Kelly v. Johnson

95 N.E. 1068, 251 Ill. 135
CourtIllinois Supreme Court
DecidedJune 20, 1911
StatusPublished
Cited by23 cases

This text of 95 N.E. 1068 (Kelly v. Johnson) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly v. Johnson, 95 N.E. 1068, 251 Ill. 135 (Ill. 1911).

Opinion

Mr. Justice Hand

delivered the opinion of the court:

This was a bill in chancery filed on the 8th day of September, 1906, in the superior court of Cook county, by A. W. Kelly, doing business as A. W. Kelly &' Co., a subcontractor, against J. W. Johnson, doing business as J. W. Johnson & Co., the original contractor, and L. G. Hallberg and Stewart Hodges, the owners, and Francis E. Broom-ell, trustee of certain premises located in the city of Chicago, to establish a mechanic’s lien under the statute for certain materials furnished in the construction of the masonry work in a brick building in course of construction on the said premises, which masonry work was being constructed by J. W. Johnson for the owners in pursuance of a contract between J. W. Johnson and the owners bearing date March 5, 1906, to which bill other material-men who had furnished material to J. W. Johnson for use in said building were made parties defendant. Answers and replications were filed and the case was referred to a master. The master took the proofs and reported that A. W. Kelly & Co.,' in pursuance of a contract with J. W. Johnson made April 15, 1906, was entitled to a sub-contractor’s lien for $793.50; that the Waukesha Lime and Stone Company, in pursuance of a contract with J. W. Johnson made April 30, 1906, was entitled to a sub-contractor’s lien for $331; that the M. A. Staley Company, in pursuance of a-contract with J. W. Johnson made August 2, 1906, was entitled to a sub-contractor’s lien for $69.88; that the Juhl Automatic Hoisting Machine Company, in pursuance of a contract with J. W. Johnson made June 4, 1906, was entitled to a sub-contractor’s lien for $295; and that the Labahn Brick Company, in pursuance of a contract with J. W. Johnson made April 27, 1906; was entitled to .a subcontractor’s lien for $455. The court entered a decree establishing such liens, from which decree E. G. Hallberg, Stewart Hodges and Francis E. Broomell, trustee, have prosecuted an appeal to this court on the ground that section 21 of the Mechanic’s Lien statute of 1903 is unconstitutional and void.

Section 21 of the statute, in part, reads as follows: “Every mechanic, workman or other person who shall furnish any materials, apparatus, machinery or fixtures, or furnish or perform services or labor for the contractor shall be known under this act as a sub-contractor, and shall have a lien for the value thereof, with interest on such amount from the date the same is due, from the same time, on the same property as provided for the contractor, and, also, as against the creditors and assignees, and personal and legal representatives of the contractor, on the material, fixtures, apparatus or machinery furnished, and on the moneys or other considerations due or to become due from the owner under the original contract, whether or not the original contractor could have obtained a lien or was by contract or conduct divested or deprived of a right to obtain a lien.”

It appears from.the evidence that the original contract of March 5, 1906, between J. W. Johnson and the owners of the said premises, provided that Johnson should receive $13,801 for the material and labor to be furnished and performed by him in doing the masonry work upon the said building, to which was added $975 for extras, which amounts aggregated the sum of $14,776 as the contract price of the masonry work on said building. It also appears that J. W. Johnson commenced work on said premises and received from the owners in payment for material and work $10,300; that when the masonry work was about four-fifths done J. W. Johnson failed, and the owners were obliged to take over the contract and complete the building at an actual cost to them of $15,353.33; that at the time the original contract was made there was no waiver of lien in the contract; that the first payment in the contract was the sum of $5000, which was made on the 15th day of May, 1906, at which time the original contract was modified by the parties by J. W. Johnson executing and delivering to the owners a waiver of lien in the original contract for all materials theretofore furnished or to be furnished thereafter on account of said building, which -waiver was in the following form:

“To all whom it may concern:
“Whereas, I, the undersigned, have been employed by Stewart Hodges and L. G. Hallberg to furnish masonry work, including labor and material, for the building known,as [describing property.]
“Now, therefore, know ye that I, the undersigned, for and in consideration of $5000 and other good and valuable considerations, the receipt whereof is hereby acknowledged, do hereby waive and release any and all lien or claim, or right of lien, on said above described building and premises under “An act to revise the law in relation to mechanics’ liens,” approved May 18, 1903, and in force July 1, 1903, on account of labor or materials, or both, furnished, or which may be furnished, by the undersigned to or on account of the said............fqr said building or premises.
“Given under my hand and seal this 15th day of May, 1906.
J. W. Johnson & Co., (Seal.)
By J. W. Johnson. (Seal.)”

