Fort Howard Senior Housing Associates, LLC v. United States

121 Fed. Cl. 636, 2015 U.S. Claims LEXIS 665, 2015 WL 3451759
CourtUnited States Court of Federal Claims
DecidedMay 29, 2015
Docket10-553C
StatusPublished
Cited by1 cases

This text of 121 Fed. Cl. 636 (Fort Howard Senior Housing Associates, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fort Howard Senior Housing Associates, LLC v. United States, 121 Fed. Cl. 636, 2015 U.S. Claims LEXIS 665, 2015 WL 3451759 (uscfc 2015).

Opinion

Enhaneed-Use Lease; Department of Veter- ’ ans Affairs; Termination for Default; Breach of Contract; Excuse; Force Majeure; Reformation; Mutual Mistake; Impossibility

OPINION

FIRESTONE, Judge.

Pending before the court- is the government’s motion for summary judgment, filed pursuant to Rule 56 of the Rules of the United States Court of Federal Claims (“RCFC”). At issue is whether the Department of Veterans Affairs (“VA”) properly terminated for default the September 28, 2006 Enhanced-Use Lease (“Lease”) between the VA and plaintiff Fort Howard Senior Housing Associates, LLC (“FHSHA”) at the Fort Howard VA Medical Center in Baltimore County, Maryland. The Lease was executed pursuant to the VA’s authority under 38 U.S.C. §§ 8161-8167 and gave FHSHA the right to occupy the property for a term of 65 years, with an option to extend the Lease for 10 additional years. In exchange for its occupation, FHSHA was required to (1) pay consideration in the form of rent; (2) design, develop and construct a new 10,000 square foot Community-Based Outpa *640 tient Clinic (“CBOC”) within 39 months; (3) design and construct multi-use residences on-site in compliance with “applicable” state and local laws, codes, and regulations; and (4) protect, preserve, maintain, and repair the property.

After several years, the VA became concerned about the status of the project and, starting in February 2009, the VA began sending notices of default to FHSHA. Ultimately, the VA determined that FHSHA was in default of the Lease and, on August 17, 2009, the VA terminated the Lease for default on the primary grounds that FHSHA had failed to (1) commence construction of the new CBOC such that it would be completed with the timeframe required under the Lease, 1 (2) maintain and secure the property, and (3) pay its proportionate share of the utility bills.

FHSHA filed its initial complaint on August 16, 2010 and an amended complaint on June 29, 2012. 2 In its complaint, plaintiff asserts that the VA’s termination was wrongful on two main grounds: (1) its failure to build the CBOC was excused by the force majeure clause in the Lease, and (2) the government otherwise breached the Lease on various grounds. In its amended answer, the government counterclaimed for breach of the Lease and seeks $313,328.45 as the amount allegedly owed to the government under the Lease.

At the heart of FHSHA’s defense to the termination is its contention that it entered into the Lease with the understanding that it would be able to build 1,300 housing units on the site and that VA’s requirement that it comply with Baltimore County zoning regulations — which without a variance would limit development to 550 units — made the project economically unviable, requiring renegotiation. FHSHA argues that Baltimore County’s failure to accept plaintiffs request for an exemption from local requirements amounted to a force majeure event under the terms of the Lease. Plaintiff further argues that the VA’s insistence that plaintiff comply with local laws in connection with the project amounted to a breach of contract on several grounds and further excused FHSHA’s obligations under the Lease. Plaintiff argues that the VA, as the federal government, is not required to comply with local laws and regulations, and thus it was the VA’s insistence that plaintiff meet local zoning requirements that made the project economically unviable.

Discovery in the case is now completed. The government has moved for summary judgment, asking the court to find that the undisputed facts establish that the termination for default was reasonable and proper and that plaintiffs nonperformance is not excusable for any of the reasons advanced by the plaintiff. In response, FHSHA argues that the government’s motion should be denied on the grounds that there are genuine issues of material fact as to each of the government’s alleged grounds for termination for default and that, even if the termination was correct, FHSHA has presented sufficient facts to show that the failure to act was excusable under the Lease. For the reasons set forth below, the court finds that the government is entitled to summary judgment with regard to the default termination for failing to build the CBOC and that the grounds asserted by FHSHA for its failure to act do not constitute excuses as a matter of law. Because FHSHA’s failure to build the CBOC within the time provided for under the Lease justified a termination for default and the failure cannot be excused, the court does not reach the alternative grounds for summary judgment set forth in the government’s motion.

I. STATEMENT OF UNDISPUTED FACTS

The following facts are not disputed. Disputed facts relevant to FHSHA’s defense *641 that its failure to perform was “excused” are discussed in connection with those claims.

A. The Lease

The authority for the VA to enter enhanced-use leases (“EUL”) such as the Lease is set forth in 38 U.S.C. §§ 8161-8167. Pursuant to VA Handbook and Directive 7415, the VA Secretary assigned the Office of Asset Enterprise Management as the office within VA responsible for oversight of VA’s EUL program and management of enhanced-use projects identified as VA asset initiatives. Def.’s App’x 295-323, VA Handbook and Directive 7415.

1. Scope of the Lease

On September 28, 2006, FHSHA and VA entered into an EUL. The Lease identifies that FHSHA’s role is to serve as the “master developer of the Property, with the right and obligation to design, develop, construct, alter, operate, maintain, repair, replace, sublease, finance, improve and renovate the Property into the Project, and to demolish any existing buddings, structures and improvements on the Property, in accordance with the terms of this Lease.” Def.’s App’x 2. The Lease defines “Project” as “[t]he Lessee’s design, development, construction, demolition, alteration, operation, maintenance, repair, replacement, subleasing, financing, improvement, and renovation of the Property as provided in this Lease.” Pursuant to the Lease, the VA leased the “Property” to FHSHA for a term of 65 years, with a FHSHA option to extend for an additional 10-year period as long as an uncured Lessee Event of Default did not exist. The Lease defines “Property” as:

[t]hat certain real property consisting of approximately ninety (90) acres (i) as described and depicted in Exhibits A, with Attachment 1 to Exhibit A, and E attached hereto and includes (ii) all buddings, improvements, utilities and infrastructure either existing or erected or placed thereon, but: (1) will not include the CBOC Parcel and the CBOC when the CBOC Parcel and CBOC revert to VA upon the completion of construction and acceptance by the Department, in accordance with Article 4, paragraph A.4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
121 Fed. Cl. 636, 2015 U.S. Claims LEXIS 665, 2015 WL 3451759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fort-howard-senior-housing-associates-llc-v-united-states-uscfc-2015.