C. E. Stukas & Sons v. Miller

198 N.W. 65, 197 Iowa 824, 1924 Iowa Sup. LEXIS 757
CourtSupreme Court of Iowa
DecidedApril 1, 1924
StatusPublished

This text of 198 N.W. 65 (C. E. Stukas & Sons v. Miller) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. E. Stukas & Sons v. Miller, 198 N.W. 65, 197 Iowa 824, 1924 Iowa Sup. LEXIS 757 (iowa 1924).

Opinion

PrestON, J.

The pleadings, comprising plaintiff’s petition, the several petitions of intervention, the cross-petition of the bonding company against the school district, the answers, exhibits attached to the pleadings, such as the contract, plans, specifications, and so on, are quite voluminous. Many pages of the abstract are taken up with their printing. The facts were, for the most part, stipulated.

Numerous questions were presented below. Appellant argues two or three propositions in this court, but appellees contend that the questions as now presented are narrowed to one issue, which, as they state it, is that certain of the appellees claim the right to recover up to 15 per cent of the contract price, by reason of filing their claims under Section 3102 of the Code, as amended by Chapter 380, Acts of the Thirty-eighth General Assembly, and all appellees claim the right to recover up to 15 per cent of the contract price, because of the implied and expressed con[826]*826tractual relation between them, tbe subcontractors, and tbe school district; that all other issues are collateral or contingent upon the one stated; and that the determination of that question against appellant will determine the entire controversy.

Appellant denies the right to recover, because the school district paid the contractors in full, and because, as it claims, they were absolved from liability by the terms of the contract, and because the bonding company alone is liable to the subcontractors.

The plaintiff and two of the interveners, whose claims aggregated approximately $3,000, filed their verified claims, notified the district, and complied with the statute before referred to. The other interveners did not strictly, perhaps, do so; but their petitions of intervention, to which were attached itemized statements, were filed before 60 days from the completion of the building, which they contend was a substantial compliance with the statute, and resulted in no prejudice to appellant. Wackerbarth & Blamer Co. v. Independent Sch. Dist., 157 Iowa 614, 616. The representative of the school district,- who was on the job, knew that materials were being furnished by them.

The contract price was $52,500. Fifteen per cent of this is $7,875, the amount for which defendant school district was held liable. The general conditions of the contract, the specifications, and drawings, were made a part of the contract. The contract was made a part of the bond, the condition of which is that, if the principal shall faithfully perform the contract on his part, and satisfy all claims and demands incurred for the same, and shall fully indemnify and save harmless the owner from all cost and damage which he may suffer by reason of failure so to do, and shall fully reimburse and repay the owner all outlay and expense which the owner may incur in making good any such default, and shall pay all persons who have contracts directly with the principal for labor or materials, then the obligation to be void; otherwise in force.

The contract was executed September 10, 1919. There was delay. The contractors became' insolvent, and were so at the time of the commencement of this action. At the last, the school district did some work to complete the building. On January 29, 1921, a written memorandum was made between the con[827]*827tractors and the district, wherein'the contractors agreed to do certain specified things which were unfinished. They did some work after that, but did not do all the things so agreed. The $8,000 was paid by the district to the contractors February- 3, 1921. At that time, the district knew that the building was not completed, and that there was other work to do under the contract. When the $8,000 was paid, the contractors had something more than that in the building, — that is, counting what labor and materials interveners had put in, and the 15 per cent retained. After the $8,000 was paid, the school district still had approximately $500 which they retained. The last work performed by the contractors was March 3, 1921. The painting was completed March 19, 1921. The other unfinished parts of the work were done by the district about August 1, 1921, and the district paid therefor out of the $500 just referred to. After the payments so made to complete the contract which the contractors had failed to do, there still remains a balance in the hands of the district of something over $300.

Provisions of the contract which seem to be material are:

Art. 1: The contractor agrees to provide all materials and to perform all the work shown on the drawings and described in the specifications, and to do everything required by the general conditions of the contract, specifications, and the drawing’s.

Art. 2: Contractor agrees that the work under the contract shall be substantially complete, ready for occupancy and acceptance of the building, at the time noted in the specifications.

Art. 3: Fixes the contract price, subject to additions and deductions as provided in the general conditions of the contract, and to make payments on account thereof as provided therein, as follows:

“Payments to be made monthly, and to be eighty-five per cent (85%) of the labor performed and the materials delivered on the premises, contractor’s payments shall be made upon receipt of the architect’s certificate, issued by the architect and based on the monthly estimate submitted to the architect by the contractor. Fifteen per cent (15%) of the amount of the contract price shall be retained sixty days after the completion and acceptance of the contract to provide protection of the owners against any liens,” etc.
[828]*828“Specifications: Art. 1 '(j) All time limits stated in tbe contract documents are of the essence of the contract.”
“Art. 28: The architect may withhold or, on account of subsequently discovered evidence, nullify the whole or a part of any certificate for payment to protect the owner from loss on account of: * * * (b-) Claims filed or reasonable evidence indicating probable filing of claims, (c) Failure of the contractor to make payments properly to- subcontractors or for material or labor. When all the above grounds are removed certificates shall at once be issued for amounts withheld because of them.
“Art. 29: Liens — Neither the final payment nor any part of the retained percentage shall become due until the contractor, if required, shall deliver to the owner a complete releage of all liens arising out of this contract, or receipts in full in lieu thereof and, if required in either case, an affidavit that the releases and receipts include all the labor and material for which a lien might be filed; but the contractor may, if any subcontractor refuses to furnish a release or receipt in full, fivrnish a bond satisfactory to the owner, to indemnify him against any claim by lien or otherwise. If any lien or claim remain unsatisfied after all payments are made, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging such lien or claim, including all costs and a reasonable attorneys’ fee.”
“Art. 43: Nothing contained in the contract documents shall create any contractual relation between any subcontractor and the owner.
“Art. 44: Nothing in this article shall create any obligations on the part of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Iowa Brick Co. v. City of Des Moines
82 N.W. 922 (Supreme Court of Iowa, 1900)
Swearingen Lumber Co. v. Washington School Township
125 Iowa 283 (Supreme Court of Iowa, 1904)
Modern Steel Structural Co. v. Van Buren County
102 N.W. 536 (Supreme Court of Iowa, 1905)
Wackerbarth & Blamer Co. v. Independent School District
138 N.W. 470 (Supreme Court of Iowa, 1912)
Des Moines Bridge & Iron Works v. Plane
143 N.W. 866 (Supreme Court of Iowa, 1913)
Mason City Brick & Tile Co. v. Lamson
190 Iowa 365 (Supreme Court of Iowa, 1920)
Reynolds v. City of Onawa
192 Iowa 398 (Supreme Court of Iowa, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
198 N.W. 65, 197 Iowa 824, 1924 Iowa Sup. LEXIS 757, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-e-stukas-sons-v-miller-iowa-1924.