Walsh v. Methodist Episcopal Church South, of Paducah

173 S.W. 241, 1915 Tex. App. LEXIS 134
CourtCourt of Appeals of Texas
DecidedJanuary 2, 1915
DocketNo. 700. [fn†]
StatusPublished
Cited by19 cases

This text of 173 S.W. 241 (Walsh v. Methodist Episcopal Church South, of Paducah) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh v. Methodist Episcopal Church South, of Paducah, 173 S.W. 241, 1915 Tex. App. LEXIS 134 (Tex. Ct. App. 1915).

Opinion

HUFF, C. J.

The appellees, the Methodist Episcopal Church South, of Paducah, Tex., and others, the trustees thereof, instituted this suit against the appellants, E. L. Walsh and the Texas & Fidelity Bonding Company, on the 18th day of March, 1914, to recover damages for breach of contract alleged by ap-pellees to have been sustained by them on the ground that appellant E. L. Walsh failed to complete a one-story brick-veneered church building in the town of Paducah, Tex., according to the terms of a valid written contract. It is alleged substantially that the contract was made and entered into by and between E. L. Walsh, as principal, and the Texas Fidelity & Bonding Company, as sureties, being the parties of the first part, and the Methodist Episcopal Church South, of Paducah, Tex., and its trustees, parties of the second part, on the 17th day of May, 1913, and said building was to be completed by the 1st day of September, 1913; and appellees allege that said building was not completed for 105 days thereafter, and that said appellants were to pay the sum of $10 per day as liquidated damages for every day of delay 'after said September 1, 1913; and also for breach of contract in failing to furnish sufficient labor and material and to pay for the same, to complete the church, and that the appellees were compelled to discharge the items for material to the amount over and above the contract price of the sum of $200, asking for judgment for the full amount of $1,250.

The appellants answered generally and specially, which will not be necessary to set out in detail.

[1] First the appellees object to the consideration of assignments 1 to 11, inclusive, and present the proposition that courts will not consider the assignments of error filed in the lower court to the conclusions of law and fact filed by the court trying the cause in the absence of a motion for new trial, calling die court’s attention to such error of fact and law committed by the trial court, and prepare bills of exceptions to such findings of fact and conclusions of law as found by the court. This court held in the cause of Cornelius v. Harris, 163 S. W. 346, that it was not necessary in a trial had before a court without a jury to file a motion for new trial in order to file assignments of error calling in question the sufficiency of the evidence as a question of law to support the judgment. In American, etc., v. Mercedes, etc., 155 S. W. 286, the same conclusion was reached, even before the amendment of article 1612 by the Thirty-Third Legislature and the addition to the rules of rule 101a (159 S. W. xi) by the Supreme Court. The appellants, in the judgment entry, had noted therein their exceptions to the findings of fact and conclusions of law filed by the court, and also excepted to the judgment of the court. We think this sufficient. Smith v. Abadie, 67 S. W. 1077; Brenton v. Peck, 39 Tex. Civ. App. 224, 87 S. W. 898; Supreme, etc., v. Ericson, 131 S. W. 92; Bond v. Garrison, 127 S. W. 839, bottom page 843, top 844; Edwards v. Youngblood, 160 S. W. 288. In this record there are bills of exceptions, state *243 ments of facts, as well as findings of the trial court. Where this is true we do not understand it to be necessary to file exceptions to the findings of the trial court. Tudor v. Hodges, 71 Tex. 392, 9 S. W. 443 Gillespie v. Crawford, 42 S. W. 621-625. The Supreme Court, in the case of Insurance Co. v. Milliken, 64 Tex. 48, gives the reason for the exceptions to the findings of the trial court. When made, the opposite party must take notice of it, and, if the findings are not as full as they should be, it will be Ms right to have a statement of facts, or, in other respects, have a complete presentation of the case. We do not understand the revision of 1911 to have changed the rule as it heretofore existed under old article 1333. This article is brought forward in the revision as articles 1987-1991, inclusive.

[2] The first and second assignments are overruled. The motion to quash the service of the citation we do not think good in the first place, and, further, it appears the appellants answered thereto. The application for continuance does not show sufficient diligence. The court’s reason given for overruling the motion justified the action of the court.

