General Fire Extinguisher Co. v. Schwartz Bros. Commission

65 S.W. 318, 165 Mo. 171, 1901 Mo. LEXIS 264
CourtSupreme Court of Missouri
DecidedNovember 19, 1901
StatusPublished
Cited by28 cases

This text of 65 S.W. 318 (General Fire Extinguisher Co. v. Schwartz Bros. Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Fire Extinguisher Co. v. Schwartz Bros. Commission, 65 S.W. 318, 165 Mo. 171, 1901 Mo. LEXIS 264 (Mo. 1901).

Opinion

VALLIANT, J.

This is a suit by a subcontractor to establish a mechanic’s lien. The trial in the circuit court resulted in a personal judgment against Schwartz Brothers Commission Company, the original contractor, for $7,830.12, and a special judgment establishing the lien, from which special judgment the defendant, the Farmers Elevator Company, the [176]*176owner of the property, and defendant St. Louis Trust Company, trustee in a deed of trust on the property, prosecute this appeal.

That the amount claimed is due the plaintiff, that the labor and materials were furnished and went into the building, that all the requirements of the statute to establish the lien have been observed, except as to the limitation of time in filing the same, are facts undisputed. The only question in the cause is, was the lien filed within four months after the indebtedness occurred as prescribed by section 4207, Revised Statutes 1899 ?'

The work in question was the construction of a fire extinguishing apparatus in the elevator. The Schwartz Brothers Commission Company contracted with.the elevator company to build an addition to their elevator according to certain plans and specifications and to equip it with a fire extinguishing apparatus, on a system to be satisfactory to the St. Louis Board of Underwriters; the object in submitting it to the approval of the board of underwriters being to obtain a reduction in insurance rates. The Schwartz Brothers sublet the contract of building and furnishing the fire extinguishing apparatus to the’ plaintiff in this suit, under certain plans and specifications agreed upon between the parties and approved by the board of underwriters. For the purposes of this suit it will not be necessary to set out here the specifications further than to say that there were to be four tanks on the top of the buildings and each tank was to be equipped with a water gauge and an air gauge.

In June, 1896, while the work was in course of construction and nearing its completion, the elevator company were anxious to have it brought to the condition which would be satisfactory to the underwriters, so that it might obtain the reduction in insurance rates, and began to urge Mr. Llenley, the inspector of the underwriters, to inspect the work and pronounce it finished. Accordingly, about July 1, Mr. Henley inspected the work, but declined to pronounce it complete, be[177]*177cause lie found some sprinkler beads not inclosed in casings" and some steam coils not covered. There was a difference of opinion between Mr. Henley and Mr. Moore, the superintendent of plaintiff’s work, as to the duty of the plaintiff under the contract to inclose, the sprinkler heads in casings as demanded, but finally Mr. Moore agreed to do so, but said he did not want to cover the steam coils just then as he was busy and there was no hurry for it but would do it later. At that time Mr. Henley made no objection relating to water gauges or air gauges; he had not then seen the contract under which the work was being done,. and inspected it only from the standpoint of a system satisfactory to the board of underwriters.. On July 23, 1896, Mr. Henley again inspected the work and finding the sprinkler heads inclosed and taking the promise of Mr. Moore that he would cover the steam coils in due season, addressed a note to the secretary of the board of underwriters of that date, informing him that the apparatus was complete. The system was put into operation that day and the elevator company’s insurance-rates reduced in consequence. The steam coils were covered within a few days thereafter.

At the time Mr. Henley gave the certificate above mentioned, each tank was supplied with a water gauge but not with an air gauge. In place of the four air gauges there was only one which was connected with the four tanks and this one was in the engine room. It seems'that such had been the system theretofore in use in similar appliances, but the contract here called for an air gauge on each tank and this was regarded as an improvement. When Mr. Henley inspected the work neither he nor Mr. Moore noticed this point. Afterwards, about November 1, a deputy of Mr. Henley’s reported to him that the apparatus was not working satisfactorily, in that a proper air pressure on the tanks could not be pumped up, owing to the arrangement of the piping and gauges, and thereupon, after consulting with Mr. Kalb, who was vice-president of the [178]*178elevator company and who acted for the company in this matter, Mr. Henley called on Mr. Moore and asked him to put- in the.air gauges. Mr. Moore testified that Mr. Kalb also called on him and pointed out to him that the gauges were called for in the contract and Moore then agreed to put them in. Mr. Kalb denied that he went in person to Mr. Moore about this, but stated that he requested Mr. Henley to go to see about it. At all events one or both of them went to see him and his attention was called to the requirement of the contract in that particular and he undertook to supply the deficiency and did so.

