Brand Inv. Co. v. United States

58 F. Supp. 749, 102 Ct. Cl. 40
CourtUnited States Court of Claims
DecidedJune 5, 1944
Docket44617
StatusPublished
Cited by38 cases

This text of 58 F. Supp. 749 (Brand Inv. Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brand Inv. Co. v. United States, 58 F. Supp. 749, 102 Ct. Cl. 40 (cc 1944).

Opinions

MADDEN, Judge.

The plaintiff made a contract with the Government for the construction of a Post Office building at New Castle, Pennsylvania. While the work was under way, the Government issued a telegraphic stop order, which is quoted in finding 5. This stop order was not lifted for 113 days, and the plaintiff was actually stopped in its work for 109 days. It claims that the stop order with its consequent delay was a breach of the contract and seeks damages. The Government undertook, at the hearing before the commissioner of this court, the burden of justifying the stop order and its duration, but presented no evidence at all to sustain that burden. It therefore properly concedes that the stop order was, so far as the evidence shows, unjustified, and we have so found. Being unjustified, it was a breach of the contract.

The remaining questions in the case have to do with some items of alleged damages. The plaintiff asks for a part of the cost of maintaining its main office during the period of the delay, proportionate to the relation which this contract bore to the total amount of all of its then current contracts, plus a large additional amount to compensate for the fact that its executives devoted more' than a proportionate part of their time to attempts to get the New Castle job under way again during the period of the stop order. The Government urges that nothing should be allowed for main office expense, since it goes on regardless of what is happening on any or all of the contractor’s jobs.

We are allowing the plaintiff a proportionate part of its main office overhead. While such an element of damage can never be proved with mathematical precision, it is standard accounting practice to attribute main office expense to various company operations on some fair basis and we follow that practice. While it is probable that the plaintiff’s executives did devote more than a proportionate part of their time to the New Castle job during the period of the stoppage, the amount of that excess has not been proved with measurable definiteness.

The other disputed element of damage is the rental value of machines and equipment which the plaintiff had on the job, and which were necessarily kept idle during the period of the stop order. The plaintiff proved that machines of this type had a certain rental value. The Government urges that the plaintiff was not in the business of renting machines to others; that it would, probably, not have rented them even if they had not been tied up on this job by the indefiniteness of the duration of the stop order; that it has not shown that it had any other job on which it could have used them itself if they had not been tied to this job.

We think that the plaintiff is entitled to recover on this item of its claim. We do not allow the full amount of the rental value, since we recognize that, if rented, the machines would have suffered wear and tear which they did not suffer while idle on this job. But when the Government, in breach of its contract, in effect condemns a contractor’s valuable and useful machines to a period of idleness and uselessness, we think that it should make compensation comparable to what would be required if it took the machines for use for a temporary period, but did not in fact use them. As a jury verdict, we allow the proved .rental value, discounted by one-half because of the absence of actual use with its resulting wear and tear. We think that the contrary view expressed by the court in Phoenix Bridge Company v. United States, 85 Ct.Cl. 603, 631, should not be followed.

The plaintiff may recover $6,215.62.

It is so ordered.

WHALEY, Chief Justice, and WHITAKER, Judge, concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daff v. United States
39 Cont. Cas. Fed. 76,697 (Federal Claims, 1994)
C.B.C. Enterprises, Inc. v. The United States
978 F.2d 669 (Federal Circuit, 1992)
C.B.C. Enterprises, Inc. v. United States
978 F.3d 669 (Federal Circuit, 1992)
Colorado Environments, Inc. v. Valley Grading Corp.
779 P.2d 80 (Nevada Supreme Court, 1989)
Capital Electric Company v. The United States
729 F.2d 743 (Federal Circuit, 1984)
L'Enfant Plaza Properties, Inc. v. United States
31 Cont. Cas. Fed. 71,681 (Court of Claims, 1983)
W. G. Cornell Co. v. Ceramic Coating Co.
626 F.2d 990 (D.C. Circuit, 1980)
Inland Container, Inc. v. United States
512 F.2d 1073 (Court of Claims, 1975)
Southern New England Contracting Co. v. State
345 A.2d 550 (Supreme Court of Connecticut, 1974)
Williams v. Fixdahl
491 P.2d 1309 (Court of Appeals of Washington, 1971)
Law v. United States
195 Ct. Cl. 370 (Court of Claims, 1971)
Nolan Brothers, Inc. v. The United States
437 F.2d 1371 (Court of Claims, 1971)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
General Insurance v. Hercules Construction Co.
385 F.2d 13 (Eighth Circuit, 1967)
L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
58 F. Supp. 749, 102 Ct. Cl. 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brand-inv-co-v-united-states-cc-1944.