McDermott v. Claas

104 Mo. 14
CourtSupreme Court of Missouri
DecidedOctober 15, 1890
StatusPublished
Cited by36 cases

This text of 104 Mo. 14 (McDermott v. Claas) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDermott v. Claas, 104 Mo. 14 (Mo. 1890).

Opinion

Thomas, J.

— Godfrey Fritz, in March, 1886, contracted with Charles Claas to erect a three-story, brick [19]*19building on a lot belonging to the latter in the city of St. Louis, and plaintiff, as subcontractor under Fritz, agreed to do and did do the brick work, and this action was brought against Fritz to recover the value of the work, and against Claas to foreclose a mechanic's lien against the building and the lot on which it stood, the amount claimed being $2,514.

The case was tried by the court without a jury. Judgment went against Fritz personally for $2,758.70, that being the principal and interest of the demand, and against Claas, fixing a lien on his property and awarding a special fieri facias against it for the payment of that amount. Claas alone appeals.

I. The first error urged for a reversal of the judgment of the trial court is that the petition does not state facts sufficient to constitute a cause of action, and the appellant’s objection to the introduction of any evidence under it ought to have been sustained. Section 8176, Revised Statutes, 1879, requires subcontractors to file with the clerk of the circuit court an account of the amount due him, “with the name of the owner or contractor or both if known to the person filing the lien.”

It is insisted that the petition in this case fails to state that the account filed with the clerk gave the name of the contractor and for that reason failed to state a cause of action to foreclose a mechanic’s lien in favor of a subcontractor. We do not think the assumption that the petition fails to make this statement is justified by the record. The petition describes the building to be erected and the property on which it was erected, alleges that the appellant owned the property ; that Godfrey Fritz was the contractor with the appellant for the erection of the building; that plaintiff made a contract with said Fritz to “do the brick work and furnish the materials for” the building for $2,514, which work he did and for which said Fritz was still [20]*20indebted to him, none of this sum having been paid. The petition then alleges that “within four months after the completion of the building, he gave notice to said defendant Olaas that he claimed a mechanic’s lien against the buildings and real estate aforesaid, for the sum aforesaid due, stating also from whom the same was due for the work and labor done and materials furnished by him as aforesaid, and that, unless the said amount was paid within ten days,” the plaintiff would file a mechanic’s lien on said buildings and real estate; that no part of said sum being paid within four months after said indebtedness accrued, to-wit, on the eighth day of September, 1886, plaintiff filed in the office of the clerk of the circuit court of the city of St. Louis, state of Missouri, “a just and true account of the demand so due him as aforesaid, after all just credits had been given, and also a true description of said real estate whereon said buildings were erected on which the work and labor mentioned were done and materials furnished to, or so near a true description thereof as to identify, the same, claiming that said demand was a lien on said property, together with the name of defendant Claas as the owner of said property, all of which statements were verified by plaintiff by bis oath; by virtue of which last-named proceeding plaintiff became entitled to and has a mechanic’s lien on and against said real estate, and the buildings and improvements thereon.”

We think the petition does state that the account filed by plaintiff in order to obtain the lien gave the name of the contractor. It does not do this in so many words, but that is the effect of what is stated. The petition having stated who the contractor was and that he was indebted to him in the sum of $2,514, for this work, goes on to state that plaintiff notified appellant that “he claimed a mechanic’s lien against the building and real estate for the sum aforesaid due, stating also-[21]*21from whom the same was due,” and that on the eighth day of September, 1886, he filed with the circuit clerk of the city of St. Louis “a just and true account of the demand so due him as aforesaid.”

That the petition alleges that the notice of the lien gave the name of the contractor, there can be no question and when the amount of the account and the name of the party who owes it are given, and then the averment is made that plaintiff filed a just and true account of the demand so due him as aforesaid” the inference is that not only the amount of the account, but the name of the party from whom it was due were given. Too much ought not to be left to inference in pleadings on the one hand, nor ought the courts to favor vague and indefinite objections on the other. Here the objection was that the petition did not state a cause of action. The particular objection under discussion was not made in the court below. The court and opposite counsel were left to conjecture what the defect in the petition was. If a petition wholly fails to state a cause of action this general objection is sufficient. R. S. 1889, sec. 2047. But, if the petition states a cause of action imperfectly or indefinitely, this objection will not avail. In that case other methods, such as a motion to make more certain and definite, are provided. Spurlock r. Railroad, 93 Mo. 530.

