Eldridge v. Fuhr

59 Mo. App. 44, 1894 Mo. App. LEXIS 391
CourtMissouri Court of Appeals
DecidedOctober 9, 1894
StatusPublished
Cited by16 cases

This text of 59 Mo. App. 44 (Eldridge v. Fuhr) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eldridge v. Fuhr, 59 Mo. App. 44, 1894 Mo. App. LEXIS 391 (Mo. Ct. App. 1894).

Opinion

Biggs, J.

This is an action on a contractor’s bond. The defendant Euhr entered entered into a written contract with the plaintiff, in which he agreed to furnish the materials and do the work (except excavation for foundation walls and cellar) in the construction of a brick building. The contract price was $4,000, to be paid in installments as the work progressed, except the last payment of $500 which was not to be paid until the completion of the building, according to contract. To secure the plaintiff in the faithful performance of this contract the defendant Euhr as principal, .and his codefendants as sureties, executed and delivered the bond in suit.

The petition sets forth in three counts various alleged breaches of the bond. In the first count it was charged that Euhr had failed in several particulars to construct the building in conformity with the contract and specifications; in the second, that he had failed to complete the building within the time prescribed; and in the third, that he had failed to deliver the building free of all-liens and claims. The aggregate amount of damage claimed is $1,823.02, less the sum of $500, balance of contract price.

The sureties filed a separate answer, in which, among other things, they alleged that the original contract had in several particulars been materially changed without their knowledge and consent, and that by reason thereof they were released from their obligation. The separate answer of Euhr was a general denial. It also contained averments as to the changes or alterations alleged in the answer of the sureties, and, in addition, set forth a counterclaim for $608.40, the value of extra work resulting from changes alleged to have been ordered by the plaintiff in the original plans. Eor that [47]*47amount, and the said sum of $500 due under the original contract, a judgment was asked.

In the replication the plaintiff admitted that by his consent and direction the original contract had been departed from by adding two extra doors, the construction of a skylight, and the use of three barrels of cement, of the total value of $52.70. For this amount it was conceded that Fuhr was entitled to credit. All other new or affirmative matter in both answers was denied.

At the conclusion of 'the evidence the court on its own motion instructed the jury as follows: “The court instructs the jury that under the law, pleadings, admissions and evidence in the case, the plaintiff is not entitled to recover on the first and second counts in his petition; and that on the third count plaintiff is entitled to recover the amount paid out by him in excess of the contract price, less the $52.70 admitted in the plaintiff’s replication to be an offset in favor of the defendants, with six per cent, per annum interest thereon from March 31, 1893.” Under this instruction the jury returned a verdict for the plaintiff for $509, upon which judgment was entered. All parties filed motions for new trial, and all have appealed.

o As we are of opinion that, under the conceded facts, the judgment as to the sureties must be reversed, we will dispose of that matter first.

Section 3 of the contract reads: “Should any alteration be required in the work, as described by the drawings or specifications, a fair and reasonable valuation of the work added or omitted shall be made by the architect, and the sum herein agreed to be paid for the work according to the original specifications shall be increased or diminished as the case may be. In case such a valuation is not agreed to, the contractor shall proceed with the alteration upon the. written order of [48]*48the owner, and the valuation of the work added or omitted shall be referred to three (3) arbitrators (no one of whom shall be personally connected with the work to which these presents refer), to be appointed as follows: One by each of the parties to this contract and the third by the two thus chosen; the decision of any two of whomshall be final andbinding, and each of theparties hereto shall pay one-half of the expenses of such reference.” The specifications, which are expressly made a part of the contract, contain the following: “The owner reserves the right * * * to order, through the architect, any change in the work without impairing the contract, the value of such changes to be mutually agreed on in writing between the architect and contractor beforehand. In default of such agreement, the architect will fix such valuations.”

