Garrison Grain & Lumber Co. v. Farmers Mercantile Co.

181 Iowa 568
CourtSupreme Court of Iowa
DecidedOctober 30, 1917
StatusPublished
Cited by9 cases

This text of 181 Iowa 568 (Garrison Grain & Lumber Co. v. Farmers Mercantile Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garrison Grain & Lumber Co. v. Farmers Mercantile Co., 181 Iowa 568 (iowa 1917).

Opinion

Salinger, J.

I. The plaintiff, the Garrison Company, and the several defendants and cross-petitioners, filed a number of sworn statements as subcontractors for mechanics’ liens for alleged unpaid labor and material furnished to the principal contractor. These claims aggregate $2,260.15, or $1,165.69 in excess of the amount left in the hands of the owner, appellant, Farmers Mercantile Company. The principal contractor made default. The owner tendered into court the balance in its hands due the contractor, and asked that same be distributed among the several claimants as the court might see fit, praying that the liens be canceled and that it be discharged from further liability. The decree gives judgment to all the claimants, and holds, the owner liable for $2,094.46, with interest. -

The contract price is ................ $5,703.90

Amount used according to settlement to complete building................$ 109.44

Payment June 2, 1912................ 500.00

Payment of July 27th (unchallenged).. 1,000.00

Payment August 3d (unchallenged) .. 1,000.00. 2,609.44

$3,094.46

[571]*571If' this were all, the owner has on hand more than enough to pay all contenders. But it paid out $1,000 on July 27th and $1,000 on August 27th. If both these are payments which it can assert, then it does not owe the principal contractor enough to pay all these claimants. The trial court allowed the payment made on July 27th and disallowed the one made on August 27th. All claims were established in full save that of Shorthill, which was reduced from $191.50 to $135.75. No one appeals save the owner. The plaintiff, the Grain Company, has filed no brief. The defendants J. D. Barr and B. E. Overman are not in the jurisdiction of the court, and no adjudication as to them was or could be attempted herein. The defendant Wenner defaulted, and, under the allegations in the cross-petition of the defendant and appellant, Wenner’s lien, if any, was canceled.

1. documentary evidence * pleadings: ad-substitution: II. We gather that the original cross-petition contained an admission that the $2,000 was not paid under the contract, but under special arrangement between the appellant and the contractor. It is contended that this pleading cannot be considered because it was substituted for. This is so only if not put in evidence. It was put in, and so became evidence, though substituted for.

2. mechanics' lien : proceedings to perfect: unauthorized items: effect. III. As to the claim of the Grain Company, we are of opinion that the item of cement is not in fact the last item furnished under the contract. . The Grain Company was charged with knowledge of the contract. The owner was justified by the contract in canceling. The owner did cancel. An agent of the Grain Company notified the principal contractor of the cancellation, and hence the Grain Company had notice of the can[572]*572cellation. The cement was furnished, after the contract was canceled. This works that the Grain Company did not serve notice within thirty days after furnishing the last item. It results it can have nothing which the owner did not owe the contractor.

3-a

3. Mechanics’ lien: right to lien : payments by owner to contractor : estoppel. We agree with the trial court that the Grain Company is estopped to claim that the $1,000 paid on July 27th should not be treated as a justified payment, even if it had given notice within thirty days after it furnished the last item. The payment was made because the Grain Company demanded it and refused to supply material unless a payment of at least $2,000 was made, and it received the money which it now urges was not rightfully paid. We think the trial court was right in holding, as against the Grain Company, that this $1,000 was npt owing the contractor. See Andrews v. Burdick, 62 Iowa 714; Vreeland v. Ellsworth, 71 Iowa 347.

3-b

4. Mechanics’ lien : right to lien : payments by owner : crediting contractor’s indebtedness to another. We are of opinion that what was done on August 27th constitutes a payment to the contractor. All said against this conclusion is.that this payment was not made to the principal contractor because an officer of the owner, who was also an officer in a bank, applied that sum on a debt owing the bank by the contractor, and did so without his request and without notifying him of such application until after it had been made. We think Knapp v. Cowell, 77 Iowa 528, settles that what was here done constitutes a payment to the contractor.

We find that the trial court erred in holding that this payment was not so ratified by the Grain Company as to [573]*573estop it from contending that it was an unauthorized payment. As just seen, the payment was made by an officer of the Grain Company to help a bank of which he was also an officer. The Grain Company must, as between it and the owner, be relegated for collection to the contract price minus the conceded reductions, plus $2,000, paid on July 27th and on August 27th. That is to say, as to the Grain Company the sum due the contractor is $1,094.46. It cannot have more than that. It remains to be seen whether it may have so much as that.

s. mechanics’ > iien: inteu- ° uient items. IV. Tyler, claiming $207.77, filed claim first, and, if entitled to anything, has priority, and is entitled to have full satisfaction, even if that exhaust the fund. See Code Sec. 3095, and Lindsay v. Zoeckler, 128 Iowa 558. The position of appellant is that the court should have estopped Tyler from claiming any lien at all “on account of his evidently trumped-up claim, and his dishonesty of purpose.” This is based upon the assertion that Tyler’s statement contains a fictitious item of $1.00 for putting in a sill for a rear door, in that Tyler claims he did this on September 23d; that he did no work on that day, or that, if he did, it was gratuitous and voluntary, and cannot be included in his claim; that, with this item excluded, the last work performed for which Tyler is entitled to a lien was done about August 21st; and that, therefore, Tyler failed to serve notice within 30 days. It is further contended that the date September 23d was inserted in the statement after it had been completed and presented to appellant, about August 26th or 27th, and it given to understand that the work contracted for by -Tyler with the principal contractor had then been completed; that the amount exhibited at this time was for the same amount which is claimed now, to wit, $207.77. The amount of the item for [574]*574putting in the sill is, to be sure, trifling in itself, and as part of a $207 claim. But, of course, that fact will not avail if its insertion was a fraudulent one. So the inquiry at this point narrows to whether Tyler perpetrated an intentional fraud. If he did, he can assert no lien. Palmer v. McGinness, 127 Iowa 118; Nancolas v. Hitaffer, 136 Iowa 341, at 345; Stubbs v. Clarinda, C. S. & S. W. R. Co., 65 Iowa 513; 27 Cyc. 203. And see Bangs v. Berg, 82 Iowa 350; Green Bay Lbr. Co. v. Miller, 98 Iowa 468; Hug v. Hintrager, 80 Iowa 359. The time at which the sill was actually put in is in dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rohlin Const. Co., Inc. v. Lakes, Inc.
252 N.W.2d 403 (Supreme Court of Iowa, 1977)
Farrington v. Freeman
99 N.W.2d 388 (Supreme Court of Iowa, 1959)
Lawrence v. Tschirgi
57 N.W.2d 46 (Supreme Court of Iowa, 1953)
Chancellor v. Melvin
52 So. 2d 360 (Mississippi Supreme Court, 1951)
Crane Co. v. Westerman
8 N.W.2d 412 (Supreme Court of Iowa, 1943)
Spahn & Rose Lumber Co. v. Eells
195 Iowa 555 (Supreme Court of Iowa, 1923)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
181 Iowa 568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garrison-grain-lumber-co-v-farmers-mercantile-co-iowa-1917.