Ward v. Haren

119 S.W. 446, 139 Mo. App. 8, 1909 Mo. App. LEXIS 450
CourtMissouri Court of Appeals
DecidedMay 25, 1909
StatusPublished
Cited by22 cases

This text of 119 S.W. 446 (Ward v. Haren) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ward v. Haren, 119 S.W. 446, 139 Mo. App. 8, 1909 Mo. App. LEXIS 450 (Mo. Ct. App. 1909).

Opinion

NORTONI, J. —

This is a suit for the balance due on a building contract. The contract contained a stipulation that if the building was not completed by the plaintiff on the 15th day of April, he would pay liquidated damages at the rate of one hundred and twenty dollars per day for the delay thereafter. The balance due plaintiff for the work seems to be conceded. The only controversy in the case is in respect of defendant’s right to liquidated damages. The defendant’s answer avers that plaintiff defaulted twelve days in completing the building, and prays for liquidated damages under the contract at the rate of one hundred and twenty dollars per day, the total claim for liquidated damages being $1,440. In reply, plaintiff concedes the stipulation in ,the contract touching liquidated damages, but avers the provision referred to was waived or the time extended because of an alteration or extra work ordered by the defendant in the roof of the building. The circuit court accepted the theory of the plaintiff and denied the defendant’s right of recovery on his counterclaim. Judgment having been given for the plaintiff, the defendant appeals.

It appears from the written contract in evidence that on February 23, 1904, plaintiff agreed and undertook to erect for the defendant a temporary building of considerable proportions immediately adjacent an important entrance to the grounds of the Louisiana Purchase Exposition, according to plans .and specifications therein mentioned. The consideration to be paid therefor was $8,120. It is conceded in the case that the building was to be erected solely for World’s Fair purposes; that is to say, to be rented by the defendant to tenants during the period of the World’s Fair. It was desirably located with respect to the Fair and its rental value was a high prospect. The Louisiana Purchase Exposition or World’s Fair was scheduled to open May 1,1904. In view of this fact, the parties stipulated that unless the building was completed by April 15th, the [11]*11plaintiff contractor would pay the defendant as liquidated damages the sum of one hundred and twenty dollars per day for each and every day he was in default in completing the building after that date. Touching this matter, it was further stipulated that if the building was completed prior to April 15th, plaintiff contractor should have one-half of the rents accruing theretofore, not exceeding in all $400. There is no question in the case as to whether the amount of one hundred and twenty dollars per day is disproportionate, when considered with reference to the actual damage the defendant might suffer in event the building was not completed on the date mentioned; that is, as to whether the amount stipulated is liquidated damages or penalty. The amount appears to have been admitted upon the trial to he liquidated damages stipulated in view of the extraordinary circumstance of the World’s Pair period. This matter will therefore not be considered.

As before stated, to relieve himself from his obligation to pay liquidated damages, the plaintiff relied upon the fact that defendant ordered certain extra work in changing the roof of the building which he had contracted to erect. The contract was entered into February 23rd; the building to be completed April 15th'. During the peri.od when the building was under construction, and on March 18th, defendant ordered a change in the roof of the building in this: the contract required the roof to be constructed of corrugated iron, and the defendant desired instead a tile roof. Plaintiff contractor agreed to substitute tile and do the extra work for the additional sum of $200. This was agreed to by the parties and the building constructed accordingly. It appears the change in roofing referred to delayed the contractor in his work several days. The parties, however, made no new stipulation with respect to the time limit in which the building should be completed. An extension of time on account of the change in roofing was neither stipulated nor discussed. The argument [12]*12on behalf of plaintiff is not that the deféndant agreed to extend the time, but that the alteration or extra work ordered, operated as an act of the defendant owner to impede or delay the work, which therefore released him from his obligation to complete the building by April 15th. Or in other words, the act of the owner in ordering the extra work, ipso facto, operated a waiver of the time limit stipulated in the' contract. From the contract before us, there appears to be no provision whatever by which the duty of making alterations or changes in the building is imposed upon the contractor; that is to say, the plaintiff contractor did not, by his contract, so completely place himself within the power of the defendant owner as to be obligated to make alterations in or do extra work on the building by the mere order of the defendant owner or his agent, the architect. Plaintiff contractor was free to make alterations or do extra work at the suggestion of the owner for additional compensation or to decline to do so, as he saw fit. There are cases where the owner has reserved to himself, by contract, the power of ordering alterations or extra work on the building, and the contractor is obligated to the performance of such orders, without the right to demand an extension of time for the completion of the work. In such circumstances, the doctrine obtains to the effect that where the owner orders additional work which the contractor may not refuse to do, and thus delays the completion of the building, the act of the owner in thus ordering the extra work operates to waive or extend the time within which the building should be completed. This for the reason the contractor being completely subservient to the owner under the contract, is compelled to do his bidding and therefore the law, in refusing to tolerate the exaction of that which is impossible, implies relief from the obligation as to time. The law declines to tolerate an arbitrary exercise of the power thus vested in the owner which would result in mulcting the contractor in damages for failing to com[13]*13píete the building within the time originally provided when the owner knew at the time of ordering the alteration that it was impossible to complete the work without an extension. For noted authorities and leading lights upon this doctrine see the English cases of Westwood v. Secretary of State for India, 11 Weekly Reporter & Digest, 261, and Dood v. Churton, 1 Q. B. Rep. 562; 45 Weekly Rep. & Digest, 490. See also the following American authorities in point: Small v. Burke, 92 N. Y. (App. Div.) 338; Ramsburg v. McCahan, 3 Gill. (Md.) 340; Lauer v. Brown, 30 Barb. (N. Y.) 416; Smith v. Gugerty, 4 Barb. (N. Y.) 614; Wright v. Meyer (Tex. Civ. App.), 25 S. W. 1125. For an instructive article see Vol. 41, Solicitors’ Journal, page 589.

