Monaghan v. Putney

37 N.E. 171, 161 Mass. 338, 1894 Mass. LEXIS 191
CourtMassachusetts Supreme Judicial Court
DecidedMay 17, 1894
StatusPublished
Cited by15 cases

This text of 37 N.E. 171 (Monaghan v. Putney) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monaghan v. Putney, 37 N.E. 171, 161 Mass. 338, 1894 Mass. LEXIS 191 (Mass. 1894).

Opinion

Holmes, J.

This is a petition to enforce mechanic’s liens. The judge before whom the case was tried found that the liens [339]*339were established, subject to an exception to his refusal to rule, as matter of law, that there was no evidence warranting his findings. The ground on which the respondent asked the ruling was that the petitioner did not file the statements required by statute within thirty days after he ceased to labor on the houses upon which the work was done.

The statements were filed on October 13, 1890. The petitioner did his work upon two houses under a contract with one Smith, who built them for the respondent. The auditor found that the petitioner had performed the contract substantially, on or before August 23,1890, that is, more than a month before the statements were filed, but that on September 22 and September 26 he did a small amount of additional work on the houses respectively, for the purpose of enabling himself to file his statements in season to maintain his liens. It appears by the schedule annexed to the auditor’s report, that the petitioner also did a little work on one of the houses on September 5. The petitioner testified, at the bearing before the court, that he did some work at the respondent’s request, and a part of his testimony would lead to the inference that this was toward the end of September. He also testified that in the middle of September he did not consider his contract fulfilled, and that he did the additional work in order to perform his contract, although he admitted that his ulterior purpose was to save his lien. If the contract had been performed at that time, probably when he consulted counsel about his lien he was in time to save it.

We cannot say that there was no evidence that the work was “ done in good faith, for the purpose of completing [the] contract, and not colorably in order to revive [the] lien,” in the language of Turner v. Wentworth, 119 Mass. 459, 464. We cannot lay it down, as matter of law, that the work was only colorable because of the ulterior purpose, or because what was done was a very trifling matter. If, as was testified, the contract did call, for what the petitioner did, and if the contract had not been treated by those concerned as fully executed at an earlier date, the petitioner’s lien was saved so far as his contract was concerned. It may be that the respondent’s testimony would have warranted the inference that Smith’s contract with the respondent was executed, and that the petitioner no longer had authority to work [340]*340upon the buildings. But we cannot draw that inference against the finding of the judge. See Worthen v. Cleaveland, 129 Mass. 670. Exceptions overruled.

C. E. Washburn, for the respondent. W. R. Bigelow, for the petitioner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. Commonwealth
194 N.E. 915 (Massachusetts Supreme Judicial Court, 1935)
Peerless Unit Ventilation Co. v. D'Amore Construction Co.
186 N.E. 280 (Massachusetts Supreme Judicial Court, 1933)
Breeding v. Melson
143 A. 23 (Supreme Court of Delaware, 1927)
In Re Proving the Will of Horton
111 N.E. 1066 (New York Court of Appeals, 1916)
National Surety Co. v. Price
172 S.W. 1072 (Court of Appeals of Kentucky, 1915)
Thurston v. Blunt
103 N.E. 478 (Massachusetts Supreme Judicial Court, 1913)
Shaughnessy v. Isenberg
99 N.E. 975 (Massachusetts Supreme Judicial Court, 1912)
Kenrick v. Boston & Albany Railroad
88 N.E. 430 (Massachusetts Supreme Judicial Court, 1909)
Nancolas & Howard v. Hitaffer
136 Iowa 341 (Supreme Court of Iowa, 1907)
D. L. Billings Co. v. Brand
73 N.E. 637 (Massachusetts Supreme Judicial Court, 1905)
General Fire Extinguisher Co. v. Schwartz Bros. Commission
65 S.W. 318 (Supreme Court of Missouri, 1901)
McLean v. Wiley
57 N.E. 347 (Massachusetts Supreme Judicial Court, 1900)
Burrell v. Way
57 N.E. 335 (Massachusetts Supreme Judicial Court, 1900)
Monaghan v. Goddard
53 N.E. 895 (Massachusetts Supreme Judicial Court, 1899)
Miller v. Wilkinson
44 N.E. 1083 (Massachusetts Supreme Judicial Court, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
37 N.E. 171, 161 Mass. 338, 1894 Mass. LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monaghan-v-putney-mass-1894.