VonPlaten v. Winterbotham

203 Ill. 198
CourtIllinois Supreme Court
DecidedJune 16, 1903
StatusPublished
Cited by24 cases

This text of 203 Ill. 198 (VonPlaten v. Winterbotham) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VonPlaten v. Winterbotham, 203 Ill. 198 (Ill. 1903).

Opinion

Mr. Justice Cartwright

delivered the opinion of the court:

The appellants VonPlaten & Dick filed in the superior court of Cook county their petition for a mechanic’s lien on an apartment house and lot in Chicago, as sub-contractors, against the appellees, Amelia E. Winterbotham, owner of the premises, and W. J. Reynolds, the original contractor; and the appellant the T. Wilce Company, a corporation, filed its intervening petition for a lien on the same premises as a sub-contractor under Reynolds. The petition and intervening petition having been answered and replications filed, the issues were referred to a master in chancery, who took and reported the evidence, with his conclusion that neither the petitioners nor the intervening petitioner were entitled to liens, and he recommended that both petitions be dismissed for want of equity. The court heard the cause on exceptions to the master’s report, and they were overruled and the petitions were dismissed. The Appellate Court for the First District affirmed the decree.

The original petition alleged that prior to August 3, 1898, the defendant Amelia E. Winterbotham entered into a contract with W. J. Reynolds for the erection of an apartment building, and agreed to pay him a large sum of money, the exact amount of which and other terms of the contract being unknown to petitioners; that on said day petitioners contracted with Reynolds to furnish the mill work; that no specific time was_set for the completion of their contract, which was made by a written proposition and acceptance, but a reasonable time, to-wit, within one year, was implied, payments to be made as deliveries progressed and final payment on the completion of delivery, and that tie original contract and sub-contract were performed. The intervening petition of the T. Wilce Company alleged that on April 4, 1898, W. J. Reynolds made a written contract with Amelia E. Winterbotham, the owner, for the carpenter work of an apartment building on the premises, for a consideration of §12,776; that on September 15, 1898, Reynolds entered into a parol contract with said company, whereby it was to furnish the hardwood flooring, and that said contract was performed prior to November 1, 1898. To the intervening petition was annexed a copy of the original contract between W. J. Reynolds and Amelia E. Winterbotham for the carpenter work on the building, to be performed on demand of the architect, so as to cause no delay in completing the building. The petition and intervening petition averred notice and the necessary facts in case the contracts created liens under the statute.

The findings of fact by the master, adopted by the court and recited in the decree, are to the effect that Amelia E. Winterbotham, on April 4, 1898, entered into a contract with W. J. Reynolds to do the carpenter work in the construction of the building; that the petitioners, VonPlaten & Dick, on August 3, 1898, entered into a contract in writing with Reynolds to deliver and furnish the mill work for $4000; that petitioners furnished and delivered substantially all the mill work, and that there remained unpaid therefor $1335.50; that Reynolds and petitioners substantially completed their respective contracts, and that petitioners served notice of the lien on the owner in due time, on October 25, 1898. The findings in reference to the T. Wilce Company were, that on March 31, 1898, Reynolds entered into a contract with said company to furnish the hardwood flooring for the building at such times and places as should be required by him, the implied time being'within the space of one year; that the company delivered the materials by October 5, 1898, of the total value of $1122, and after deducting items of expense and the value of material returned, the amount due was $1100.18, and that notice of a lien was duly served.

The master stated in his report that he based his conclusion that the law did not allow liens to the petitioners or intervening petitioner upon the fact that no specific time was fixed in either of the sub-contracts for the performance of the same or for payment. This was a conclusion of law from the facts. The petitioners and the intervening petitioner each filed exceptions to the conclusion of the master on the question of law, and the exceptions were overruled by the court, and the same reason for dismissing the petitions and denying liens was stated in the decree. The exceptions as to the legal conclusion of the master were neither necessary nor proper. Where the master states the facts correctly, it is not necessary for one who claims that the master is mistaken as to the legal consequences of the facts to except to the report. Exceptions relate to matters of fact, and the question whether the master has drawn an incorrect legal conclusion from the facts will be heard without exceptions. (2 Daniell’s Ch. Pr. sec. 1310; Hurd v. Goodrich, 59 Ill. 450; Hayes v. Hammond, 162 id. 133.) It is also immaterial what reason the court stated in the decree for rendering it, if the facts stated therein lead, as a matter of law, to the same conclusion. An appellate court will not reverse a decree which correctly pronounces the judgment of the law upon the facts because an improper reason is given for the conclusion. A decree which is correct in the law should be affirmed, whether the reasons recited in it, which are no essential part of the decree, are correct or not.

