Douglas Lumber Co. v. Chicago Home for Incurables

43 N.E.2d 535, 380 Ill. 87
CourtIllinois Supreme Court
DecidedMay 13, 1942
DocketNo. 26489. Decree affirmed.
StatusPublished
Cited by29 cases

This text of 43 N.E.2d 535 (Douglas Lumber Co. v. Chicago Home for Incurables) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Douglas Lumber Co. v. Chicago Home for Incurables, 43 N.E.2d 535, 380 Ill. 87 (Ill. 1942).

Opinion

Mr. Chief Justice Murphy

delivered the opinion of the court:

Plaintiff, Douglas Lumber Co., began this action in the circuit court of Cook county to foreclose a mechanic’s lien for material furnished by it in construction and repair work on a building located at 125-127 West Monroe street, Chicago. The defendants are the Chicago Home for Incurables, the owner of the premises, Down Town Auto Parking Co., its lessee, Down Town Parking Stations, Inc., sublessee, Edwin E. Hartrich, the contractor, and L. A. Gorman Co. Inc., the subcontractor and the one to whom plaintiff furnished the material in question. After the taking of a large amount of evidence before the master, and the overruling of exceptions to the master’s report, a decree was entered in favor of plaintiff. All the defendants except the subcontractor, L. A. Gorman Co.,.Inc., have joined in this appeal. A direct appeal to this court is supported by the claim that section 21 of the Mechanic’s Lien act as amended in 1913 (111. Rev. Stat. 1941, chap. 82, par. 21) is unconstitutional.

The facts are that early in 1938 the Down Town Auto Parking company entered into a written contract with Hart-rich as general contractor to remodel a building then situated on the property and convert it from a bank building to a three-story reinforced concrete garage with a concrete ramp leading from the floor on the street level to the roof, thus permitting the parking of automobiles on three floors and the roof. The owner of the property gave its consent to the remodeling of the building. On March 22, 1938, the contractor, Hartrich, sublet the reinforced concrete work to L. A. Gorman Co., Inc., under a written contract. The regular contract and the subcontract contained similar provisions regarding monthly payments to be made on account of the contract price. They provided that there should be paid at the end of each period 85% of the value of the work in place as estimated by the architect.

Plaintiff sold building materials to the subcontractor, the Gorman company, consisting principally of crushed stone, sand, cement and lumber. The stone, sand and cement were used by the subcontractor in the concrete work and the lumber was used in the making of forms in the concrete construction.

The contention of defendants that plaintiff executed a release of lien necessitates a brief statement of the facts in reference to the circumstances surrounding the execution of two instruments, one dated July 30, 1938, the other September 1, 1938. The monthly requisition dated August 2, 1938, submitted by the Gorman company to Hartrich asked for the payment of $10,276.50 which was estimated to be 85% of the value of the work then completed. This requisition was accompanied by an instrument executed by plaintiff, which recited that the plaintiff “does hereby waive and release any and all lien or claim or right of lien on said above building [125 West Monroe street] and premises under the Statutes of the State of Illinois relating to Mechanic’s liens on account of labor or materials, or both, furnished by the undersigned to or on account of the said L. A. Gorman Company, for said building or premises.” Contractor Hartrich submitted the Gorman company requisition, plaintiff’s waiver of lien and his own monthly requisition to the owner for payment. The full amount of the Gorman company requisition was not paid by Hartrich to the company. August 6, Hartrich paid $7000 and on August 26, $1000, leaving $2276.50 of the Gorman company requisition unpaid. In turn the Gorman company failed to pay plaintiff in full for the materials delivered by it for the period ending July 30, 1938, being the period covered by the waiver of lien.

