Andrews & Smith v. Burdick & Goble

62 Iowa 714
CourtSupreme Court of Iowa
DecidedJune 15, 1883
StatusPublished
Cited by22 cases

This text of 62 Iowa 714 (Andrews & Smith v. Burdick & Goble) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrews & Smith v. Burdick & Goble, 62 Iowa 714 (iowa 1883).

Opinions

Beck, J.

I. Plaintiffs furnished materials to Burdick & Goble, builders, who were erecting a storehouse for Potter & Skevington, under a contract with him. By the terms of the contract, payments were to be made in nearly equal parts upon the execution of the contract, and the completion of the building, and its acceptance by Potter & Skevington. It was to be completed between the 15th and 20th of June. It was not finished until the 3d of July. On the 5th day of June, plaintiffs furnished the materials to recover for which this suit is brought. On the morning of the 3d of July, jilaint-iffs filed in the clerk’s office a statement and claim for a lien, and in the evening of that day caused the notice to be served upon Potter & Skevington required by the statute. There was evidence showing that they had knowledge of the fact that the sub-contractors had furnished^he materials. But on the 3d day of July, after plaintiffs’ claim for a lien was filed, and before the written notice prescribed by the statute was served, they paid the contractors in full the amount due them for the building. Extra work, amounting to $75, was done, and paid for at the final settlement. Extra work was contemplated in the contract.

A motion for a new trial was made by plaintiffs, on the [716]*716ground that there had been a material alteration of the contract for the building, which was unknown to the plaintiffs before the trial, purporting to bind the contractors to furnish all materials, no such provision being in the original writing. The motion was overruled. The amount in controversy being less than $100, the district court certified certain questions of law to this court, whei’eof the following is a copy? verbatim et literatim. The points raised by the questions will be understood by attention to the facts of the case above stated.

“ 1st. Under a written contract for the completion of a building by the 15th to 20th of June, 1880, and the payment therefor to Ipe made upon the completion, of the building, which, in fact, was not completed until July 3d, 1880, would a sub-contractor, who furnished materials on the 5th day of June, 1880, and filed a mechanics’lien therefor in the clerk of courts’ office on the 3d day of July, 1880, before pajunent was made by'the owner to' the contractor, and, after said lien was filed, and on the same day, but before written notice therefor was served by the sub-contractor upon the owner, but with verbal notice of the plaintffs’ lien, the owner paid the contractor in full, and afterwards, on the same day, written notice was served of the filing of said lien by the sub-contractor upon the owner, can the sub-contractor enforce that lien against the building?

“2d. "Where a written contract provides that the building i s to be completed by the 15 th to the 20 th of J une, and that com - píete payment is then to be made, but the building is not,, in fact, completed until thirteen days thereafter, and the owner acquiesces in such deldfy, is this such a change in the contract as will entitle a sub-contractor to 30 days after furnishing material in which to file his claim for a lien, and serve written notice thereof on the owner, and will the owner be liable to such sub-contractor, although the building may have been completed and the contractor paid in full therefor prior to the expiration of such 30 days?

3d. Where a contract for the building of a store-room pro-[717]*717.videcl that the contractor should furnish such extras as should be ordered by letter, and extras were, in fact, furnished by them, but it is not shown whether they were ordered by letter or otherwise, and when the contract provides for payment of the contract price upon the completion of the building, but is silent as to the date of payment for the extras that may be furnished, can a sub-contractor who furnished material and filed his claim for a lien, and gave written notice thereof, within 80 days, establish a lien against the building for the materials furnished by him, or to the extent of the extras furnished by the contractors, if the building was finished and accepted by the owner within 30 days, and payment in full made therefor to the contractors within the 30 days?

“4th. Where there was a written contract for the erection of a building, would an unauthorized material alteration in the terms of said contract, after it was executed and delivered, entitle a sub-contractor, who furnished material for said building, to 30 days after the materials were furnished in which to file his lien and serve written notice thereof? Would such alteration of the written contract invalidate it, so that the subcontractor would have thirty days after furnishing materials in which to file his lien and serve his notice, regardless of the terms of said written contract?