This is a cut-throat practice at best, and it is often used oppressively. Such an objection can be taken by demurrer, but parties choose to remain under cover and spring it on their adversaries at a time when they are least able to defend themselves or parry the blows. However, as everyone ought to know, and must be held to know, when he has stated a cause of action, or failed to state one, he ought not to complain if taken by surprise' at an inopportune time. But such an objection, to be available at the trial, must go to the entire sufficiency of the petition to state a cause of action, and [22]*22•cannot avail where it states a cause of action which is * indefinite and imperfect in some of its averments. We think, in the case at bar, if there be any defect in the petition, it is simply in not making affirmative allegations, but leaving a material matter to inference alone. This defect cannot be reached by the objection made in this case. It ought to have been made by motion to require plaintiff to make the petition more definite and certain. If that motion had been made, or the objection at the trial had been specific as to this point, the defect could have been remedied by amendment. Objections should be timely and specific.

The evidence in this case showed beyond controversy that the account filed did disclose the name of the contractor, as well as that of the owner of the property. Hence, this objection is simply a technical one. The court ought not to do a vain thing, and it would be a vain thing to reverse and remand this case on this technical ground, simply to give appellant an opportunity to traverse an unquestionable fact, a fact that has been once proved, and which appellant on the trial had a right to dispute, but which he did not dispute, and which he knows, and this court knows, would be conclusively proved on another trial. On this point the result must always be the same, because the fact involved is of record. Dailey v. Houston, 58 Mo. 361; Cruchon v. Brown, 57 Mo. 38; R. S. 1889, sec. 2303; Conly v. Doyle, 50 Mo. 234.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shelby Contracting Co. v. Pizitz
231 So. 2d 743 (Supreme Court of Alabama, 1970)
Ladue Contracting Co. v. Land Development Co.
337 S.W.2d 578 (Missouri Court of Appeals, 1960)
Roy F. Stamm Electric Co. v. Hamilton-Brown Shoe Co.
171 S.W.2d 580 (Supreme Court of Missouri, 1943)
Springfield Planing Mill, Lumber & Construction Co. v. Krebs
193 S.W. 621 (Missouri Court of Appeals, 1917)
Thompson v. Stearns
195 S.W. 43 (Missouri Court of Appeals, 1917)
McMillan & Parker v. Ball & Gunning Milling Co.
177 S.W. 315 (Missouri Court of Appeals, 1915)
State ex rel. Gardner v. Webb
164 S.W. 184 (Missouri Court of Appeals, 1914)
Monmouth College v. Dockery
145 S.W. 785 (Supreme Court of Missouri, 1912)
Feeny v. Rothbaum
137 S.W. 82 (Missouri Court of Appeals, 1911)
Lucas v. Gobbi
103 P. 157 (California Court of Appeal, 1909)
Robinson v. Levy
117 S.W. 577 (Supreme Court of Missouri, 1909)
Sharp v. Missouri Pacific Railway Co.
111 S.W. 1154 (Supreme Court of Missouri, 1908)
Kneisley Lumber Co. v. Edward B. Stoddard Co.
88 S.W. 774 (Missouri Court of Appeals, 1905)
Holland v. Cunliff
69 S.W. 737 (Missouri Court of Appeals, 1902)
Duerst v. St. Louis Stamping Co.
63 S.W. 827 (Supreme Court of Missouri, 1901)
Wells v. Adams
88 Mo. App. 215 (Missouri Court of Appeals, 1901)
Nanz v. Park Co.
103 Tenn. 299 (Tennessee Supreme Court, 1899)
Oglesby v. Missouri Pacific Railway Co.
51 S.W. 758 (Supreme Court of Missouri, 1899)
Pipkin v. National Loan & Investment Ass'n
80 Mo. App. 1 (Missouri Court of Appeals, 1899)
Cobb v. Lindell Railway Co.
50 S.W. 310 (Supreme Court of Missouri, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
104 Mo. 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdermott-v-claas-mo-1890.