The contracts with all the sub-contractors who were allowed liens, with the exception of A. W. Kelly & Co. for $793.5°, whose contract for materials bore date of April 15, 1906, the Waukesha Lime and Stone Company for $331, whose contract bore elate of April 30, 1906, and 'that of the Labahn Brick Company for $455, whose contract for material bore date of April 27, 1906, were made subsequent to the date of said waiver of lien by J. W. Johnson.

The lien of a sub-contractor can only exist by virtue of the original contract, and in case the original contract provides there shall be no lien on the improved property format erial and labor, furnished by the original contractor, such contract is binding upon a sub-contractor, and a subcontractor, when a lien has been waived in the original contract, has no lien for material or labor. (Williams v. Rittenhouse & Embree Co. 198 Ill. 602; VonPlaten v. Winterbotham, 203 id. 198.) We think as to all contracts for material or labor made subsequent to May 15, 1906,— the date of the waiver of all liens for material and labor, executed by J. W. Johnson to Hodges and Hallberg, — no sub-contractors’ liens can exist. Clearly, if a lien can be waived in the original contract it can be subsequently waived, for a valuable consideration, as between the original parties. The right to modify a contract as between the original parties, so long as there are no intervening rights, involves the exercise of the same power as does the execution of the original contract. The section of the statute heretofore referred to, we think, in so far as it attempts to give a sub-contractor a lien when the original contract waives all liens or all liens have been thereafter released by the contractor, is clearly unconstitutional, as its enforcement against an owner, where the original contractor has waived all liens, or all liens have been released subsequent to the date of the contract, would be to deprive the owner of his property without due process of law, as it would prevent the owner from máking such contract with reference to his property as he might see fit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dunlop v. McAtee
333 N.E.2d 76 (Appellate Court of Illinois, 1975)
Jankoviak v. Butcher
159 N.E.2d 377 (Appellate Court of Illinois, 1959)
Douglas Lumber Co. v. Chicago Home for Incurables
43 N.E.2d 535 (Illinois Supreme Court, 1942)
Walker v. Collins Construction Co.
236 N.W. 334 (Nebraska Supreme Court, 1931)
General Motors Acceptance Corp. v. Goldboges
260 Ill. App. 474 (Appellate Court of Illinois, 1931)
McNulty v. White
242 Ill. App. 37 (Appellate Court of Illinois, 1926)
Bassett v. Carpenter
220 P. 1028 (Supreme Court of Kansas, 1923)
McMillan v. Joseph P. Casey Co.
231 Ill. App. 422 (Appellate Court of Illinois, 1923)
Herman H. Hettler Lumber Co. v. Hodge
227 Ill. App. 383 (Appellate Court of Illinois, 1923)
People v. Holder
199 P. 832 (California Court of Appeal, 1921)
Baldwin Locomotive Works v. Edward Hines Lumber Co.
125 N.E. 400 (Indiana Supreme Court, 1919)
North Side Sash & Door Co. v. Goldstein
121 N.E. 563 (Illinois Supreme Court, 1918)
Henry Marble Co. v. Church
205 Ill. App. 249 (Appellate Court of Illinois, 1917)
Interstate Contracting & Supply Co. v. Belleville Savings Bank
197 Ill. App. 30 (Appellate Court of Illinois, 1915)
Rittenhouse & Embree Co. v. Warren Construction Co.
264 Ill. 619 (Illinois Supreme Court, 1914)
Rittenhouse & Embree Co. v. William Wrigley, Jr., Co.
264 Ill. 40 (Illinois Supreme Court, 1914)
Dupuis v. Snook
186 Ill. App. 330 (Appellate Court of Illinois, 1914)
Stewart v. Talbott
146 P. 771 (Supreme Court of Colorado, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
95 N.E. 1068, 251 Ill. 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-v-johnson-ill-1911.