Wackerbarth & Blamer Co. v. Independent School District

138 N.W. 470, 157 Iowa 614
CourtSupreme Court of Iowa
DecidedNovember 18, 1912
StatusPublished
Cited by6 cases

This text of 138 N.W. 470 (Wackerbarth & Blamer Co. v. Independent School District) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wackerbarth & Blamer Co. v. Independent School District, 138 N.W. 470, 157 Iowa 614 (iowa 1912).

Opinion

Evans, J.

— The case was submitted upon an agreed statement of facts. Only questions of law, therefore, are submitted for our consideration. These questions are two in number: (1) Did the plaintiff comply with the preliminary requirements of section 3102, or did he fail to file his statement of account with the proper officer of the school district? (2) Were the provisions of section 3102 available to the plaintiff after the principal contractor had made a general assignment for the benefit of his creditors ?

Section 3102 is as follows:

Public Buildings or Bridges — Claim of Subcontractor. Every mechanic, laborer or other person who, as subcontractor, shall perform labor upon or furnish materials for the construction of any public building, bridge or other improvement not belonging to the state, shall have a claim against the public corporation constructing such building, bridge, or improvement for the value of such services and material, not in excess of the contract price to be paid for such building, bridge or improvement, nor shall such cor[616]*616poration be required to pay any such claim before or iu any different manner from that provided in the principal contract. Such claim shall be made by filing with the public officer through whom the payment is to be made an itemized and sworn statement of the demand, within thirty days after the performance of the last labor or the furnishing of the last of the material, and such claims shall have priority in the order which they are filed.

i. School buildings: subcontractors’ ofaiSmefiUnE In attempted compliance with the requirements of this section the plaintiff filed an itemized and sworn statement of his account with the treasurer of the school district; and within a few minutes thereafter, and . , approximately at the same time, he served a “ . ' written notice of such filing upon the president and secretary of such school district. It is urged by appellee that the treasurer was 'not the proper officer with whom such statement should have been filed, but that it should have been filed with the secretary as being the officer contemplated by the provisions of the quoted section. This contention is based in part upon the case of Green Bay Lumber Co. v. Thomas, 106 Iowa, 420. That was an action against the county. The statement was filed or left with one member of the board of supervisors. We held in that case that it should have been filed with the county auditor. This section of the statute was not at that time identical with its present form. Its requirement then was that the statement should be filed “With the officer through whose order the payment is to be made.” It will be noted that the statute in its present form requires a filing with the “public officer through whom the payment is to be made.” It was this provision which led the appellant to make the formal filing with the treasurer on the theory that he was the officer through whom payment would be made. It is argued that the change in the statute was intended only to improve its form, and not to change its real meaning, and that its meaning and intent are not there[617]*617by changed. The argument is that the treasurer as a disbursing officer can exercise no responsibility except to pay the warrants drawn upon him, that the warrants must be drawn by the president and secretary, and that such warrants when drawn and delivered constitute payment within the meaning of the statute. The argument is not without its force. - A warrant being once issued and delivered is practically beyond recall or defense; but the fact remains that the treasurer is the officer through whom the payment is made in the literal sense. It is evident, also, that, if the plaintiff had filed its statement with the secretary in lieu of the treasurer or with the president in lieu of either, he could not have escaped the menace of plausible argument against the course adopted. As against the secretary, it could be said that he is not the officer through whom “payment” should be made, and, further, that he is not the officer “through whose order” the payment is to be made. His duties are clerical and are performed under the' direction of the board of directors in pursuance only of their official action. The order or warrant, when issued upon the direction of the board, must be signed by the president and the secretary. If it would have been sufficient to file with the secretary under the terms of the statute, by the same reasoning it would be sufficient to file the same with the president. As urged by appellees, the real purpose of the statute is very plain. It is intended to bring the claim definitely and formally to the attention of the governing officers of the corporation before its liability thereon can attách. We have already noted the fact that the plaintiff not only filed the sworn statement with the treasurer, but he immediately served written notice to that effect upon the president and the secretary. ' We think that such a course fully met the requirements of the statute and amounted to a filing of the statement with the president, secretary, and treasurer. To hold otherwise would be unduly technical, and would ignore, not only the spirit of the statute, but its [618]*618literal letter as well, in that the treasurer is an officer through whom “payment” is made.

Same- insoicSáFcontrací1’ tor: effect. II. We turn now to the second question. A few hours prior to the filing of the sworn statement by plaintiff and on the same day, the principal contractor, Netcott, made a gene:i-’al assignment for the benefit of his creditors. The plaintiff filed its claim with- ^ ^ thirty-day period, and complied in all. respects with every requirement of the statute. It is agreed that there was in the hands of the school district, due under the contract, at the time of such filing, the net sum of $6,168.57 over and above one prior claim of $97. The question is, can the plaintiff be deprived of the benefits of section 3102 by the mere act of the principal contractor in transferring his claim against the school district to some other person? Does the mere fact that the principal contractor made a general assignment for his creditors prevent the plaintiff from availing himself of this statute thereafter, even though within the statutory period ? Our first impressions on the oral argument inclined to the affirmative on this question. Dpon further consideration we are convinced that the position is not sound. We have held heretofore that the statute creates no lien in favor of the subcontractor, although it does offer him a certain equitable right. Whitehouse v. Surety Co., 117 Iowa, 328; Green Bay Lumber Co. v. Independent School District of Odebolt, 125 Iowa, 227; Swearingen Lumber Co. v. School District, 125 Iowa, 283; Steel Co. v. Van Buren County, 126 Iowa, 619.

In the Swearingen case, supra, we held that where the school district was garnished, and answered showing its indebtedness, and was adjudged to pay the claim of the garnishee, it was entitled to credit for the amount so paid, and was liable only for the amount remaining in its hands. And this was held notwithstanding that the subcontractor filed his claim therewith within thirty days. He had not filed his [619]*619claim when the school district answered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eclipse Lumber Co. v. Iowa Loan & Trust Co.
38 F.2d 608 (Eighth Circuit, 1930)
Fuller & Hiller Hardware Co. v. Shannon & Willfong
215 N.W. 611 (Supreme Court of Iowa, 1927)
C. E. Stukas & Sons v. Miller
198 N.W. 65 (Supreme Court of Iowa, 1924)
Emery v. Leighton
182 Iowa 1363 (Supreme Court of Iowa, 1918)
Handlan-Buck Manufacturing Co. v. Waterloo Drop Forge Co.
173 Iowa 452 (Supreme Court of Iowa, 1916)
Des Moines Bridge & Iron Works v. Plane
143 N.W. 866 (Supreme Court of Iowa, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
138 N.W. 470, 157 Iowa 614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wackerbarth-blamer-co-v-independent-school-district-iowa-1912.