Bruns v. Braun

35 Mo. App. 337, 1889 Mo. App. LEXIS 181
Missouri Court of Appeals·Decided April 2, 1889·Published·Cited by 20 cases

Opinion

Biggs, J.,

delivered the opinion of the court.

This is an action to enforce a mechanic’s Hen for work done and material furnished in the reconstruction or repairing of a certain building situated on lots 14 and 15, in block 544, Carr’s addition to the city of St. Louis, held by defendant Braun under a lease from one Bernard Luethemeyer. The plaintiff filed his account and statement for a mechanic’s lien, as an original contractor, with the clerk of the circuit court on the [341] sixteenth day of March, 1887. The account and statement as filed showed, that the amount due plaintiff for work and materials furnished in making the improvements on the building, was $770.43, and that the work was begun on the twenty-fifth day of August, 1886, and was completed on the eighteenth day of September, 1886. The building repaired by plaintiff was used as a theatre, and the defendant Braun and Joseph L. Frasier, his co-tenant, were running the house under the firm of name of Philip Braun & Co. It appears from the pleadings and evidence, that the plaintiff first contracted with defendants to tear down and remodel the second story of the building in a certain way then agreed upon, which contemplated the use entirely of wooden materials, for which defendant agreed to pay plaintiff the sum of five hundred and thirty-five dollars. This contract was entered into on the twenty-fifth day of August, 1886. The plaintiff began work under this contract, and while at work on the building, the city authorities interfered, and objected to some of the materials used in the building, and defendants were then compelled to take out a building permit, issued by the city, by which the defendants were compelled to change their plans and use stone and brick in making some parts of the changes in said building. The plaintiff ’s testimony shows that thereupon, the defendants instructed him to make the changes and additions to the original plan, and agreed with him that this would increase the cost of the improvement in the sum of two hundred and sixty-eight dollars, which they agreed to pay plaintiff. The defendant Braun denied this latter contract, and said that it was the understanding that his co-defendant Frasier should pay for the additional work. There was also some testimony about a subsequent contract, by which in making the changes in the building, plaintiff was to remove an old porch, connected with the building, for which he was to receive [342] as additional compensation, the sum of thirty dollars. It appears from the evidence that plaintiff completed the contract, except in one or two unimportant particulars, which are not urged as a defense to the action.

The defendant Braun filed an answer in the nature of a general denial, but the defendant Frasier made default, and judgment was taken against him accordingly. The issues between plaintiff and defendant Braun, as made by the respective pleadings, were tried by the court, without the intervention of a jury, which resulted in a verdict and judgment for plaintiff for the sum of eight hundred and fifty-six and forty-five hundredths dollars, the amount of plaintiff’s account with six per cent, interest thereon from the date of the filing of the lien, and this judgment was by the court declared to be a special lien on said property. No instructions were asked or given. The defendant Braun filed his motion for a new trial and after alleging the usual and familiar grounds, h e asked the court to set aside the verdict and judgment, and grant him anew trial, because the plaintiff had no mechanic’s lien for a part of his claim (if for any), and that the items of the account were so mixed and com mingled, that it was impossible for the court to determine for what part a lien was given. A motion in arrest of judgment was also filed and defendant urged as a special reason why this motion should prevail, that the lien was not filed by plaintiffs in the office of the circuit clerk within the time prescribed by law.

Both motions were overruled, and the defendant Braun duly excepted, and has brought the case to this court by appeal, and urges the following reasons why the judgment is wrong and should be reversed. First, Because the evidence fails to show that the lien was filed within the statutory period of six months. Second, That the work was done under three different and distinct contracts and the work under each contract as [343] stated in the account .cannot be separated or ascertained, which rendered the lien void as to all of the work. Third, That the account as filed included work or labor for which no lien was given by the statute. That is, the tearing down of the building and porch, and that the cost of this work was “lumped” with the cost of the other work, so that the one could not be separated from the other, and that for this reason the lien was void and should not have been enforced.

It would be better to dispose of the second objection made by defendant Braun, as the conclusion reached in that matter will more readily enable us to dispose of the first objection upon satisfactory grounds.

The defendant contends that the lien account as filed embraces work done and materials furnished in the repair of the building under three distinct and separate contracts, and that the items are so commingled and mixed that it is impossible to separate and distinguish the one from the other, and that for this reason, the whole lien account is void and incapable of enforcement. This court decided in the case of James Kearny et al. v. Wurdeman, 33 Mo. App. 447, “that where work was done on a building or other improvement by the same party, but under different and distinct contracts, the entire work might be embraced or carried into one account and lien paper. But in order to give a lien for the entire amount of work done, it should appear that the last item under each contract was within the time prescribed by the statute for filing the lien.” It is therefore apparent that when work done and materials furnished, under two or more contracts, are included in one lien paper, it is absolutely necessary that the items, under each contract, should be separately stated, in order for the court to determine whether the lien of the mechanic or material man, exists as to all, or only a portion of the work done. In [344] tlie case at bar, if the work was done under separate and distinct contracts within tlie meaning of the law, then the objection made by the defendant may be good.

Free access — add to your briefcase to read the full text and ask questions with AI

Bruns v. Braun, 35 Mo. App. 337, 1889 Mo. App. LEXIS 181 (Mo. Ct. App. 1889).

35 Mo. App. 337 (Bruns v. Braun) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Midwest Floor Co. v. Miceli Development Co.
304 S.W.3d 243 (Missouri Court of Appeals, 2009)
Luise, Inc. v. Village of Skokie
781 N.E.2d 353 (Appellate Court of Illinois, 2002)
Robinette v. Servite Fathers
364 N.E.2d 679 (Appellate Court of Illinois, 1977)
Dean v. McFarland
500 P.2d 1244 (Washington Supreme Court, 1972)
Arthur Morgan Trucking Co. v. Shartzer
174 S.W.2d 226 (Missouri Court of Appeals, 1943)
Ketcham v. Land Title & Trust Co.
101 A. 764 (Supreme Court of Pennsylvania, 1917)
St. Louis Fire Door & Sheet Metal Works v. Viviano
185 S.W. 218 (Missouri Court of Appeals, 1916)
Badger Lumber Co. v. W. F. Lyons Ice & Power Co.
160 S.W. 49 (Missouri Court of Appeals, 1913)
Voightman & Co. v. Southern Railway Co.
123 Tenn. 452 (Tennessee Supreme Court, 1910)
Pusey & Jones v. Pennsylvania Paper Mills
173 F. 634 (U.S. Circuit Court for the District of Middle Pennsylvania, 1909)
May v. Mode
123 S.W. 523 (Missouri Court of Appeals, 1909)
E. R. Darlington Lumber Co. v. James T. Smith Building Co.
114 S.W. 77 (Missouri Court of Appeals, 1908)
General Fire Extinguisher Co. v. Schwartz Bros. Commission
65 S.W. 318 (Supreme Court of Missouri, 1901)
Flanagan Bros. v. O'Connell
88 Mo. App. 1 (Missouri Court of Appeals, 1901)
Mitchell Planing Mill Co. v. Allison
40 S.W. 118 (Supreme Court of Missouri, 1897)
Miller v. Herbert
62 Mo. App. 682 (Missouri Court of Appeals, 1895)
Fruin-Bambrick Construction Co. v. Jones
60 Mo. App. 1 (Missouri Court of Appeals, 1894)
Eldridge v. Fuhr
59 Mo. App. 44 (Missouri Court of Appeals, 1894)
Kern v. Pfaff
44 Mo. App. 29 (Missouri Court of Appeals, 1891)