Epeneter v. Montgomery County

67 N.W. 93, 98 Iowa 159
CourtSupreme Court of Iowa
DecidedMay 13, 1896
StatusPublished
Cited by16 cases

This text of 67 N.W. 93 (Epeneter v. Montgomery County) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Epeneter v. Montgomery County, 67 N.W. 93, 98 Iowa 159 (iowa 1896).

Opinion

Kinne, J.

3 I. As to the claim of Welsháns & Gibson, appellee contends that these defendants have served no notice of appeal. This contention is well founded. They presented their claim to the court below, by way of a cross-petition. The only notice of appeal is given by the plaintiff. While it is true that counsel appearing for the plaintiff, also appeared in the lower court for said cross-petitioners, that fact does not relieve said cross-petitioners from serving notice of, an appeal from the decree of the court below in case they desired to question its correctness in this court. Not having done so, they are concluded by that decree, and their case cannot be considered.

4 II. It is contended by appellants that Refregier’s claim is not valid, because not in form in compliance with the statute. In that part of the affidavit making the claim, this language is used: “That affiant hereby' claims a mechanic’s lien against said Montgomery county, Iowa, and the funds set apart for the erection of said court house, for the sum of two thousand three hundred and fifty dollars, with interest thereon from the sixth day of July, 1891.” It is insisted that the statute gives no right to a lien, either upon the property or the fund, and, having asked for that to which he was not entitled under the law, the claim cannot be recognized as being in compliance with the statute. The requirements of the statute are that, within thirty days from the time the last material was furnished or the last labor done, the claimant must file with the proper officer, an itemized and sworn statement of his demand. Acts Twentieth General Assembly, Chapter 179. This he did. More was not required of him, and he was not called upon to claim a lien as against either the property or the fund; and, by so doing, he effected [167]*167nothing. Having complied with the statute, the fact that he claimed a lien which the statute did not give, is not fatal to.his recovery. When the proper statement was filed in time, and duly verified, the statute fixed the extent of his remedy. The case is unlike McGillivray v. District Township, 96 Iowa, 629 (65 N. W. Rep. 974), and cases there cited, where the absolute requirements of the law were not complied with. In form, the claim was sufficient.

5 III. In the title of chapter 179, Acts Twentieth General Assembly, and within brackets, appear these words: “Additional to ch. 100 of the Acts of the 16th General Assembly.” Chapter 100, thus referred to, relates to mechanics’ liens. Appellee contends'that the enrolled bill does not contain the words quoted, and that we should not consider them; that the act is in no way additional to, or amendatory of the mechanics’ lien statutes, but is an independent statute, giving relief only to sub-contractors, and should be construed without regard to said mechanic’s lien laws. In the view we take of the case, it is not material to now determine whether or not this statute is to be construed with reference to the mechanic’s lien statutes or not. If, as appellants contend, it is thus to be construed, we do not think appellants can recover in this case. The fact that in a few instances, the county paid the contractor a sum in advance of the time when the estimate was, in fact, made, is no ground for holding the county liable to plaintiff, as in every case such sum so paid was deducted from the ninety per cent, due, as shown by the estimate next following, and it is impossible to discover how this worked any prejudice to plaintiff, as the total sums, in fact paid, were all due the contractor by the very terms of the contract.

Now, unless the fact that the defendant county had knowledge of the furnishing'of labor and material [168]*168by plaintiff and Ms assignors, which was not paid for, would preclude said defendant from paying in accordance with its contract, the payment of these sums in advance of the actual estimate would furnish no ground of complaint to plaintiff and his assignors. The county never paid to the contractor more than the ninety per cent, of the estimate. In the completion of the building, it expended a sum greater than the amount which would still have been due the contractors (including the ten per cent, withheld on estimates made), had they completed the entire work in accordance with the contract. This, under the terms of the contract, heretofore referred to, it had a clear right to do. So that, instead of there being any sum due the contractor, he is indebted to the county. The act under which recovery is sought in this case clearly contemplates that the county shall not be required to pay in any event a sum in excess of the contract price. It provides: “Shall have a valid claim against the public corporation constructing such building, * * * for the value of such services and material, in an amount not in excess of the contract price to be paid for the building. * * * Nor shall any such corporation be required to pay any such claim at any time before, or in any manner different, from that .provided in the principal contract.’’

