the value of the building that it lost through foreclosure. The record does not support a finding that the default termination necessarily caused the foreclosure. The Court does not have before it Moreland’s bank loan agreement(s), and thus cannot say whether Moreland had any recourse against the bank after the VA’s default termination, whether Moreland could have refinanced the balance of the loan, or whether Moreland had the means to repay the loan balance to retain its asset. The record also does not indicate whether Moreland was entitled to any offsetting recovery from the bank upon the later sale or lease of the building. Without sufficient evidence of causation, the claim for the lost building asset must fail.

Findings of Fact

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
76 Fed. Cl. 268, 2007 U.S. Claims LEXIS 117, 2007 WL 1180489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moreland-corp-v-united-states-uscfc-2007.