Hiller v. Daman

166 S.W. 869, 183 Mo. App. 315, 1914 Mo. App. LEXIS 486
CourtMissouri Court of Appeals
DecidedMay 5, 1914
StatusPublished
Cited by6 cases

This text of 166 S.W. 869 (Hiller v. Daman) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hiller v. Daman, 166 S.W. 869, 183 Mo. App. 315, 1914 Mo. App. LEXIS 486 (Mo. Ct. App. 1914).

Opinion

NORTONI, J.

This is a suit for damages alleged to have accrued through several breaches of a building contract. Plaintiff recovered and defendant prosecutes the appeal.

Plaintiff is the owner of the buildings, and defendant William Daman is the contractor, while defendants John C. Timmerberg and Maggie Daman are sureties on his bond for the faithful performance of the contract.

A jury was waived, and the case tried before the court, which found the issue for plaintiff and gave judgment against all the defendants, from which they jointly prosecute the appeal. The contractor, Mr. Daman, interposed a counterclaim for certain alleged extra work, but the finding and judgment were for plaintiff and against him on that as well.

It appears that the items involved in the counterclaim pertain to certain matters covered in the contract for which compensation has been made in accordance with the contract terms, and, therefore, it will be unnecessary to consider the counterclaim separate and apart from the question arising in plaintiff’s case.

There are a number of points made in the brief for a reversal of the judgment, hut it will not be necessary to discuss them all. Some of them are obviously without merit and others are concluded by our view of the contract and the obligation it imposes.

[324]*324It appears that on April 20, 1908, defendant William Daman entered into a written contract with Frank A. J. Hiller, whereby he agreed to provide all of the materials and perform all of the work for the completion of two two-story brick buildings situate on a lot at the southwest corner of Clayton and Taylor avenues in St. Louis. One of the buildings contemplated in the contract was designed for a store building with flats overhead, while the other was a double flat building. The buildings were to be constructed in accordance with the plans and specifications prepared by Victor J. Klutho, architect for the owner.

By article 4 of the contract, it is stipulated that the store and flat building should be completed and possession given to the owner on or before August 1,1908, and the double flat building to be completed and given over to the owner on or before August 20, 1908.

By article 9 of the contract, the price to be paid the contractor for the excavations and the buildings is agreed upon at $14,943, to be paid upon the certificate of the architect on or about the first day of each month—that is, payments equal to ninety per cent of the value of the work performed during the preceding month to be then due and payable. However, the same 9th article of the contract further provides as follows: “It is hereby understood and agreed between the parties that in case filled ground is encountered, prices for extra work to be as follows: Excavation, 75 cents per yard at single measurement. Concrete work, 22 cents per cubic foot. Rubble masonry, $4 per perch.” In excavating the cellars for the buildings, filled ground was encountered by the contractor, and it became nece’ssary for him to proceed to a considerable depth by sinking a number of wells and erecting concrete pillars therein. The prosecution of this work was delayed some by frequent rains, until, all in all, several weeks of time were consumed before the foundations were completed. A considerable controversy in the [325]*325case arises on this matter, for it is said by defendant contractor that snch was extra work which operated to extend the time for the completion of the buildings, while it is asserted on the part of plaintiff that such was work contemplated in the contract, and that no extension of time may be had therefor at any rate, for the reason the contractor laid no claim thereto under the 7th article of the contract, which imposed this obligation upon him. Moreover, it is asserted on the part of defendant sureties that such additional work on foundations was extra work, beyond the pale of the contract, the performance of which destroyed its identity and, therefore, discharged them. On the other hand, it is asserted by plaintiff that such extra work being expressly mentioned and provided for in the contract, in case filled ground was encountered, it was within the contemplation of all the parties, and, therefore, it was, though its precise. extent was unknown, a part of the very contract to which the sureties assented upon signing the bond.

The petition is in four counts, but the court found the issue for defendants and gave judgment in their favor on the first count, and that matter will not be further noticed.

In the second count of the petition, the breach assigned relates to the failure of the contractor to install plate glass mirrors for the medicine cases in each of the bathrooms contained in the buildings. Such mirrors were required, according to the plans and specifications, and the breach touching this matter seems to be conceded. It appears the contractor installed inferior mirrors in the medicine cases in eight bathrooms, and it is said the value of each is two dollars less than the mirrors called for in the contract. The court found the issue for plaintiff touching this matter and awarded him damages to the amount of fifteen dollars. The evidence supports the finding, and it may be put aside without further consideration.

[326]*326Among other things, the 9th article of the contract provides substantially that, should there prove to be any claim which may be established by mechanic’s lien against the buildings, or either of them, after all payments are made by the owner, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging’ it. After the owner had paid the contractor all moneys due him, save $43.17, one Ehle, the plasterer, a subcontractor, served notice on plaintiff that there was a balance due him for plastering of $139.94 and also toot steps to establish a mechanic’s lien on the buildings by serving notice to that effect. Plaintiff thereupon paid this entire claim, under the provision of the contract last quoted, in order to prevent the accrual of costs, and there seems to be no controversy in the case with respect to the fact that the balance of $139.94 was due the plasterer and that it was paid by plaintiff as above stated. The breach declared upon in the third count of the petition relates to this matter, and it proceeds to recover $139.94 so paid to Ehle, the plasterer.

The court found the issue for plaintiff on this count, but deducted therefrom the balance due the contractor and then in the hands of plaintiff—that is, $43.17—and gave judgment for plaintiff for the remainder. This finding and judgment are amply supported by the evidence and seem to be well enough in every respect, but defendant argues that plaintiff should not recover therefor because the contract says the amount is to be refunded if paid on “any such claim after all payments are made to the contractor.” Because there remained $43.17 in the hands of the owner due the contractor, it is said the payment of the plasterer’s bill was premature, but, obviously, this argument is without merit. It is highly technical and without substance, for it is conceded that the plasterer’s bill of $139.94 was unpaid and that plaintiff paid it in order to prevent a lien from being established against [327]*327the buildings, and this, too, after the lien notice was served upon him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herbert & Brooner Construction Co. v. Golden
499 S.W.2d 541 (Missouri Court of Appeals, 1973)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Leigland v. Rundle Land & Abstract Co.
208 P. 1075 (Montana Supreme Court, 1922)
Wm. P. Jungclaus Co. v. Ratti
118 N.E. 966 (Indiana Court of Appeals, 1918)
Walsh v. Methodist Episcopal Church South, of Paducah
173 S.W. 241 (Court of Appeals of Texas, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
166 S.W. 869, 183 Mo. App. 315, 1914 Mo. App. LEXIS 486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hiller-v-daman-moctapp-1914.