The wooden ■ handles on the water gauges that had previously been put on having been broken, Mr. Moore concluded to put in combination water and air gauges which was done and this was approved by all the parties The combination water and air gauges was regarded as the better system. The apparatus being at that time in operation, to do this work it was necessary to empty the tanks and afterwards replace the air in them, which operation threw the whole system out of action and it had to be readjusted. These combination gauges were put in on Saturday, November 7. On Monday, November 9, plaintiff was notified that one of the glass tubes of the new gauges was broken, which allowed the air to escape. On November 10, this was remedied and the air again pumped into the apparatus. On November 11,-a sand hole was discovered in one of the new valves and this the plaintiff was required to replace, involving again the throwing of the system out of gear and restoring it to condition; this was done November 12, and was the last work done by the plaintiff as under the contract. The lien was filed within four months of that date, the ten days’ previous notice thereof required by the statute having been duly given.

By the terms of the contract the Schwartz company was to pay the plaintiff the agreed price “in cash in thirty days after completion of the work herein specified, and approval by the St. Louis Board of Fire Underwriters.” On June 30, 1896, [179]*179as the work was nearing its completion the Schwartz company-executed and delivered to plaintiff its mine promissory notes covering the amount of the contract price of the work, the first payable sixty days after date, the others at intervals of fifteen days, the last maturing one hundred and eighty days from date, the notes being timed to mature within four months from the date when it was assumed the work would be finished.

The payments were divided in this way for the accommodation of the Schwartz company and at their request. Towards the latter part of September, 1896, Mr. Schwartz and Mr. Kalb called on Mr. Moore to ask an extension of the notes, but Moore was unwilling to extend them beyond the period in which he could file his mechanic’s lien and so informed them. Lie was then under the impression that the work was finished and that the four months limitation was running.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manning Construction Co. v. MCI Partners, LLC
419 S.W.3d 134 (Missouri Court of Appeals, 2013)
Charles D. Jones Co. v. Cliff Manor, Inc.
668 S.W.2d 613 (Missouri Court of Appeals, 1984)
Mitchell Engineering Co. v. Summit Realty Co.
647 S.W.2d 130 (Missouri Court of Appeals, 1982)
A. E. Birk & Son Plumbing & Heating, Inc. v. Malan Construction Co.
548 S.W.2d 611 (Missouri Court of Appeals, 1977)
Trout's Investments, Inc. v. Davis
482 S.W.2d 510 (Missouri Court of Appeals, 1972)
George F. Robertson Plastering Co. v. Altman
430 S.W.2d 169 (Supreme Court of Missouri, 1968)
Tabet Lumber Company v. Baughman
439 P.2d 706 (New Mexico Supreme Court, 1968)
Arch Sellery, Inc. v. Simpson
346 P.2d 1068 (Wyoming Supreme Court, 1959)
Harry Cooper Supply Co. v. Gillioz, 5560 (mo.banc 6-16-1937)
107 S.W.2d 798 (Supreme Court of Missouri, 1937)
Allison v. Schuler
36 P.2d 519 (New Mexico Supreme Court, 1934)
Breeding v. Melson
143 A. 23 (Supreme Court of Delaware, 1927)
Floreth v. McReynolds
224 S.W. 995 (Missouri Court of Appeals, 1920)
Tull v. Fletcher
196 S.W. 436 (Missouri Court of Appeals, 1917)
J. F. Meyer Manufacturing Co. v. Sellers
182 S.W. 789 (Missouri Court of Appeals, 1916)
National Surety Co. v. Price
172 S.W. 1072 (Court of Appeals of Kentucky, 1915)
Riverside Lumber Co. v. Schafer
158 S.W. 340 (Supreme Court of Missouri, 1913)
Bewick v. Price
154 S.W. 876 (Missouri Court of Appeals, 1913)
Rieflin v. Grafton
115 P. 851 (Washington Supreme Court, 1911)
Feeny v. Rothbaum
137 S.W. 82 (Missouri Court of Appeals, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
65 S.W. 318, 165 Mo. 171, 1901 Mo. LEXIS 264, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-fire-extinguisher-co-v-schwartz-bros-commission-mo-1901.