George Green Lumber Co. v. Fendl

246 Ill. App. 132, 1927 Ill. App. LEXIS 261
Appellate Court of Illinois·Decided October 19, 1927·No. Gen. No. 31,493·Published·Cited by 1 cases

Opinion

Mr. Presiding Justice Taylor

delivered the opinion of the court.

This is an appeal by the defendants from a decree granting the petitioner, George Green Lumber Company, a mechanic’s lien in the sum of $599.47.

The defendants, Arthur C. Taylor and Reniee Taylor, his wife, were owners in fee of certain real estate in Cook county, known as Lot 225 Downing’s Subdivision. On August 6, 1924, they conveyed it by trust deed to the defendant, Union Trust Company of Chicago to secure certain notes and interest. On July 12, 1924, the Taylors and the defendant, Fendl, entered into a written contract whereby Fendl was to repair and remodel the buildings on the property for $4,100. The contract provided that $200 should be paid down, 90 per cent paid as the work progressed, and the “balance to be paid when the work is completed.” On July 17, 1924, the petitioner, who is here suing as a subcontractor, entered into an agreement with Fendl, the original contractor, to furnish to the property in question certain specified items of lumber and material. The terms of their agreement were contained in a letter of the petitioner to Fendl. As to payment, it contained the following, “Terms payable within 60 days from date of last material.” The master found that it was agreed between them that the price of the material should be $875, payable 60 days from the date of the last delivery; that between July 28 and October 15, 1924, the petitioner had delivered material, the charge for which was $639.74; that owing to certain agreed upon charges, all the estimated material was not delivered; that in the course of performance by the petitioner, at the request of Fendl, the petitioner delivered $256.53 of extra material which it was agreed should be paid for within 60 days after final delivery; that the total amount to be paid by Fendl to the petitioner was $866.27; that Fendl made certain payments to the petitioner, leaving a balance due of $599.47; that the petitioner fully completed its deliveries and contract with Fendl on October 15, 1924.

On December 11, 1924, the petitioner served a notice of a claim for a mechanic’s lien on the Taylors. That notice contained the following:

“And that beginning with the 28th day of July, 1924, and concluding with the 15th day of October, 1924, we furnished and delivered to said premises upon the orders of said John Fendl * * * material of the * * * value of $872.58; of which said sum there has remained due and owing to us an unpaid balance of $599.47, since the 15th day of October, 1924, and that we will hold said premises * * * liable therefor,”

The master, also, found that on November 5, 1924, Fendl drew a superintendent or architect’s certificate addressed to the Union Trust Company of Chicago, by which said John Fendl certified that the complainant was entitled to payment in the sum of $483.87 for the lumber and millwork delivered to said premises and used on the same in and about making said alterations, improvements, additions and that said certificate Was on or about the same date thereof presented to Arthur C. Taylor and Reniee Taylor, his wife, who wrote their indorsements on the same and directed the Union Trust Company, to pay to said George Green Lumber Company, $483.87; that said sum was never paid to the petitioner.

The master found that, although the last of the material was delivered by the petitioner on October 15, 1924, and the notice of a claim for lien was served on the Taylors on December 11, 1924,. and the petition for a lien was filed on April 13, 1925, more than four months — the time fixed by section 33 of the Lien Act — after the last material was delivered by the petitioner, nevertheless, by reason of the terms of the. contract between Fendl and the petitioner, the purchase price of the material sold by the petitioner to Fendl did not become due until 60 days after October 15, 1924, the date of the last delivery, that is, until December 15, 1924, and that the statement in the notice of December 11, 1924, that there remained an unpaid balance of $599.47 since October 15, 1924, in no way affected the 60 days provided for in the agreement between Fendl and the petitioner, or its rights against the owners, and that the petitioner had the right to file its petition, as it did, on April 13, 1925, being less than four months after December 15, 1924, because it was within four months “after the time the final payment” was due the petitioner, that is, was due the “contractor or laborer or party furnishing the material.” (Section 33 of Lien Act, Cahill’s St. ch. 82, ¶ 33.)

The only notice given by Fendl, in the course of the fulfillment of his contract, as to work and materials furnished by the petitioner, and as to amounts, was served on August 26, 1924, on the Union Trust Company, for the purpose of procuring from the latter certain payments, on account of the owners. It recited, among other things, that the petitioner had furnished material at a charge of $705, and had been paid $265.

Free access — add to your briefcase to read the full text and ask questions with AI

George Green Lumber Co. v. Fendl, 246 Ill. App. 132, 1927 Ill. App. LEXIS 261 (Ill. Ct. App. 1927).

246 Ill. App. 132 (George Green Lumber Co. v. Fendl) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Material Service Corp. v. Ford
250 Ill. App. 373 (Appellate Court of Illinois, 1928)