McLaughlin v. Schawacker

31 Mo. App. 365, 1888 Mo. App. LEXIS 187
CourtMissouri Court of Appeals
DecidedJune 5, 1888
StatusPublished
Cited by6 cases

This text of 31 Mo. App. 365 (McLaughlin v. Schawacker) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLaughlin v. Schawacker, 31 Mo. App. 365, 1888 Mo. App. LEXIS 187 (Mo. Ct. App. 1888).

Opinion

Thompson, J.,

delivered the opinion of the court.

This is an action by a subcontractor to recover a balance due from a firm of principal contractors and to establish a mechanic’s lien for such balance against a lot of ground and a building. The original petition was filed on the nineteenth of May, 1887, and the principal contractors, Dennis Dempsey and William J. Dempsey, and also the owner, Christopher Schawacker, were made defendants. Personal service was had upon each of these defendants. On the sixteenth of July, 1887, two other defendants, Maria W. Johnson and John H. Tennent, entered their appearance, and the plaintiff, by leave of court, filed an amended petition, and on his motion summons was ordered for the other defendants, Mathilda Davis, James S. Davis, her husband, and James S. Davis as trustee for Mathilda Davis. In accordance with this motion, summons was issued for the last-named defendants on the eighteenth of July, which was returned duly executed. The amended petition was not served on the defendants Dennis Dempsey and William J. Dempsey. These defendants filed no answer. The other defendants jointly answered by a general denial, followed by a special traverse of the essential allegations of the amended petition, and an averment that the plaintiff had failed to comply with the statutes in reference to mechanic’s liens by filing a. [370]*370just and true account of any work or materials furnished, etc. The original petition is not set out in the record, so that it does not appear that it was in any respect different from the amended petition except in respect of the additional defendants. A default was taken against the defendants Dennis Dempsey and William J. Dempsey. There was a trial by a jury of the issues made by the amended petition and the answer of the other defendants, which resulted in a verdict and judgment'against the defendants Dennis Dempsey and William J. Dempsey in the sum of $1,162.74, and a finding that the plaintiff had established a mechanic’s lien on the building and lot in the sum of $1,008.47, subject to a prior lien in favor of the defendant Maria N. Johnson, for the amount due under a certain deed of trust. After an unsuccessful ¿notion for a new trial, the defendants, other than Dennis Dempsey and William J. Dempsey, prosecute this appeal. The record is voluminous. The points insisted upon by the appellants are the following :

I. That the petition is not sufficient, under section 3166, Revised Statutes, to entitle the plaintiff to a mechanic’s lien, for the reason that the account therein set forth embraces labor and lime, brick and other materials, and the petition is open to the objection that it embraces a lumping charge. This account was as follows:

“January 19, 1887.
“To contract price for brick-work on building, 414 South 3rd street, St. Louis, under contract with William Dempsey and D. J. Dempsey......................$5,738 00
“These labor and materials furnished from September 30, 1886, to and including January 19, 1887. (Made up as follows ):
[371]*371“ To labor and materials in furnishing and putting into building of Chris. Schawacker, 414 South 3rd street, St. Louis, Mo. (including brick, mortar, labor, and all materials), 10,156 stock brick at $42.00 per M.................. 426 57
To labor and materials in furnishing and putting into .same building (including brick, mortar, labor, and all materials) 245,073 hard red brick at $12.50 per M.....’.. 3,063 40
To hauling scaffolding for work on said building.................. 20 00
To use of scaffolding on work on said building................... 85 00 '
To red paint used in said building,' four barrels.................... 25 39
To allowance made for shortage in building and walls, credit agreed to be given Schawacker......... 117 64
$3,738 00
Credits:—
Cash by order Dec. 11, ’86.$ t/oo 00
Cash by order Dec. 17, ’86. 800 00
Cash by order Dec. 27,’86. 1,200 00
Credit for shortage as above. 117 64 $2,617 74
$1,120 36”

The ground on which it is claimed that the above account embraces a lumping charge of several materials is that it does not separate the amount due for brick from the amounts due for mortar, for other materials, and for labor. We do not think that the account is open to this objection within the meaning of the decisions which bear upon this question. The account is framed with the view of making separate, charges for two classes of brick laid in the wall, according to what is known as [372]*372“wall measurement,” which is the measurement established by statute. Acts of 1885, p. 200, sec. 3. It charges for certain brick work, itemized according to kinds of brick and number of each kind used. This is sufficient under several decisions. Hayden v. Wulfing, 19 Mo. App. 353; Johnson v. Building Co., 23 Mo. App. 546.

II. It is next objected that the petition fails to state a cause of action, because the account annexed thereto was not a just and true account, within the meaning of section 3176, Revised Statutes. This objection is based upon the following grounds: That there is an item on the debit side, “To allowance made for shortage in building and walls, credit agreed to be given Schawacker, $117.64” ; that on the credit side of the account there is a “credit for shortage as above, $117.64,” from which it is argued that no credit was given ; and that, in order to fill out the amount of the contract price of the brick work on the building, which was $3,738, it was necessary to charge up the following items:

“ To hauling scaffolding for work on said building..........................$ 20 00
To use of scaffolding on work on said building.......................... 85 00
To red- paint used in said building, four barrels......................,____ 25 39
To allowance made for shortage in building and walls...................... 117 64
Making a total of.................$248 03”

We think these objections untenable. The objection that the item for shortage is on both the debit and the credit side of the account is merely specious, since it is not necessary to put such an item in the account at allin fact, it is not an item. It was evidently placed there by the draughtsman of the account on the conception of showing how much was allowed for shortage in the building and walls. Precisely the same balance would have been arrived at if the plaintiff had drawn. [373]*373his account without saying anything about the contract price or the shortage, but charging the other items on the debit side and giving on the credit side the credits which are given, except the credit for shortage. As to the other items charged for and objected to, it is sufficient to say that under the instructions of the court the jury rejected them from the amount for which their finding established the lien against the property, although they included them in their finding against the Dempseys.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riverside Lumber Co. v. Schmidt
109 S.W. 71 (Missouri Court of Appeals, 1908)
Brockmeier v. Dette
58 Mo. App. 607 (Missouri Court of Appeals, 1894)
McDermott v. Claas
104 Mo. 14 (Supreme Court of Missouri, 1890)
Sloan v. Frye
36 Mo. App. 523 (Court of Appeals of Kansas, 1889)
Doyle v. Wurdeman
35 Mo. App. 330 (Missouri Court of Appeals, 1889)
Bruns v. Braun
35 Mo. App. 337 (Missouri Court of Appeals, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
31 Mo. App. 365, 1888 Mo. App. LEXIS 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mclaughlin-v-schawacker-moctapp-1888.