Floreth v. McReynolds

224 S.W. 995, 205 Mo. App. 143, 1920 Mo. App. LEXIS 90
CourtMissouri Court of Appeals
DecidedAugust 10, 1920
StatusPublished
Cited by9 cases

This text of 224 S.W. 995 (Floreth v. McReynolds) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Floreth v. McReynolds, 224 S.W. 995, 205 Mo. App. 143, 1920 Mo. App. LEXIS 90 (Mo. Ct. App. 1920).

Opinion

STURGIS, P. J.

This is a suit to enforce a mechanic's lien against property owned by defendant. The defendant lived in and near Pierce City, Missouri, but had accepted employment talcing him to Central and South America where he had resided for several years. He had acquired and maintained the property in quetsion as a home for his mother and sister who resided in a dwelling house thereon. The defendant returned at intervals to visit and see after his mother and sister and on one of these visits in the summer or fall of 1916 he determined to remodel and put modern improvements in this dwelling. Intending to leave again soon the defendant contracted with Frank Smith, a contractor, to do or have done this work. The defendant contracted with Smith to ’ furnish the material and do the general plumbing work, also to install a water system and a lighting plant, each of said items at a fixed price amounting to $987.73. Plaintiff did this work as a sub-contractor of Smith. It was agreed that Smith would have general supervision' of the work. It is also known that extra work and material would be necessary in connection with this part of the work and that Smith would order and be the judge as to such extras. The defendant then left the country and the work of remodeling his house was done in the winter and spring of 1916-17. Money was deposited in bank or furnished to Smith to pay for the work. - Smith paid part of plaintiff’s bill but not all. Defendant again visited his mother at Pierce City for a short time in October and November, 1918, and then went to NewYork City where he was when this suit was begun in February, 1919. Plaintiff, served constructive notice on defendant of his lien claim about February 1st and filed the lien claim with the Circuit Clerk February 15, 1919. This lien claim is as follows : 1916.

*146 To Contract for Plumbing............$224.85
To Contract for Water System........ 522.88
To Contract for Light Plant........ 240.00
987.73.
Sept. 26, By Cash........................ 500.00
Balance.......... 487.73
Nov. 17, 50 Feet 10 Galv. Valley............ 3.45
21, 30 Feet 12 Galv. Valley............ 2.40
29, 16 Feet 10 Galv. Valley .......... 1.05
494.63
Dec. 7, By Cash.......................... 300.00
194.63
1917
. Feb. 7, 20 lbs, 8d Case Nails.................80
Extras on Plumbing, etc............... 265.73
461.16
May 18', By.Cash ........................ 200.00
Balance...................... 261.16
June 9, 21 3-4 lbs. Galv. Iron made to order .. 4.35
265.51
1918
Oct. 18, Charging Batteries & Connecting DrainPipes (1 hr.).....................90
Nov. 23,‘Charging Batteries, 3 Hours with Helper.............................. 3.90
$270.31

This account is accompanied by an itemized statement, without any, dates, of the “extras on plumbing etc.” charged at $265.73.

The defendant raised the question in the Circuit Court as to validity of the constructive service of the *147 summons by leaving a copy with his sister. Later however he filed an answer to the merits and went to trial. By so doing he waived any question of service and tins point need not be considered.

The material question in the case is whether plaintiff perfected his lien within the statutory limit for filing liens after the work and furnishing material is completed. The plaintiff concedes that the validity of the lien depends ,on the last two items dated October 18 and November 23, 1918. The defendant contends that these items are merely colorable, not properly charged as a part ol' the lien account and charged only to save the lien from the Statute of Limitations.

It. will be noted that the Een account is singularly indefinite as to the dates of work done or materials furnished. The plaintiff merely charges under the indefinite date of 1916 the three contract items of plumbing $224.85, Water System $522.88 and Light Plant $240 without designating when the work was done or materials furnished. He charges under date of February 7,1917, the items of “Extras on Plumbing etc.,” amounting to $265.73, though it is hardly possible that all the items oí work and labor set out, but not dated, were 'furnished or performed on that day. Only five small items or charges are definitely dated, three in November, 1916, one on February 7, 1917 and one on June 9, 1917. These items are evidently extras. Then there is an interval of one year and four months followed by the two disputed items in October and November, 1918. The evidence is almost as indefinite and the most that we can say is that plaintiff performed his contract jobs and furnished the extras, other than the disputed items, during the last half of 1916 and the first half of 1917. He says he was delayed in his work by the carpenters as he could do his work only as the carpenter work progressed.

While defendant does not raise the question of failure of plaintiff to do all the work as contracted, the plaintiff admits that he never did complete the plumbing job of installing a bath tub and lavatory because, *148 as he says, .the hath room floor was not completed. This it seems was the fault of the contractor, Smith, who defaulted in his work and left it unfinished. Plaintiff’s foreman having this work in charge said that the last carpenter. work was done in the fall of 1917 and that this was the last of plaintiff’s work also till the-,items of October and November, 1918. Plaintiff now says that it was defendant’s fault that he has not completed his contract and that, having done all he could, defendant’s indebtedness accrued nevertheless. [McCall v. Atchley, 256 Mo. 39, 164, S. W. 593; Holden v. Lyons, 175 Mo. App. 165, 157 S. W. 811.] Had plaintiff waited till he had completed the contract by installing this hath tub and lavatory and had included these items in his lien account, such might have extended the time for establishing his lien; but he did not do that and so has no items after .Tune-9, 1917, except the disputed ones of October 18 and November 23, 1918.

It should.be noted that the item of October 18th is for “charging batteries and connecting drain pipe (1 Hr) .90;” and that of November 23,1918, is for “Charging Batteries 3 hours with helper 3.90.” The trial court made a finding of facts and .as to these items said: “The court finds that the last work done on this job by the plaintiff was the connection of a drain pipe

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manning Construction Co. v. MCI Partners, LLC
419 S.W.3d 134 (Missouri Court of Appeals, 2013)
Midwest Floor Co. v. Miceli Development Co.
304 S.W.3d 243 (Missouri Court of Appeals, 2009)
S & R Builders & Suppliers, Inc. v. Marler
610 S.W.2d 690 (Missouri Court of Appeals, 1980)
Westinghouse Electric Co. v. Vann Realty Co.
568 S.W.2d 777 (Supreme Court of Missouri, 1978)
Bremer v. Mohr
478 S.W.2d 14 (Missouri Court of Appeals, 1972)
Mitchell v. Beaver Dredging Co.
8 Alaska 566 (D. Alaska, 1935)
Richards Brick Co. v. Wright
82 S.W.2d 274 (Missouri Court of Appeals, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
224 S.W. 995, 205 Mo. App. 143, 1920 Mo. App. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/floreth-v-mcreynolds-moctapp-1920.