Wykoff v. Stewart

180 Iowa 949
CourtSupreme Court of Iowa
DecidedSeptember 20, 1917
StatusPublished
Cited by2 cases

This text of 180 Iowa 949 (Wykoff v. Stewart) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wykoff v. Stewart, 180 Iowa 949 (iowa 1917).

Opinion

Preston, J.

i. drains : construction : contract, breach of: insolvency withhowing°paymates.01' cst1’ The plaintiff, Wykoff, in the case entitled as above, first brought suit against defendant W. L. Stewart, contractor, and the surety company. Two other parties, Lehigh Sewér Pipe & Tile Company, and Lehigh Clay Products Company, brought separate actions. Five or six others filed petitions of in-, tervention. Other defendants are the board of supervisors and its chairman, the county auditor, the drainage district, and other claimants. As said, on the hearing of the main c.ase of the drainage district against the contractor and surety company, the several cases of parties who had filed claims and asked for liens were all consolidated. The court decreed that the claims as filed, which appellants are claiming were not liens, be established, and judgment was rendered. Judgment was rendered against the surety company in favor of the county for the use and benefit of the drainage district and some other 8 or 10 claimants, in the sum of $744.22, and preference was given as against the funds. Appellant concedes that, as to the labor and material bills, no complaint is made, and from the holding of the trial court as to these items,there has been no appeal. Appel-. lant concedes also that the expenses reasonably necessary in completing the job were proper items to pay from the district funds, but says that the district must show that it performed its part of the contract, and that it has not done so because it withheld a part of the estimates, and did not show that it relet the work at a reasonable price. These matters will be referred to later.

[951]*951The issues presented are those arising in The cross-bill of the surety company and the cross-bill of the drainage district, and the answers of each to the pleadings of the other. The county, the board of supervisors, the auditor and the drainage district are referred to in the argument as “the drainage district.” Briefly, the cross-petition of the drainage district alleges the letting of the contract to W. L. Stewart, on February 16, 1912, to construct Drainage Ditch No. 2 for $34,018.10; the execution and delivery of a bond by the contractor, with defendant surety company as security; the failure of the contractor to construct the ditch; the forfeiture of the contract or abandonment of the work; the subsequent reletting of the work, its completion, and the commencement of actions by laborers and materialmen; that all proceedings in reletting the work were in accordance with law. Tt asked that it be given a preference to the funds remaining against the contractor and the surety company on their bond for the shortage. The surety company alleges that, under the contract, the contractor was entitled to 80 per cent of each estimate as soon as it Avas filed; that the district refused to pay said SO per cent, and because of such failure it Avas impossible for him to complete his contract with the district; that the district had no right to Avithhold the money; that the district has collected large sums of money on account of the construction of said improvement, and has failed to properly account therefor; that the surety company is entitled to a judgment granting it a preference to the funds in the hands of the drainage district; that, because the drainage district prevented the completion of the contract by the contractor, the surety company is released, and is not liable to the district on its bond because of the wrongful conduct of said district. The drainage district contends that the contractor abandoned the work; that the contract was releí and the Avork completed; and that it rightfully AAuthheld the 80 [952]*952per cent under the law and provisions of the contract and bond; and that no part of this money was withheld until after the contractor had abandoned the work, and until after liens or claims were filed. Among other provisions of the contract are the following:

“Failure to Prosecute Work.
“If the second party shall fail to prosecute the work according to the work specified, or shall fail or refuse to prosecute the work after commencing the same, and damage to the ditch or district results therefrom, the second party shall be liable therefor, and the first party may recover such damage by an action on the bond of the second party; or the said party of the first part may retain from the amount otherwise due the parties of the second part, from time to time, such sum as shall reimburse the parties of the first part for such damage, or enable them to repair the same.
“Abandoning Work.
“In case the party of the second part shall abandon the work or fail to make satisfactory progress on said work, said first parties may cause said work to be completed, and the parties of the second part, and also the sureties on the bond herein referred to, shall be jointly and severally liable to the parties of the first part for any and all loss and damage resulting from such default, either from the greater expense of so completing said work, or from any other cause.
“Subletting.
“It is further agreed by the said parties of the second part that it will give its personal attention to the .faithful prosecution of said work, and will not assign or sublet the same or any part thereof, without the previous written consent of the parties of the first part, subject to such conditions for its own protection as it may see fit to impose.
[953]*953“Revoking Contract.
“The parties of the first part may stop the work or revoke this contract, or both, if the party of the second part or its employees shall willfully refuse to comply with any of the terms and requirements hereof, in which event the party of the second part shall forfeit to the parties of the first part all payments due or to become due on said work, as liquidated damages for such breach of contract, and shall be liable for any further damages by reason thereof, and the parties of the first part shall be in no manner liable for stopping the work or revoking the contract.
“Party of the second part will, in a good workmanlike manner, at its own expense, furnish and pay for all labor and material and perform all the work necessary for the excavation and construction of the ditches of the said district.”

The bond provides:

“Now, therefore, if the said W. L. Stewart shall well and faithfully perform and carry out all the terms, agreements, conditions and covenants contained in said contract, and shall pay, as they, become due, all just claims for work, tools, machinery, skill and material used in the completion of said contract, in accordance with its terms, and if the said W. L. Stewart will save the said county of Humboldt and state of Iowa harmless from all costs and charges that may accrue on account of the doing of the work specified in said contract, then this obligation shall be void; otherwise to remain in full force and effect.”

The specifications for the contract provide, among other things:

“All plans, specifications and reports in the possession of the engineer, and all laws enacted by the general assembly of Iowa which may apply to the legal construction of tile drains, shall be considered as part of these general specifications.”

[954]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Center Drainage District No. 1 v. Capitol Indemnity Corp.
147 N.W.2d 245 (Wisconsin Supreme Court, 1967)
Monona County v. O'Connor
215 N.W. 803 (Supreme Court of Iowa, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
180 Iowa 949, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wykoff-v-stewart-iowa-1917.