Walsh v. Methodist Episcopal Church

212 S.W. 950, 1919 Tex. App. LEXIS 772
CourtTexas Commission of Appeals
DecidedJune 21, 1919
DocketNo. 63-2806
StatusPublished
Cited by19 cases

This text of 212 S.W. 950 (Walsh v. Methodist Episcopal Church) is published on Counsel Stack Legal Research, covering Texas Commission of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh v. Methodist Episcopal Church, 212 S.W. 950, 1919 Tex. App. LEXIS 772 (Tex. Super. Ct. 1919).

Opinion

SONFIELD, P. J.

The Methodist Episcopal Church, South, of Paducah, Tex., and the trustees thereof, plaintiffs, brought action against E. L. Walsh and the Texas Fidelity Bonding Company, defendants, to recover damages sustained by plaintiffs through the failure of defendant Walsh to complete a church building in the town of Paducah, Tex., according to the terms of a written contract. The Texas Fidelity & Bonding Company was sued as surety on the bond of Walsh. The cause was tried to the court, and judgment rendered against defendants in the sum of $1,029.36, of which amount $840 Was for 84 days’ delay in completing the building after the stipulated time at the rate of $10 per day. On appeal, the judgment of the district court was affirmed as to defendant Walsh, and as to the surety company reversed and rendered. 173 S. W. 241. Writ of error was granted on the application of defendant Walsh.

The question for determination is, Should the provision for the payment or forfeiture of $10 for each day’s delay in completing the building after the specified date be construed as a stipulation for liquidated damages or as a penalty? The provision reads as follows:

“The contractor shall complete the several portions and the whole of the work comprehended in this agreement by and at the time or times hereinafter stated, to wit, September 1, 1913; and in the event the contractor fails to complete the same within the time specified, he forfeits the sum of $10.00 per day for every day it remains incomplete on his contract as liquidated damages; and party of the second part (the trustees) shall deduct the same out of the contract price if sufficient funds then remain in their hands; otherwise party of the first part to pay same at Padpcah, Texas, on demand.”

The Court of Civil Appeals held that the damages for failing to complete the church building within the time provided would necessarily be uncertain and their amount indeterminate; therefore the provision should be construed as fixing by stipulation the amount of the recovery; in other words, liquidated damages rather than a penalty.

In the view we take of the case, we deem it unnecessary to inquire into the correctness of this holding, being of opinion, upon an examination of the record, that the court reached a correct conclusion in construing this provision.

[1] In the Court of Civil Appeals defendant assigned as error the refusal of the trial court to permit the witness J. A. Lester to state what amount, if anything, plaintiff had paid out as rent for a building in which to hold public worship after the time the church building should have been completed under the terms of the contract and the time when it was actually completed, for the reason mentioned and set out in his bill of exception No. 1. The Court of Civil Appeals held the testimony irrelevant, the damages recoverable being the value of the use of the building during the time it should have been in use after September 1st. We concur in this holding.

Defendant’s first assignment in his application for writ of error herein is as follows:

“The Court of Civil Appeals erred in sustaining the objections of plaintiffs and thereby refusing to permit the witness, J. A. Lester, to state what amount, if anything, plaintiff had paid out as rent for a building in which to worship after the time said church building should have been completed under the terms of the contract and the time when it was actually completed, and Hie probable rental value of said clvurch.”

The italicized portion of this assignment of error does not appear in the assignment presented to the Court of Civil Appeals, nor does the bill of exception show any effort on the part of defendant to prove by the witness the probable rental value of the church. Had defendant proven or sought to prove rental value, a different case would have been presented.

Defendant did not plead that the provision in the contract for liquidated damages was intended as a penalty, or that there was no approximation between the stipulated amount and the actual damages suffered, nor was there any evidence of the amount of actual damages.

In Collier v. Betterton, 87 Tex. 440, 29 S. W. 467, in refusing a writ of error, the Supreme Court discussed the question of liquidated damages passed upon'by the Court of Civil Appeals.