In affirmance of the general doctrine that the contractor is released from his obligation to complete the building within the time specified by an act of the owner which impedes or delays his performance, see the follorving authorities in point: Holme v. Guppy, 3 M. & W. Rep. 389; Thornhill v. Neats, 8 C. B. Rep. 830; Russell v. Viscount La De Bandeira, 13 C. B. Rep. 148; Close v. Clark, 16 Daly’s Rep. (N. Y.) 91; Dannat v. Fuller, 120 N. Y. 554; Eldridge v. Fuhr, 59 Mo. App. 44; Van Buren v. Digges, 52 U. S. 461, 11 How. 461; 30 Am. and Eng. Ency. Law (2 Ed.), 1255, 1256.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gaunt v. Shelter Mutual Insurance Co.
808 S.W.2d 401 (Missouri Court of Appeals, 1991)
Statler Manufacturing, Inc. v. Brown
691 S.W.2d 445 (Missouri Court of Appeals, 1985)
Three-O-Three Investments, Inc. v. Moffitt
622 S.W.2d 736 (Missouri Court of Appeals, 1981)
Howard v. Nicholson
556 S.W.2d 477 (Missouri Court of Appeals, 1977)
Kansas City, Missouri v. Kansas City, Kansas
393 F. Supp. 1 (W.D. Missouri, 1975)
Herbert & Brooner Construction Co. v. Golden
499 S.W.2d 541 (Missouri Court of Appeals, 1973)
MFA Mutual Insurance Co. v. Farmers & Merchants Insurance Co.
443 S.W.2d 220 (Missouri Court of Appeals, 1969)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
Missouri Pacific Railroad Company v. Terrell
410 S.W.2d 356 (Missouri Court of Appeals, 1966)
Peter Kiewit Sons' Co. v. Pasadena City Junior College District
379 P.2d 18 (California Supreme Court, 1963)
Austin-Griffith, Inc. v. Goldberg
79 S.E.2d 447 (Supreme Court of South Carolina, 1953)
Ellis Gray Milling Co. v. Sheppard
222 S.W.2d 742 (Supreme Court of Missouri, 1949)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Lehigh Portland Cement Co. v. Virginia Steamship Co.
111 S.E. 104 (Supreme Court of Virginia, 1922)
Cowles v. J. C. Mardis Co.
192 Iowa 890 (Supreme Court of Iowa, 1921)
Wm. P. Jungclaus Co. v. Ratti
118 N.E. 966 (Indiana Court of Appeals, 1918)
Ward v. Haren
167 S.W. 1064 (Missouri Court of Appeals, 1914)
Hiller v. Daman
166 S.W. 869 (Missouri Court of Appeals, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
119 S.W. 446, 139 Mo. App. 8, 1909 Mo. App. LEXIS 450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ward-v-haren-moctapp-1909.