The plaintiff, in his replication and testimony, admitted that the door and skylight had been added on his verbal order, and that the three barrels of cement were not included in the contract, and that, under the decision of the architect beforehand, he agreed to pay for the same as extra materials. It was conceded by the plaintiff that neither he nor the architect had agreed with Ruhr as to the cost of the extras, and that the architect had not fixed or attempted to fix the cost thereof. By the express terms of the contract, the plaintiff reserved the right, by the observance of certain formalities, to order changes in the building. If these formalities had been observed, it is clear that the original contract would have been in no way changed, and the sureties would have remained bound. But it is undisputed that, in ordering the additions, the contract was disregarded. Did this release the sureties? Let us examine the question in the light of recent adjudications in this state.

In the recent case of Beers v. Wolf, 116 Mo. 179, [49]*49the supreme court had under consideration the same question, which arose under a similar state of facts. There the building contract contained the following clauses: “The superintendent shall be at liberty to make any deviation from, or alteration in, the plan, form, construction, detail and execution described by-the drawings and specifications, without invalidating or rendering void this contract, and, in case of any difference in the expense, an addition to or abatement from the contract price shall be made, and the same shall be determined by the architect; and in case any such alteration or change shall be made or directed by the said superintendent as aforesaid in the plans, drawings and construction of the aforesaid building, and in case of any omission or addition to said building being required by spid superintendent, the cost and expense thereof is to be agreed upon in writing, and such agreement is to be signed by said parties of the second part and superintendent before the same is done, or before any allowance therefor can be claimed; and, in case of any failure to so agree, the same shall be completed on the original plan.” It appeared that various changes had been made in the work, but that, in making the changes, the conditions of the contract had not been observed, and there was no evidence that the sureties consented to the changes. The court held that the sureties were released.

In the case of Killoren v. Meehan, 55 Mo. App. 427, we had the same question under consideration. The building contract in that case contained the following clause: “The superintendent shall be at liberty to make any deviation from, or alteration in, the plan, form, construction, detail and execution described by the drawings and specifications, without invalidating or rendering void this contract, and in case of any dif[50]*50ference in the expense, an addition to, or abatement .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Equitable Surety Co.
167 N.W. 292 (Supreme Court of Minnesota, 1918)
J. S. Mayfield Lumber Co. v. Mann
1916 OK 752 (Supreme Court of Oklahoma, 1916)
Bird v. Steele
132 P. 724 (Washington Supreme Court, 1913)
Lazelle v. Empire State Surety Co.
109 P. 195 (Washington Supreme Court, 1910)
Heidbrink v. Schaffner
127 S.W. 418 (Missouri Court of Appeals, 1910)
Ward v. Haren
119 S.W. 446 (Missouri Court of Appeals, 1909)
Pittsburg Bridge Co. v. St. Louis Transit Co.
116 S.W. 467 (Missouri Court of Appeals, 1909)
Martin v. Whites
106 S.W. 608 (Missouri Court of Appeals, 1907)
Reissaus v. Whites
106 S.W. 603 (Missouri Court of Appeals, 1907)
Alcatraz Etc. Assn. v. U.S. F. Etc. Co.
85 P. 156 (California Court of Appeal, 1906)
Alcatraz Masonic Hall Ass'n v. United States Fidelity & Guaranty Co.
3 Cal. App. 338 (California Court of Appeal, 1906)
Huber v. St. Joseph's Hospital
83 P. 768 (Idaho Supreme Court, 1905)
Cann v. Rector of Church of the Redeemer
85 S.W. 994 (Missouri Court of Appeals, 1905)
Bagwell v. American Surety Co.
77 S.W. 327 (Missouri Court of Appeals, 1903)
Fullerton Lumber Co. v. Gates
89 Mo. App. 201 (Missouri Court of Appeals, 1901)
United States v. Freel
92 F. 299 (U.S. Circuit Court for the District of Eastern New York, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
59 Mo. App. 44, 1894 Mo. App. LEXIS 391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eldridge-v-fuhr-moctapp-1894.