In that case, suit was brought to recover a balance due under a building contract. The contract stipulated that the building should be completed by the 1st day of October, 1889, failing in which contractor should pay to Collier, the owner, as liquidated damages, $10 per day for every day the completion should be delayed. Defendant Collier in his answer prayed damages for delay in the completion of the house, as a counterclaim, relying solely, so far as shown by the record before the Supreme Court, upon a stipulation in the contract as fixing the amount. The trial judge charged the jury, in effect, to allow the defendant damages upon his counterclaim at the rate of $10 a day from October 1, 1889, to November 12, 1889, the time at which defendant entered and occupied a part of the house. Pursuant to the instruction, the jury found for the defendant $420 offset against the balance otherwise due on the contract price, and gave verdict for the plaintiff for the difference. In passing upon the question of the correctness of the ruling of the trial court, the Court of Civil Appeals said:

[952]*952“We do not think the action of the trial court upon this issue can be complained of by the appellant. We think the stipulation in the contract for $10 per day as liquidated damages for each day of deiay in the completion of the building should have been construed and treated as a penalty. * * * Under such a construction there was not proof of damages to the extent of the recovery, and the appellant [Collier] suffered no injury from the charge as given.”

The Supreme Court, discussing the construction of the provision with reference to damages, said:

“The principle would appear to be that although a sum be named as ‘liquidated damages,’ the courts will not so treat it, unless it bears such proportion to the actual damages that it may reasonably be presumed to have been arrived at upon a fair estimation by the parties of the compensation to be paid for the prospective loss. If the supposed stipulation greatly exceed the actual loss — if there be no approximation between them, and this being made to appear by the evidence — then it seems to us, and then only, should the actual damages be the measure of the recovery.”

Applying the rules of law to the facts in that case, the court continued:

“In this case as presented to us there is no evidence by which the actual damage resulting from the failure to complete the building at the time stipulated can be ascertained, ten dollars per day is apparently a very large sum to pay for the rent of a house which cost $5,670 to construct; but we do not know the value of the lot. Nor is it clear, that, even if the evidence disclosed the entire value of the property, we would be justified in assuming even approximately, its rental value. Such being the state of the case, we are not prepared to concur in the ruling of the Oourt of Oivil Appeals upon the point just discussed.”

[2] The contract price of the church building to be erected was $5,200.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips v. Phillips
820 S.W.2d 785 (Texas Supreme Court, 1992)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Johnson Engineers, Inc. v. Tri-Water Supply Corp.
582 S.W.2d 555 (Court of Appeals of Texas, 1979)
Oetting v. Flake Uniform & Linen Service, Inc.
553 S.W.2d 793 (Court of Appeals of Texas, 1977)
Smith v. Lane
236 S.W.2d 214 (Court of Appeals of Texas, 1950)
Brand Inv. Co. v. United States
58 F. Supp. 749 (Court of Claims, 1944)
White v. Wilbanks
144 S.W.2d 941 (Court of Appeals of Texas, 1940)
Employers' Liability Assur. Corp. v. Eckert
46 S.W.2d 464 (Court of Appeals of Texas, 1932)
Constitution Indemnity Co. of Philadelphia v. Armbrust
25 S.W.2d 176 (Court of Appeals of Texas, 1930)
Schwarz v. Lee
287 S.W. 519 (Court of Appeals of Texas, 1926)
Pace v. Olvey
282 S.W. 940 (Court of Appeals of Texas, 1926)
American Nat. Bank of Wichita Falls v. Haggerton
250 S.W. 279 (Court of Appeals of Texas, 1922)
McElroy v. Danciger
241 S.W. 1098 (Court of Appeals of Texas, 1922)
Long v. Martin
234 S.W. 91 (Court of Appeals of Texas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
212 S.W. 950, 1919 Tex. App. LEXIS 772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-v-methodist-episcopal-church-texcommnapp-1919.