Schaller-Hoerr Co. v. Gentile

153 Ill. App. 458, 1910 Ill. App. LEXIS 985
Appellate Court of Illinois·Decided March 31, 1910·No. Gen. No. 14,965·Published·Cited by 9 cases

Opinion

Mr. Justice Freeman

delivered the opinion of the court.

Schaller-Hoerr Company filed a petition seeking a mechanic’s lien upon property therein described owned by the defendants, claiming to have furnished material used in the construction of a building upon said premises. The building was erected under a written contract by one John T. Vitullo. The appellant, Frank Scaar & Company, answered the original petition and by an intervening petition prayed for a lien in its own behalf for materials by it furnished and used in the erection of the building. The original -contract made by defendant, Michelo Gentile, owner of the premises, with John T. Vitullo, the contractor, is dated July 8, 1905. By its terms Vitullo agreed to furnish all necessary materials and to erect the building in accordance with “the draft, plans, explanations and specifications” annexed to the contract. The original price was fixed at $2,500, the last payment to be made “upon completion of work and the owner to be well satisfied that the building is free from any lien or any other unpaid bills and that the building is erected according to the plans” attached. The agreement was subsequently modified and the plans changed to include additional improvements. In his answer the contractor, Vitullo, alleges the amount due for the erection of the building to have been $5,277, of'which he was paid $4,014.56; that other sums to the amount of $619.50 were paid by said owner to subcontractors and that $644.06 is still due the original contractor.

It is urged in behalf of defendants that the rights of the subcontractors, complainants herein, were affected by the terms of the original contracts of which they are presumed to have had notice, which contracts it is claimed contained -an agreement by the original contractor to the effect that the .building was to be free from any lien. It is -contended by complainants however that the right of a subcontractor to a lien “is not dependent upon the right of the original contractor to have one,” citing Wood v. Gumm, 67 Ill. App. 518-522. The contracts in this case, original and modified, were made after the Mechanic’s Lien Law of 1903 was in force. By section 35 (21) of that law (R. S. Chap. 82), it is provided that every subcontractor shall have a lien for material or labor furnished for the contractor on the moneys or other consideration due or to become due from the owner under the original contract, “whether or not the original contractor could have obtained a lien on was by contract or conduct divested or deprived of a right to obtain a lien.” If this provision as it now stands is valid, a subcontract tor may not now be deprived of a lien by reason of provisions of the original contract between the owner and the principal contractor. Section 22 of the. Mechanic’s Lien Law of 1895 did not contain the same provision. R. S. 1899, chap. 82, sec. 36 (22). In Keeley Brewing Co. v. Decorating Co., 194 Ill. 580-593, it was said that “the lien of the subcontractor being a direct lien, its existence does not depend upon the existence or non-existence of a contractor’s lien.” In that respect however that case has been overruled in Von Platen v. Winterbotham, 203 Ill. 198-203. The case of Brown Const. Co. v. Cent. Ill. Const. Co., 234 Ill. 397-401, was “brought under the Act in reference to liens upon railroads,” not now in question. But the construction there given (p. 402) of Von Platen v. Winterbotham is “that the right of the subcontractor to enforce a lien is barred whenever the contract entered into by the owner contains an agreement that there shall be no lien.” In the Von Platen case it was said: “It is not to be presumed that the legislature intended to restrict or abridge the right of contract which the owner has, and to give a lien to a subcontractor, where the terms of the only contract to which the owner is a party are such that no lien can arise or in spite of an agreement that there shall be no lien.” The contract in that case was under the lien law of 189.5. Since that decision the Mechanic’s Lien Law of 1903 has been enacted and in it the provision herein-above quoted has been inserted, seeming to indicate that the legislature did intend thereby “to restrict or abridge the right of contract” in that respect, without regard to whether such attempted abridgement shall ultimately bp deemed constitutional or not. Its constitutionality hówever is not for this court to consider. It is our duty to follow the statute while it remains in force, and under it the subcontractor is given a lien “whether or not the original contractor could have obtained a lien or was by contract or conduct divested or deprived of a right to obtain a lien.”

It is contended in behalf of petitioner, Schaller-Hoerr Company, that the only question as to its right to a lien is, was the notice served upon defendant within the sixty days allowed by the statute. There is evidence tending to show that said petitioner’s last delivery of material for the building in controversy was upon November 15, 1905. If such is the fact, then the notice served upon the owner January 13, 1906, was within sixty days thereafter. The master however found that the petitioner’s claim in this respect is not sustained by the evidence. The remedy sought by appellant is purely statutory and the burden is on the petitioner “to prove on the hearing that he had complied with the statutory conditions precedent to his right to enforce the lien.” Crandall v. Lyon, 188 Ill. 86-91. The master finds that the materials claimed to have been delivered November 15th were in fact put into the building at least five days before that date. There is evidence which justifies the master’s conclusion and the court’s decree. In any event a careful scrutiny of the evidence makes it clear that petitioner has failed to make satisfactory proof, the burden of which was his, that the final delivery in question was made upon the date claimed and not prior thereto; has failed therefore to prove compliance on his part with the statutory requirement as to the sixty days’ notice, without which proof he is not entitled to the lien as claimed.

Free access — add to your briefcase to read the full text and ask questions with AI

Schaller-Hoerr Co. v. Gentile, 153 Ill. App. 458, 1910 Ill. App. LEXIS 985 (Ill. Ct. App. 1910).

153 Ill. App. 458 (Schaller-Hoerr Co. v. Gentile) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership
731 N.E.2d 394 (Appellate Court of Illinois, 2000)
J&K Cement Construction, Inc. v. Montalbano Builders, Inc.
456 N.E.2d 889 (Appellate Court of Illinois, 1983)
Capital Plumbing & Heating Co. v. Snyder
275 N.E.2d 663 (Appellate Court of Illinois, 1971)
Roth v. Lehman
116 N.E.2d 413 (Appellate Court of Illinois, 1954)
Alexander Hendry Co. v. Mooar
242 Ill. App. 516 (Appellate Court of Illinois, 1926)
Holmes v. S. H. Kress & Co.
1924 OK 25 (Supreme Court of Oklahoma, 1924)
Patterson v. Denton
201 Ill. App. 382 (Appellate Court of Illinois, 1916)
People ex rel. State Board of Health v. Powella
176 Ill. App. 603 (Appellate Court of Illinois, 1913)