Swearingen Lumber Co. v. Washington School Township

125 Iowa 283
CourtSupreme Court of Iowa
DecidedOctober 21, 1904
StatusPublished
Cited by3 cases

This text of 125 Iowa 283 (Swearingen Lumber Co. v. Washington School Township) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swearingen Lumber Co. v. Washington School Township, 125 Iowa 283 (iowa 1904).

Opinion

Weaver, J.

The petition alleges that the defendant school township let to one J. O. Frizelle a contract for the construction of a schoolhouse, that plaintiff as subcontractor furnished- to Frizelle the lumber and materials for said building, and that upon the debt thus arising there is due and owing to the plaintiff a balance of $452.75. It is also alleged that after furnishing said lumber and materials to Frizelle, and within thirty days after delivering the.last item thereof, plaintiff presented to said school district, and filed with the proper officer thereof, an itemized and sworn statement of said claim. It is -further alleged that, at the time of the furnishing of said materials and the presentation of said claim, there was due and owing from the district township to said Frizelle, as a balance upon the contract price for said schoolhouse, the sum of $385.65, and that said sum is still due and unpaid. Hpon these allegations plaintiff demands judgment against said school township for- the amount so alleged to be in its hands and unpaid to said contractor.

[285]*285Answering this claim, the defendant admits having let the contract to Frizelle for the construction of a schoolhouse, as alleged, for the sum of $684.50, to be paid $300 when the foundation of the house was finished, and the remaining sum of $384.50 when the house was completed and delivered according to contract. It is alleged that on July 1, 1902, the first installment of $300 became due, and was then fully paid, and that upon July 25, 1902, the building was fully completed and accepted, and that the remaining installment of $384.50 thereupon became due and payable. It is further alleged that on said day, and after said balance became due and payable to Frizelle, and before the district township had any notice or knowledge of the plaintiff’s claim, said defendant was garnished, as the debtor of Frizelle, at the suit of one A. M. 'Hull, before a justice of the peace, and made answer to such garnishment, disclosing the indebtedness as aforesaid. The matter of said garnishment came on for hearing before said justice of the peace on August 6, 1902, and defendant, by its secretary, appeared thereto, filed an answer showing the facts as to the state of its account with Frizelle, and said justice thereupon entered judgment requiring defendant, as garnishee of Frizelle, to pay to said Hull the sum of $89.44 and costs. In obedience to this judgment, defendant has paid the amount of Hull’s claim, leaving still in its hands due to Frizelle the sum of $290.10, which it is ready and willing to pay to plaintiff, and tenders judgment accordingly. It is also' alleged that, at the time of making its answer to said garnishment, defendant had no notice that plaintiff herein had or claimed any right as subcontractor to the moneys in its hands due to .the said Frizelle, and that such answer was made in good faith. It is also admitted by the answer that on August 6, 1902, plaintiff filed with and served upon the president and secretary of the defendant an itemized and sworn statement of its demand, and that on August 20, 1902, a similar statement was served upon the president, secretary, and treas[286]*286uref, but that neither of said notices or statements were served or filed until the defendant’s answer as garnishee had been taken as above related. In a second count of its answer the defendant states the history of the case as aforesaid, and further alleges that plaintiff intervened in the garnishment proceedings before the justice of the peace, seeking to establish the priority of its claim on said fund, and that such intervention was dismissed. Thereupon the plaintiff herein appealed from the ruling of the justice of the peace to the district court, by which court the appeal was afterward dismissed. ' By these rulings and orders it is alleged that the demand presented by plaintiff .in the case at bar has already been adjudicated. To each of these counts of the answer plaintiff interposed a demurrer, which was overruled, and from the judgment entered on said demurrer this appeal'has been taken.

1. Public corporations: garnishment; claims of subcontractors. Assuming, as we must, the truth of the statement of facts contained in the answer, they disclose a good defense to the plaintiff’s demand. The right of plaintiff to recover, if at all, is based upon Code, section 3102, which provides that a subcontractor who iur material or labor for the construction of a public building may have a claim therefor against the public corporation for which the building is constructed, “ not in excess of the contract price to be paid for such building, nor shall such corporation be required to pay any such claim before or in any different manner from that provided in the principal contract.” In order to have the advantage of this remedy, the claim must be filed with the public officer through whom the payment is to he made, in the form of an itemized sworn statement of the demand, within thirty days after furnishing the last item of materials or labor for which payment is claimed. In Epeneter v. Montgomery County, 98 Iowa, 159, we held that a public corporation which has let a contract for a public improvement ma.y pay the contractor according to the terms of the agreement, without in[287]*287curring any liability to subcontractors whose claims are not filed as provided by law before such payment is made. It is a well-settled principle of law that.a subcontractor must take notice of the terms of the principal contract, and is bound thereby. See authorities cited in the Epeneter Case, 98 Iowa, 171. This case has since been cited and followed in Iowa Stone Co. v. Crissman, 112 Iowa, 122; Beach v. Wakefield, 107 Iowa, 567; Green Bay L. Co. v. District, 121 Iowa, 663.

2. Same. It is argued herein by the appellant that the case at bar does not come -within the rule of these precedents, because it, is said the debt was not due from the district to the contractof when the garnishment was made. We do not so construe the record. The contract provided that the building was to be finished and delivered free from any lien for work done or material furnished on or before August 15, 1^02,” and the argument, is that, although the building was completed on July 25, 1902, yet, appellant’s claim being outstanding and unpaid, the debt to Lrizelle was not due or payable until that claim was satisfied. It is admitted that plaintiff’s demand was not a lien on the building, but the claim is made that we should interpret this clause of the contract in reference to liens as intended to protect the subcontractor in his statutory right to enforce his demand against the school district. But a construction so forced and violent as this cannot be allowed. The building was completed July 25, 1902. So far as the record shows, there was no lien upon it, and the contractor was entitled to demand, and appellee was privileged, if not indeed bound, to pay the remainder of the contract price.

3. Priority of liens. But it is also insisted that, even if the debt was due, the appellant had thirty days from the date of the last item furnished the contractor in which to present and file its claim, and that the attaching creditor could not obtain any priority by his garnishment. To this it may be answered that Code, section 3095, as to pri[288]*288ority between garnishments and mechanics’ liens, can have no application to cases like this, where no lien is created or provided for.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eclipse Lumber Co. v. Iowa Loan & Trust Co.
38 F.2d 608 (Eighth Circuit, 1930)
C. E. Stukas & Sons v. Miller
198 N.W. 65 (Supreme Court of Iowa, 1924)
Wackerbarth & Blamer Co. v. Independent School District
138 N.W. 470 (Supreme Court of Iowa, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
125 Iowa 283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swearingen-lumber-co-v-washington-school-township-iowa-1904.