[3] The third and eighth assignments assert the proposition that the contract authorT izing a recovery as liquidated damages the sum of $10 per day after September 1, 1913, was a penalty, and not a liquidated demand. The article of the contract upon which the suit was based is as follows:

“The contractor shall complete the several portions and the whole of the work comprehended in this agreement by and at the time or times hereinafter stated, to wit, September 1st, 1913; and in the event the contractor fails to complete the same within the time specified, he forfeits the sum of $10.00 per day for every day it remains incomplete on his contract as liquidated damages; and party of the second part (the trustees) shall deduct the same out of the contract price if sufficient funds then remain in their hands; otherwise party of the first part to pay same at Paducah, Texas, on demand.’’

This is a contract to build a church according to certain plans and specifications, and to complete the same by the 1st day of September, 1913. The damages for failing so to complete the building would necessarily be uncertain and difficult to arrive at under the ordinary rules of law. The compensation for the breach was evidently fixed in consequence of the difficulty in ascertaining the damages. Indianola v. Railway Co., 56 Tex. 606-608; City of Marshall v. Atkins, 127 S. W. 1151.

[4] It has been held that contracts to pay a certain sum per day after a given time can be recovered as a liquidated demand. Collier v. Betterton, 87 Tex. 440, 29 S. W. 467; Brown Iron Co. v. Norwood, 69 S. W. 253; Orenbaum Bros. v. Sewell, 153 S. W. 905. Especially is this the rule where the damages are difficult of ascertainment. In this case appellaoA sought to prove that the church used the courthouse and a church belonging to another denomination, without paying anything for the use thereof, and here urges no damages were sustained by the ap-pellees. This testimony we think irrelevant. The question would be the value of the use of the building during the time it should have been in use after September 1st. This case certainly falls under the rule above stated. We think from the contract the intention of the parties is clearly expressed to pay $10 per day as a liquidated sum. It is stipulated that the same shall be deducted from the contract price if sufficient funds remain in the hands of the trustees; otherwise the contractor was to pay the sum on demand. We see no room to construe a different meaning from the one expressed in the contract, especially under the particular circumstances of the subject-matter of the agreement. Yetter v. Hudson, 57 Tex. 604; Eakin v. Scott, 70 Tex. 442, 7 S. W. 777; Orenbaum v. Sewell, 153 S. W. 905, and authorities cited. These assignments will be overruled.

[5, 6] The fourth, sixth, and seventh assignments present error in the action of the court in admitting certain carbon copies of letters from parties representing the appellees to the Texas Fidelity & Bonding Company, during the month of December, 1913, and January, 1914.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morgenroth v. First State Bank
66 S.W.2d 458 (Court of Appeals of Texas, 1933)
Hill v. State
59 S.W.2d 411 (Court of Criminal Appeals of Texas, 1933)
Employers' Liability Assur. Corp. v. Eckert
46 S.W.2d 464 (Court of Appeals of Texas, 1932)
Schwarz v. Lee
287 S.W. 519 (Court of Appeals of Texas, 1926)
Pace v. Olvey
282 S.W. 940 (Court of Appeals of Texas, 1926)
Citizens' Guaranty State Bank of Hutchins v. National Surety Co.
258 S.W. 468 (Texas Commission of Appeals, 1924)
Citizens' Guaranty State Bank of Hutchins v. National Surety Co.
242 S.W. 488 (Court of Appeals of Texas, 1922)
Texas Glass & Paint Co. v. Fidelity & Deposit Co. of Maryland
226 S.W. 811 (Court of Appeals of Texas, 1920)
Givens v. Turner
225 S.W. 403 (Court of Appeals of Texas, 1920)
Travelers' Ins. Co. of Hartford v. Scott
218 S.W. 53 (Court of Appeals of Texas, 1919)
Walsh v. Methodist Episcopal Church
212 S.W. 950 (Texas Commission of Appeals, 1919)
American Indemnity Co. v. Board of Trustees
200 S.W. 592 (Court of Appeals of Texas, 1918)
De Bruin v. Santo Domingo Land & Irrigation Co.
194 S.W. 654 (Court of Appeals of Texas, 1917)
Goodman v. W. S. Peck & Co.
192 S.W. 785 (Court of Appeals of Texas, 1917)
Craver v. Greer
178 S.W. 699 (Court of Appeals of Texas, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
173 S.W. 241, 1915 Tex. App. LEXIS 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-v-methodist-episcopal-church-south-of-paducah-texapp-1915.