We have not held that.a mechanic, workman or material-man under an original contractor must enter into a contract specifying a time for performance and payment, as in the case of an original contractor with the owner, but we decided in Williams v. Rittenhouse & Embree Co. 198 Ill. 602, that where the original contract did not comply with, the requirements of the statute, without which no lien could be had by virtue of the act, there would be no lien in favor of a sub-contractor. We did not decide in that case, as contended by counsel for appellees, that the Rittenhouse & Embree Company had no lien because their contract with Stevens & Sherbrook, the principal contractors, fixed no time for the completion of the subcontract or for final payment. Stevens & Sherbrook were the original contractors for the carpenter and mill work under a verbal contract which did not specify a time for performance or payment, and the Rittenhouse & Embree Company entered into a verbal contract with Stevens & Sherbrook to furnish the lumber. The entire discussion in the opinion related to the question whether the Stevens & Sherbrook contract was sufficient to create any liens under the act. We referred to section 6 of the Mechanic’s Lien law, and held that, inasmuch as the contract did not fix the times for performance and payment, there was no lien, by virtue of the law, to either of the parties. That decision must be regarded as inconsistent with what was said in Keeley Brewing Co. v. Neubauer Decorating Co. 194 Ill. 580, to the effect that the lien of a sub-contractor is not subordinate to that of the original contractor or dependent upon the fact that the original contract authorizes a lien.

The right to establish mechanics’ liens against property is created by a single act of a comprehensive nature embracing all liens of that nature, and entitled “An act to revise the law in relation to mechanic’s liens.” (Laws of 1895, p. 225.) The right to a lien arises out of a contract between the owner of the premises to be charged with the lien, or one whom such owner has authorized or knowingly permitted to improve the same, and a contractor for the improvement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cordeck Sales, Inc. v. Construction Systems, Inc.
917 N.E.2d 536 (Appellate Court of Illinois, 2009)
Shaffer v. Cullerton Corp.
141 N.E.2d 77 (Appellate Court of Illinois, 1957)
Robertson v. Huntley & Blazier Co.
115 N.E.2d 533 (Appellate Court of Illinois, 1953)
Buster v. Chicago, M., St. P. & P. R. Co
195 F.2d 73 (Seventh Circuit, 1952)
Douglas Lumber Co. v. Chicago Home for Incurables
43 N.E.2d 535 (Illinois Supreme Court, 1942)
Rosehill Cemetery Co. v. City of Chicago
185 N.E. 170 (Illinois Supreme Court, 1933)
George Green Lumber Co. v. Fendl
246 Ill. App. 132 (Appellate Court of Illinois, 1927)
Pittsburgh Plate Glass Co. v. Kransz
125 N.E. 730 (Illinois Supreme Court, 1919)
Pittsburgh Plate Glass Co. v. Huberty
213 Ill. App. 315 (Appellate Court of Illinois, 1919)
Interstate Contracting & Supply Co. v. Belleville Savings Bank
197 Ill. App. 30 (Appellate Court of Illinois, 1915)
Rittenhouse & Embree Co. v. Warren Construction Co.
264 Ill. 619 (Illinois Supreme Court, 1914)
Dupuis v. Snook
186 Ill. App. 330 (Appellate Court of Illinois, 1914)
Elgin, Joliet & Eastern Railway Co. v. Northwestern National Bank
165 Ill. App. 35 (Appellate Court of Illinois, 1911)
Schaller-Hoerr Co. v. Gentile
153 Ill. App. 458 (Appellate Court of Illinois, 1910)
Weidle v. Elgin, Joliet & Eastern Railway Co.
152 Ill. App. 292 (Appellate Court of Illinois, 1910)
Miller v. Benson
146 Ill. App. 132 (Appellate Court of Illinois, 1908)
Central Illinois Construction Co. v. W. W. Brown Construction Co.
137 Ill. App. 532 (Appellate Court of Illinois, 1907)
Gillett v. Chicago Title & Trust Co.
82 N.E. 891 (Illinois Supreme Court, 1907)
Merritt v. Crane Co.
80 N.E. 103 (Illinois Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
203 Ill. 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vonplaten-v-winterbotham-ill-1903.