Woodcrest Homes, Inc. v. First National Bank of Pueblo (In Re Woodcrest Homes, Inc.)

11 B.R. 342, 1981 Bankr. LEXIS 3713
CourtUnited States Bankruptcy Court, D. Colorado
DecidedMay 20, 1981
Docket19-10926
StatusPublished
Cited by3 cases

This text of 11 B.R. 342 (Woodcrest Homes, Inc. v. First National Bank of Pueblo (In Re Woodcrest Homes, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodcrest Homes, Inc. v. First National Bank of Pueblo (In Re Woodcrest Homes, Inc.), 11 B.R. 342, 1981 Bankr. LEXIS 3713 (Colo. 1981).

Opinion

MEMORANDUM OPINION, FINDINGS OF FACT, CONCLUSIONS OF LAW AND ORDER DETERMINING LIENS

GLEN E. KELLER, Jr„ Bankruptcy Judge.

Plaintiff seeks a determination of the validity, extent, and priority of Defendants’ interest in its real property. The Defendant Martin Trenching and Excavating has counterclaimed for an order declaring it to have a valid mechanic’s lien in the amount of $295,692.79 and permitting foreclosure thereof. The matter is before the Court largely upon stipulated facts, a brief recitation of which is important to the understanding of the legal issues.

In 1978, the Plaintiff, Woodcrest Homes, Inc., began to develop a residential subdivision in Pueblo, Colorado. In July, the City of Pueblo approved the subdivision plat and, in doing so, accepted Woodcrest’s dedication of the subdivision streets to the public for its perpetual use and benefit. Martin agreed in September to perform certain work and immediately began to lay the water and sewer lines and complete the necessary excavation. The various water and sewer lines were installed both within and outside the geographic boundaries of the subdivision. Some of the lines within the subdivision were located under the previously dedicated streets, while others were situated in utility easements on Woodcrest’s property. Woodcrest paid Martin $75,-750.00 on January 9, 1979. On the 9th of May, $90,000.00 was paid, and on the 21st of May, Martin received a check from Plaintiff for $45,000.00. Much of the work was completed by August, 1979. Martin sent Wood-crest a bill for $295,692.79, reflecting the total amount then due. That invoice was never paid, and Martin took steps to establish and foreclose a mechanic’s lien on the Woodcrest property under the General Mechanic’s Lien Statute, §§ 38-22-101 et seq., C.R.S. 1973. Before foreclosure could be obtained, however, a petition under Chapter 11 of Title 11, United States Code, was filed with this Court, effectively staying further action by Martin. In the course of administering Debtor’s estate, a sale free and clear of all liens was authorized, and the entire subdivision was sold to a third party. From the sale, Woodcrest received $100,000.00 in cash and a note for the balance of $865,-000.00. Of that $100,000.00, pursuant to all lien claimants’ stipulation, Martin was paid $77,327.25.

Woodcrest advances two arguments in opposition to Martin’s alleged mechanic’s lien. The first is that Martin has waived its right to a mechanic’s lien for all work completed prior to May 23, 1979, when Martin received its last payment from Woodcrest. This is based on Martin’s apparent execution of two lien waivers located on the backs of the May 9th and May 21st checks. The second argument is that much of the work done was not lienable under the statute.

*344 The lien waivers were stamped forms and provided as follows:

Endorsement and negotiation of the within check constitutes an irrevocable waiver of all mechanic’s liens rights for material and/or labor furnished and/or performed for the construction of improvements on the following described property to date of such negotiation. Street Address: Bellview, First and Second Filing
Owner: Woodcrest Homes, Inc. Being in the City of Pueblo, County of Pueblo, State of Colorado.

Whether the above language is effective as a waiver of Martin’s pre-May 23rd lien rights must be determined. It is clear that the right to a mechanic’s lien can be waived in Colorado. See § 38-22-119 C.R.S. 1973 and Bishop v. Moore, 137 Colo. 263, 323 P.2d 897 (1958). However, if the waiver is to be enforceable, consideration is required. See, e. g., Pierson v. Sewell, 97 Idaho 38, 539 P.2d 590 (1975); Kelly v. Johnson, 251 Ill. 135, 95 N.E. 1068 (1911); Sussel Company v. First Federal Savings and Loan Association, 304 Minn. 433, 232 N.W.2d 88, aff’d, 307 Minn. 199, 238 N.W.2d 625 (1975); Skidmore v. Eby, 57 N.M. 669, 262 P.2d 370 (1953). Colorado authority on this point appears to be in accord. See Western Federal Savings and Loan Association v. National Homes Corporation, 167 Colo. 93, 445 P.2d 892 (1968). In the Western Federal case, the Colorado Supreme Court overturned a lower court ruling that certain lien waivers were unenforceable for want of consideration. The Court found that the voluntary agreement of the lender to continue financing a financially troubled joint venture was adequate consideration to support lien waivers executed by a. joint ven-turer who had supplied materials.

A lien waiver may be enforceable even without consideration if an estoppel can be shown. The owner or lender must show that he materially changed his position in justifiable reliance upon the lien waiver executed by the claimant. See, e. g., Giammarino v. J.W. Caldewey Construction Company, 72 S.W.2d 159 (Mo.App. 1934). This principle has recently been approved in Colorado. In Mountain Stone Company v. H.W. Hammond Company, 39 Colo.App. 58, 564 P.2d 958 (1977), it was held that where a subcontractor advised an owner in writing that he had been paid in full and the owner proceeded, to disburse funds to the contractor in reliance upon the representation, the waiver was enforceable without finding specific consideration. The Court quoted the following language from McLellan v. Hamernick, 264 Minn. 345, 118 N.W.2d 791 (1962):

The owner of the property was entitled to protect himself from liens against his property by requiring lien waivers before he paid the balance due the contractor. If those furnishing material and labor were willing to execute such lien waivers, relying upon the contractor’s promise to pay them, they should not be heard to complain after the homeowner has altered his position in reliance on such waivers. Any other rule would render lien waivers valueless.

Applying these principles to the case at hand, The Court must find either consideration for the lien waivers or an estoppel. Clearly, the payments made by the May 9th and May 21st checks cannot be consideration since Woodcrest was merely doing that which it was legally obliged to do. Beebe Construction Corporation v. Circle R Company, 10 Ohio App.2d 127, 226 N.E.2d 573 (1967). In Beebe, it was held that a waiver executed in consideration of payments the owner was legally required to make was not a bar to the assertion of a lien for any amount remaining unpaid. Woodcrest argues that the checks are consideration for the waiver because they were issued prior to the completion by Martin of its duties under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
11 B.R. 342, 1981 Bankr. LEXIS 3713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodcrest-homes-inc-v-first-national-bank-of-pueblo-in-re-woodcrest-cob-1981.