Nancolas & Howard v. Hitaffer

136 Iowa 341
CourtSupreme Court of Iowa
DecidedJune 7, 1907
StatusPublished
Cited by9 cases

This text of 136 Iowa 341 (Nancolas & Howard v. Hitaffer) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nancolas & Howard v. Hitaffer, 136 Iowa 341 (iowa 1907).

Opinion

Si-ieewiN, J.—

In May, 1902, tbe defendants, Ilitaffer & Pronty, entered into a written contract with tbe appellant Bartlett, by tbe terms of wbicb they agreed to build for Bartlett, for tbe sum of $10,670, a tbree-story brick building and to furnish all labor and material for tbe same according to tbe plans and specifications of Bartlett’s architect. At about tbe time this contract was entered into, tbe contractors entered into a contract with tbe plaintiffs herein, by tbe terms of wbicb tbe plaintiffs were to furnish all hardware necessary for tbe construction of tbe Bartlett building. Tbe plaintiffs furnished hardware and builders’ material in accordance with tbe terms of their contract, until the building collapsed during tbe progress of the work thereon. They also furnished material wbicb went into tbe building after its reconstruction commenced, and this action is to establish and enforce a mechanic’s lien for tbe material so furnished. A portion of tbe building collapsed in August, 1902, at wbicb time, as we understand the record, less than a third of tbe material furnished by them bad been used in the building. Tbe last item of tbe material furnished was on March 18, 1903; and this charge was for repairs to a Yale lock. The next preceding charge was on February 3d, and the statement and affidavit for a lien were filed on tbe 3d day of April, 1903. Tbe appellants claim that tbe charge of March 18th is not a lienable item, and this presents one of the questions for determination in this case.

1. Mechanics’ liens: repair of material furnished. It is largely a question of fact, and, tbe trial court having found adversely to tbe appellant’s contention, we shall not consider at length the evidence supporting its finding. It appears from the record, however, that a Yale lock was furnished for the the building, and put in place some time prior front door of [343]*343to tbe 18th of March. In attempting to make it work more readily, one of the contractors took it off of the door and took it to pieces, and while doing so lost some of the parts connected with the lock proper, which necessitated returning the lock to the factory for repairs. It was returned to the plaintiffs herein, and by them returned to the manufacturers, and was afterwards sent back to them and delivered to Bartlett himself. There was a charge for repairing the lock and for expressage thereon. We think the item a lienable one under the statute, which provides a lien for “ any materials . . . or fixtures for any building,” etc. The contractors undertook to furnish the building with the lock in question, and it was to be delivered over to the appellant in good working order, and, if it became necessary to have it repaired in order to so deliver it, it was proper for the contractors or for the plaintiffs as subcontractors acting under their direction to have necessary repairs thereon made, and to make a charge therefor. If this was done in good faith, and not for the purpose of extending the time in which the lien might be filed, we see no reason for holding the item not lienahle. So far as the authorities have been called to our attention, they seem to establish a rule in accordance with this conclusion. Jefferson Water Supply Co. v. Riter, 138 Ind., 170 (37 N. E. 652); Monaghan v. Putney, 161 Mass. 338 (37 N. E. 171) ; Miller v. Wilkinson, 167 Mass. 136 (44 N. E. 1083) ; Great Spirits Springs Co. v. Chicago Lumber Co., 47 Kan. 672 (28 Pac. 714) ; Conlee v. Clark, 14 Ind. App. 205 (42 N. E. 762, 56 Am. St. Rep. 298). In Turner v. Wentworth, 119 Mass. 459, a small amount of additional work was done at the owner’s request several months after the other work was performed. The court there says: The evidence shows that the petitioners did some labor and furnished some materials used in the erection of the building within the thirty days. If this was done in good faith for the purpose of completing their contract, and not colorably in order to revive [344]*344their lien, the thirty days would begin running from the time they thus performed labor and furnished materials.”

2 Same- mate-liabmty: of owner. By the terms of Bartlett’s contract with Hitaffer & Prouty, he was to make semimonthly payments on the estimates of his architect, reserving’in all cases twenty per cent. sxlck esthnates to protect himself. The evidence shows, and the trial court so found, that the account sued on herein began to run while Bartlett was making payments to the contractors in accordance with the contract, and while there were funds in his hands due the contractors which he afterwards paid out upon estimates which were not liens upon the premises, and for which no liens were ever claimed. It "appears from the record that Bartlett knew very soon after the work on this building commenced that the hardware was being furnished by these plaintiffs; and, this being true, he had no right to pay out the reserve funds which he held in his hands on other claims for which no lien had been filed, and, having done so, he is liable for the plaintiff’s claim, unless the conditions raised by the collapse of the building shall be held 'to, relieve him of such liability. Queal v. Stradley, 117 Iowa, 748; Green Bay Lumber Co. v. Adams, 107 Iowa, 672; Green Bay Lumber Co. v. Thomas, 106 Iowa, 154; Othmer v. Clifton, 69 Iowa, 656.

3. Same. After the collapse of the building, the contractors and Bartlett entered into a contract, whereby it was to be reconstructed without at that time determining who was responsible for the collapse, and the practical effect of •this contract was to put the entire building under the management and control of Bartlett; he agreeing to pay for the additional material and labor necessary to carry on the work.. There is also testimony tending to show that Bartlett by his statements induced the plaintiffs to continue furnishing material for his building, relying for their pay on him rather than on the contractors. In view of this testimony and his control over the building and the payments [345]*345made by him for other material and for labor during the reasonable reconstruction of the building, we think the district court properly held him liable for the material furnished by the plaintiffs after the collapse.

The appellant contends that the reconstruction of the building made necessary by its collapse cost him much more than he had agreed to pay in his original contract, and that he was entitled to use all the money remaining in his hands after making payments according to the terms of the contract, for the purpose of the reconstruction. This might be true under ordinary circumstances, but the record before us convinces us that, if the’ appellant was not directly responsible for the collapse of the building on account of faulty plans and specifications, he was at least chargeable with as much fault as were the contractors, and that he is now in no situation to make the claim as against the plaintiffs’ right that he be permitted to reconstruct his building with the funds which would otherwise have gone to the plaintiffs.

4. statement fais^charges. The appellant further contends that the plaintiffs’ lien should not be established because the itemized statement therefor contained charges for items which are not properly lienable. This condition will not defeat the right to a lien, unless it be shown that the plaintiffs were knowingly attempting by false charges to subject the defendants’ property to an improper burden.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Des Moines Furnace & Stove Repair Co. v. Lemon
56 N.W.2d 923 (Supreme Court of Iowa, 1953)
Crane Co. v. Westerman
8 N.W.2d 412 (Supreme Court of Iowa, 1943)
Bolhuis Lumber & Manfg. Co. v. Van Tubergen
230 N.W. 910 (Michigan Supreme Court, 1930)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)
Mason City Brick & Tile Co. v. Lamson
190 Iowa 365 (Supreme Court of Iowa, 1920)
Stephenson v. Svenson
187 Iowa 802 (Supreme Court of Iowa, 1919)
Cedar Rapids Sash & Door Co. v. Heinbaugh
183 Iowa 1236 (Supreme Court of Iowa, 1918)
Garrison Grain & Lumber Co. v. Farmers Mercantile Co.
181 Iowa 568 (Supreme Court of Iowa, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
136 Iowa 341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nancolas-howard-v-hitaffer-iowa-1907.