6 In nearly all of the cases in this state, decided under the general mechanic’s lien law, wherein the the owner has been held liable to a sub-contractor who filed his lien and served' the statutory notice within the time required, such liability has been based upon one or both of the following grounds: First, that the contract between the owner of the building and the principal contractor gave the owner the right to pay the claims of sub-contractors, and deduct the sum so paid from the amount due the coiitractor; second, that the contract [169]*169between the owner and the principal contractor did not call for payments from the owner to the principal contractor at certain fixed times, and in certain specified amounts. The doctrine that one has a right to pay in accordance with the terms of his contract was recognized as early as the case of Kilbourne v. Jennings, 38 Iowa, 533. And see Stewart v. Wright, 52 Iowa, 355 (3 N. W. Rep. 144). In that case it is said: “The single question' to be determined upon the demurrer was whether the payments, made in good faith, without notice, and in strict accord with the contract, protect the defendant from again paying to the sub-contractors the amounts of their respective liens. This question was undoubtedly correctly determined by the court below. Any other rule, followed to its logical conclusion, would effectually prevent a person from complying with a contract which all the world must admit he has a right to make and perform. * * * Counsel for appellant argue this case upon the theory that the sub-contractor is not bound to take notice of the terms of the contract between the owner and the principal contractor. The argument seems to be that the owner must act at his peril, and cannot make payments according to the terms of his contract, without making inquiry as to'whether there may not be sub-contractors who may thereafter file liens and give him notice. But this last clause of section 7, above quoted, charges sub-contractors with notice of the terms of the contract. ” In the same case it is said that the statute “recognizes contracts as binding, and does not alter their terms, much less provide that a man may not pay his contractor in advance, if he so agrees.” This case is followed in Roland v. Railway Co., 61 Iowa, 380 (16 N. W. Rep. 355). In Lumber Co. v. Osborn, 72 Iowa, 474 (34 N. W. Rep. 215), it is said: “It will be observed that the payments were made in strict accord with the contract,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Des Moines Furnace & Stove Repair Co. v. Lemon
56 N.W.2d 923 (Supreme Court of Iowa, 1953)
Beyer v. Zindorf
198 P. 977 (Washington Supreme Court, 1921)
Orcutt Co. v. Schlappi
188 Iowa 378 (Supreme Court of Iowa, 1919)
Cedar Rapids Sash & Door Co. v. Heinbaugh
183 Iowa 1236 (Supreme Court of Iowa, 1918)
Wykoff v. Stewart
180 Iowa 949 (Supreme Court of Iowa, 1917)
Kelly v. Johnson
95 N.E. 1068 (Illinois Supreme Court, 1911)
Sioux Falls Pressed Brick Co. v. Board of Education
125 N.W. 291 (South Dakota Supreme Court, 1910)
Chicago Lumber & Coal Co. v. Garmer
109 N.W. 780 (Supreme Court of Iowa, 1906)
Modern Steel Structural Co. v. Van Buren County
102 N.W. 536 (Supreme Court of Iowa, 1905)
Swearingen Lumber Co. v. Washington School Township
125 Iowa 283 (Supreme Court of Iowa, 1904)
Green Bay Lumber Co. v. Independent School District
101 N.W. 84 (Supreme Court of Iowa, 1904)
Iowa Stone Co. v. Crissman
83 N.W. 794 (Supreme Court of Iowa, 1900)
Iowa Brick Co. v. City of Des Moines
82 N.W. 922 (Supreme Court of Iowa, 1900)
Beach v. Wakefield
107 Iowa 567 (Supreme Court of Iowa, 1898)
Green Bay Lumber Co. v. Thomas
76 N.W. 651 (Supreme Court of Iowa, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
67 N.W. 93, 98 Iowa 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/epeneter-v-montgomery-county-iowa-1896.