The second waiver of lien was executed and delivered under the following conditions. The requisition for monthly payment presented by Gorman on or about September 1, 1938, was $18,435. The master found, and the finding is supported by the evidence, that the plaintiff was unwilling to execute another waiver of lien for the reason it had not received the balance due July 30. It was delivered to the Gorman company on the express condition that it would not be delivered to Hartrich unless Hartrich paid the Gorman company the requisition in full. Louis A. Gorman, of the Gorman company, testified that when he delivered plaintiff’s waiver to Hartrich he explained to him the condition of its delivery and told Hartrich he had not paid the plaintiff for the materials covered by the waiver, and that he would be unable to do so unless his. requisition was paid in full and that if it was not paid in full, plaintiff’s waiver should be returned to him as he had no authority to deliver it except that full payment be made. There was a controversy between the Gorman company and Hartrich as to the amount due on the second requisition. However, in the requisition which Hartrich submitted under his general contract he set forth the value of the work then performed by the Gorman company at substantially the same figure as that stated in the Gorman company requisition. The architect approved the Hartrich requisition without deduction and caused payment to be made on that basis. Instead of paying the $18,435 due on the Gorman company requisition, Hartrich paid $11,000. Louis A. Gorman testified that he refused the money and asked that plaintiff’s waiver of lien be returned to him, that Hartrich told him the waiver had been delivered to the owner and could not be returned. The Gorman company then accepted the payment of $11,000. Hartrich denied any conversation in regard to the conditional delivery. The evidence discloses that Hartrich received $2790.52 on his requisition for work covered by the Gorman company in excess of the amount paid to the Gorman company for the same work. This amount was subsequently paid to the Gorman company and that company paid plaintiff $2000, which sum was less than the amount remaining due on the July 30 statement.

On December 6, 1938, plaintiff served notice of his claim for lien and within four months from the date on which the final payment became due, this action was instituted.

It was stipulated that the owners are indebted to Hart-rich under his contract with them more than the amount of plaintiff’s claim. There is no claim that the work was not completed according to contract or that the Gorman company work was not satisfactory.

After overruling exceptions to the master’s report, a decree was entered in favor of plaintiff, as follows: (a) A judgment as at common law against L. A. Gorman Co., Inc., for $9027.59; (b) a prior lien upon the real estate involved for $3750.44 with interest at 5% from December 10, 1938, to the date of the master’s report, October 5, 1940, a total of $4097.08, and ordered foreclosure of such lien; (c) a prior lien upon the money due Hartrich from the Chicago Home for Incurables and the Down Town Auto Parking company, or one of them, on Hartrich’s contract in the sum of $7144.85, with interest from December 10, 1938, to the date of report, a total of $7794.83. The decree contains a finding that there is due Hartrich, but still held by the owners, more than sufficient to pay plaintiff’s claim. This judgment was ordered to be satisfied pro tanto to the extent and in the amount plaintiff received on the foreclosure of the lien on the real estate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman A. Koglin Associates v. Valenz Oro, Inc.
680 N.E.2d 283 (Illinois Supreme Court, 1997)
Premier Electrical Construction Co. v. American National Bank
658 N.E.2d 877 (Appellate Court of Illinois, 1995)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
Kupferschmid, Inc. v. Rodeghero
488 N.E.2d 305 (Appellate Court of Illinois, 1986)
Martinez v. Knochel
462 N.E.2d 1281 (Appellate Court of Illinois, 1984)
Federal Savings & Loan Insurance v. American National Bank & Trust Co.
450 N.E.2d 820 (Appellate Court of Illinois, 1983)
Fed. Sav. & Ln Ins. v. Am. Nat'l Bk & Tr.
450 N.E.2d 820 (Appellate Court of Illinois, 1983)
C. S. Lewis, Inc. v. Cabot Corp.
407 N.E.2d 84 (Appellate Court of Illinois, 1980)
Bethlehem Steel Corp. v. Tishman-Adams, Inc.
360 N.E.2d 475 (Appellate Court of Illinois, 1977)
Dunlop v. McAtee
333 N.E.2d 76 (Appellate Court of Illinois, 1975)
Excellent Builders, Inc. v. Pioneer Trust & Savings Bank
305 N.E.2d 273 (Appellate Court of Illinois, 1973)
Warren v. Bill Ray Construction Co., Inc.
269 So. 2d 25 (District Court of Appeal of Florida, 1972)
Drost v. Professional Building Service Corp.
286 N.E.2d 846 (Indiana Court of Appeals, 1972)
City of Evanston v. Risinger
253 N.E.2d 918 (Appellate Court of Illinois, 1969)
Nevada Equities, Inc. v. Willard Pease Drilling Co.
440 P.2d 122 (Nevada Supreme Court, 1968)
In Re H. G. Prizant & Co.
257 F. Supp. 145 (N.D. Illinois, 1965)
D. D. Kennedy, Inc. v. Lake Petersburg Ass'n
203 N.E.2d 145 (Appellate Court of Illinois, 1964)
Pascal P. Paddock, Inc. v. Glennon
203 N.E.2d 421 (Illinois Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
43 N.E.2d 535, 380 Ill. 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/douglas-lumber-co-v-chicago-home-for-incurables-ill-1942.