“5th. Where a written contract has been materially altered without authority, after execution and delivery, would the parties therein be permitted to show and rely upon the oral agreement upon which the written agreement was drawn, or will the parties be required to rely and recover, if at all, upon an implied compact to pay when the building was completed, and in such case would the sub-contractor have thirty days after furnishing material in which to file his lien and serve written notice thereof?”

II. The first question presents, briefly stated, the case of i.MBCHAsracs’ coutractor: avoidance of hfprmSpaí contractor. payment by the owner of the building to the contractor before the expiration of thirty days after x j j "ie lx,a^enaIs were furnished by the sub-contractor, ailcj before service of the written notice, required [718]*718by the statute, of the tiling of the claim and statement for a lien by the sub-contractor, with knowledge that the sub-con-ta'ractor had furnished the materials.

III. The statute secures to a sub-contractor a lien for materials or labor. Chap. 100, Acts Sixteenth General Assembly, ~IIE SAME. § 7 (Miller’s Code, S 2134; McClain’s Statutes, p. 599) provides that, “to preserve Jus lien as against the owner, and to prevent payment by the latter to the principal contractors or to intermediate sub-contractors, but for no other purpose, the sub-Contractor must, within the thirty days, as provided in section six, serve upon such owner, his agent or trustee, a written notice of the filing of said claim.” The notice referred’to, which is provided for by section six, must be given within thirty days after the date upon which the last of the materials was furnished.

It will be observed that the lien of the sub-contractor may exist for thirty days without the written notice. If such written notice be not given within that time, the lien ceases. The provision is explicit, and no exception is found in the statute which will discharge the lien within the thirty days. But this court, liberally construing the statute, so as to protect the owner who in good faith paid the contractor in accord with the agreement between them, held that such payment, made without knowledge on the part of the contractor of the claim of the sub-contractor, would defeat the lien of the latter. Stewart c& Hayden v. Wright, '52 Iowa, 335. The decision is based upon the right of the parties to the contract to make payment as provided therein, and the doctrine that the sub-contractor must take notice of the contract between the owner and contractor, and that his rights are subordinate thereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Iowa v. Tyjaun Levell Tucker
Supreme Court of Iowa, 2021
State of Iowa v. Howard J. Thompson
Supreme Court of Iowa, 2021
Simmons v. Brenton Nat. Bank of Perry
390 N.W.2d 143 (Court of Appeals of Iowa, 1986)
Rasmussen v. Norby
282 N.W. 712 (Supreme Court of Iowa, 1938)
State v. Apodaca
82 P.2d 641 (New Mexico Supreme Court, 1938)
Brenton v. Lewiston
236 N.W. 28 (Supreme Court of Iowa, 1931)
Mason City Brick & Tile Co. v. Lamson
190 Iowa 365 (Supreme Court of Iowa, 1920)
Garrison Grain & Lumber Co. v. Farmers Mercantile Co.
181 Iowa 568 (Supreme Court of Iowa, 1917)
Wine v. Jones
183 Iowa 1166 (Supreme Court of Iowa, 1917)
Lohman v. Reymond
137 P. 375 (New Mexico Supreme Court, 1913)
Iowa Stone Co. v. Crissman
83 N.W. 794 (Supreme Court of Iowa, 1900)
Greenlee v. North British & Mercantile Insurance
71 N.W. 534 (Supreme Court of Iowa, 1897)
Epeneter v. Montgomery County
67 N.W. 93 (Supreme Court of Iowa, 1896)
Exchange Bank v. Pottorfe
65 N.W. 312 (Supreme Court of Iowa, 1895)
French v. French
15 L.R.A. 300 (Supreme Court of Iowa, 1892)
Smith & Co. v. Hill
49 N.W. 1043 (Supreme Court of Iowa, 1891)
Brown & Sons v. Smith
41 N.W. 27 (Supreme Court of Iowa, 1888)
Teager v. Landsley
27 N.W. 739 (Supreme Court of Iowa, 1886)
Colyar v. Pettit
18 N.W. 694 (Supreme Court of Iowa, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
62 Iowa 714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrews-smith-v-burdick-goble-iowa-1883.